Additional Questions Received 8-11.pdf
PDF 14 KB Posted
- Attached to
- Boiler Replacement Project
- Solicitation number
- GS-03P-09-AZ-C-0004
About this file
Additional Questions Received
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ALL QUESTIONS.pdf | ||
| BMS Contractor.pdf | ||
| Amendment 0003.pdf | ||
| Additional Questions Received 40-51.pdf | ||
| Additional Question 28.pdf | ||
| Additional Questions 35-39.pdf | ||
| Site Visit 3.pdf | ||
| SF 24 Bid Bond.pdf | ||
| Additional Questions Received 17-34.pdf | ||
| FINAL QUESTIONS SUBMISSION.pdf | ||
| Site Visit 2.doc | DOC document | |
| Additional Questions 15 16.pdf | ||
| Additional Questions 12-14.pdf | ||
| Completed Pre proposal Questions Answers.pdf | ||
| Pre Proposal Minutes.pdf | ||
| Amendment 0002.pdf | ||
| Site Visit.pdf | ||
| Amendment 0001.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Additional Questions Received #8-11
8.) Will a copy of the sign in sheet be available for review?
Response: Yes, the sign in sheet will be posted on FedBizzOpps.
9.) Please confirm the roof area outside the boiler mechanical room is available as a lay down area; advise of any precautions or concerns.
Response:
See answer to question (7). The roofing shall be protected by temporary covering so as to prevent damage during equipment lifts and lay downs. Multiple boiler lay downs on the roof at the same time shall not be permitted.
10.) Concerning the asbestos on the breeching. Is the General Contractor (Division #1) carrying this remediation cost or is this included in the mechanical specialty contractors cost?
Response: The cost of asbestos remediation shall be included in the price from all offerors. The asbestos abatement is part of this contract whether the prime contractor or a sub consultant performs the work is up to each offeror. The abatement firm must meet the qualifications listed in the abatement specification which was created by The Oak Group Inc. This specification is posted to FedBizzOpps as a separate document from VECSIE’s boiler replacement specification
11.) Regarding the Electrical work to be performed on this project, is it Mandatory for the Electrical Contractor to be in possession of a “City of Philadelphia” Electrical License?
Response: All contractors performing work must be licensed in the jurisdiction where the work is to be performed.