Text version

project manual:

Burlington Court Reconfiguration Project

Burlington Federal Building USPO and Courthouse

11 Elmwood Avenue Burlington, VT 05401

Building No. VT0024ZZ

GSA-4068

May 23, 2017

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice Properly destroy documents when no longer needed

Burlington Court Reconfiguration Project Burlington Federal Building USPO and Courthouse, 11 Elmwood Avenue, Burlington, VT 05401

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS TOC - 1

TABLE OF CONTENTS

Number SECTION TITLE

COVER SHEET

TOC TABLE OF CONTENTS

011000 SUMMARY

011400 WORK RESTRICTIONS

012500 SUBSTITUTION PROCEDURES

012900 PAYMENT PROCEDURES

013100 PROJECT MANAGEMENT & COORDINATION

013120 CRITICAL PATH METHOD SCHEDULING FOR SHORT PROJECTS

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013300 SUBMITTAL PROCEDURES

014000 QUALITY ASSURANCE & CONTROL REQUIREMENTS

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015930 SECURITY PROCEDURES

015950 SAFETY & HEALTH

016000 PRODUCT REQUREMENTS

017000 EXECUTION REQUIREMENTS

017310 CUTTING & PATCHING

017320 SELECTIVE DEMOLITION

017350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK

017410 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT

017419 CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017810 PROJECT RECORD DOCUMENTS

017822 OPERATION AND MAINTENANCE DOCUMENTATION

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS TOC - 2

018200 DEMONSTRATION AND TRAINING

020850 ASBESTOS ABATEMENT

061053 MISCELLANEOUS ROUGH CARPENTRY

064116 PLASTIC LAMINATE FACED ARCHITECTURAL CABINETS

072100 THERMAL INSULATION

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

081113 HOLLOW METAL DOORS AND FRAMES

081416 FLUSH WOOD DOORS

083113 ACCESS DOORS AND FRAMES

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

087100 FINISH HARDWARE

088000 GLAZING

091110 NON-LOAD-BEARING STEEL FRAMING

092500 GYPSUM BOARD

095110 ACOUSTICAL PANEL CEILINGS

096500 RESILIENT FLOORING

096813 TILE CARPETING

096816 SHEET CARPETING

099120 INTERIOR PAINTING

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS TOC - 3

101423.13 ROOM IDENTIFICATION SIGNAGE

102213 WIRE MESH PARTITIONS

102800 TOILET ACCESSORIES

104413 FIRE EXTINGUISHER CABINETS

105200 FIRE PROTECTION SPECIALITIES

102217 MODULAR PARTITIONS

210529 PIPE HANGERS AND SUPPORTS

211300 SPRINKLER PIPING

211313 SPRINKLER SYSTEMS

220518 ESCUTCHEONS FOR PLUMBING PIPING

220719 PLUMBING PIPING INSULATION

221116 DOMESTIC WATER PIPING

221316 SANITARY WASTE AND VENT PIPING

221319 SANITARY WASTE PIPING SPECIALTIES

223300 ELECTRIC DOMESTIC WATER HEATERS

224213.13 COMMERCIAL WATER CLOSETS

224216.13 COMMERCIAL LAVATORIES

224223 COMMERCIAL SHOWERS

230553 IDENTIFICATION FOR HVAC EQUIPMENT

230593 TESTING ADJUSTING & BALANCING FOR HVAC

230713 DUCT INSULATION

230800 COMMISSIONING OF HVAC

230900 INSTRUMENTATION AND CONTROL FOR HVAC

230923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233600 AIR TERMINAL UNITS

233713 DIFFUSERS, REGISTERS AND GRILLES

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS TOC - 4

237313 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS

238126 SPLIT-SYSTEM AIR CONDITIONERS

238219 FAN COIL UNITS

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260923 LIGHTING CONTROL DEVICES

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES & CIRCUIT BREAKERS

265100 INTERIOR LIGHTING

271500 COMMUNICATIONS HORIZONTAL CABLING

APPENDIX A SUBMITTAL REGISTER

APPENDIX B ASBESTOS AND LEAD PAINT REPORTS

APPENDIX C MODULAR PARTITIONS SCHEDULE

END OF TABLE OF CONTENTS

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUMMARY 011000 - 1

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Name and Location: Burlington Court Reconfiguration Project, Burlington Federal Building USPO and Courthouse, 11 Elmwood Avenue, Burlington, VT 05401.

B. Project Summary Description: Selective demolition and construction of interior renovations of approximately 22,950 square feet as phased construction.

C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by: EDM, 100 West Street, Pittsfield, MA 01201.

D. Project Delivery Method: Traditional design/bid/build.

E. The Contracting Officer (CO) for the project is: Michele Valenza. The Contracting Officers Representative (COR) for the project is: Travis Bonnett.

1.2 WORK SEQUENCE

A. The work shall be conducted in phases on the second, fourth, fifth floors and penthouse in this building: Phase 1A and 3 - Fourth and Fifth Floor Chambers, Probation Offices, Conference Room and Law Clerk Offices, Phase 1B - Fourth Floor Chambers and Penthouse AHU / Fourth Floor Mechanical, Phase 2 Second Floor Bank Clerks Office, Phase 3 Fifth Floor Law Clerk Offices, Phase 4 and Phase 5 Fifth Floor District Clerk of Courts (North and South), Phase 6 Fourth Floor Chambers and Law Clerk Offices, Phase 7 - Fourth Floor Probation Offices (North) and Penthouse AHU / Fourth Floor Mechanical, and Phase 8 Probation Offices (South). Refer to the Construction Drawings for additional phasing information.

