Liquidated_Damages_Construction.pdf

PDF 47 KB Posted

Attached to
Recapture Basement - Zorinsky
Solicitation number
GS-06P-15-TC-P-7003
Issued by

About this file

Liquidated Damages Clause

View the file

Other files

File Type Posted
CONSTRUCTION_CONTRACT_CLAUSES.pdf PDF
Wage_Determination.pdf PDF
Combined_Specifications.pdf PDF
SF18_-_Request_for_Quotation.pdf PDF
The_Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FAR 52.211-11 – Liquidated Damages – Construction

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $140.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.