B. In addition, work will be required in other Phase areas in order to support infrastructure and utility scope for the Phase in the current work area. Work in the Phase 1A Computer Room 526 will continue throughout the project phases which follow. Data connectivity will need to be provided in the Phase 8 area to Computer Room 526 prior to the start of demolition work in the Phase 7 work area.

C. Building will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. The following phasing description is provided for Contractor convenience to outline the proposed phasing plan, and includes but not be limited to the following items:

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUMMARY 011000 - 2

1. Phase 1A and 3 (Fifth Floor Chambers, Probation Offices, Conference Room and Law Clerk Offices): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 120 calendar days after notice to proceed:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides build-out of Phase area and modular partitions.

e. Contractor provides door control and access control system.

f. Contractor provides testing and balancing of Phase area.

g. Substantial completion and punch list.

h. Agency contractor moves furniture and workstations into Phase area.

i. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

j. Furniture punch list.

k. Agency move-in and occupancy – completed within 10 calendar days.

2. Phase 1B (Fourth Floor Chambers and Penthouse AHU / Fourth Floor Mechanical): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 90 calendar days after Phase 1A and 3 completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides Penthouse AHU and mechanical in Phase 1B and portions of

Phase 6 area.

e. Contractor provides build-out of Phase area.

f. Contractor provides door control and access control system.

g. Contractor provides testing and balancing of Phase area.

h. Substantial completion and punch list.

i. Agency contractor moves furniture and workstations into Phase area.

j. Contractor provides power feeds, devices and data cabling and devices to furniture and completes punch-down.

k. Furniture punch list.

l. Agency move-in and occupancy – completed within 10 calendar days.

3. Phase 2 (Second Floor Bank Clerks Office): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 45 calendar days after Phase 1B completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides build-out of Phase area and modular partitions.

e. Contractor provides door control and access control system.

f. Contractor provides testing and balancing of Phase area.

g. Substantial completion and punch list.

h. Agency contractor moves furniture and workstations into Phase area.

i. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

j. Furniture punch list.

k. Agency move-in and occupancy – completed within 10 calendar days.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUMMARY 011000 - 3

4. Phase 4 and 5 (Fifth Floor District Clerk of Courts (North and South): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 60 calendar days after Phase 2 completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides build-out of Phase area and modular partitions.

e. Contractor provides door control and access control system.

f. Contractor provides testing and balancing of Phase area.

g. Substantial completion and punch list.

h. Agency contractor moves furniture and workstations into Phase area.

i. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

j. Furniture punch list.

k. Agency move-in and occupancy – completed within 10 calendar days.

5. Phase 6 (Fourth Floor Chambers and Law Clerks Offices): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 60 calendar days after Phase 4 and 5 completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides build-out of Phase area and modular partitions.

e. Contractor provides door control and access control system.

f. Contractor provides testing and balancing of Phase area.

g. Substantial completion and punch list.

h. Agency contractor moves furniture and workstations into Phase area.

i. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

j. Furniture punch list.

k. Agency move-in and occupancy – completed within 10 calendar days.

6. Phase 7 (Fourth Floor Probation Offices (North) and Penthouse AHU / Fourth Floor Mechanical): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 90 calendar days after Phase 6 completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides Penthouse AHU and mechanical in Phase 7 and portions of

Phase 6 area.

e. Contractor provides build-out of Phase area and modular partitions.

f. Contractor provides door control and access control system.

g. Contractor provides testing and balancing of Phase area.

h. Substantial completion and punch list.

i. Agency contractor moves furniture and workstations into Phase area.

j. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

k. Furniture punch list.

l. Agency move-in and occupancy – completed within 10 calendar days.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUMMARY 011000 - 4

7. Phase 8 (Fourth Floor Probation Offices (South): The following work, in accordance with the phasing drawings, shall be substantially complete, ready for occupancy, within 60 calendar days after Phase 7 completion:

a. Agency provides Phase area clear of furniture and equipment.

b. Contractor provides temporary partitions and protection.

c. Contractor provides demolition of Phase area.

d. Contractor provides build-out of Phase area and modular partitions.

e. Contractor provides door control and access control system.

f. Contractor provides testing and balancing of Phase area.

g. Substantial completion and punch list.

h. Agency contractor moves furniture and workstations into Phase area.

i. Contractor provides power feeds, devices and data cabling and devices to modular partitions and furniture and completes punch-down.

j. Furniture punch list.

k. Agency move-in and occupancy – completed within 10 calendar days.

8. Final Completion: Completion of all work in accordance with the phasing drawings shall be substantially complete, ready for occupancy, within 20 calendar days after completion of Phase 8.

a. Contractor provides final testing and balancing of all Phase areas.

b. Contractor provides all final closeout documents and compliance with closeout requirements.

1.3 WORK BY OTHER CONTRACTORS

A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.

1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY

A. The project includes Government furnished property to be installed by the Contractor. The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.

1.5 MISCELLANEOUS PROVISIONS

A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.

Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUMMARY 011000 - 5

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.

3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place.

D. Existing utility services with related meters and equipment will remain in place.

E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011000

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

WORK RESTRICTIONS 011400 - 1

SECTION 011400 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 CONTRACTOR USE OF PREMISES

A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.

B. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Maintain existing building in a safe and weather-tight condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Space on the premises which can be made available for the Contractor's storage and related activities is extremely limited. Materials should be staged off-site and phased for delivery to the work area. Arrange and gain approval for use of this space through the Contracting Officer. Use of on-site space must not interfere with operations of the Government.

7. Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The loading dock is available for the delivery of materials, tools, and supplies between working hours, typically 6:00 AM to 5:00 PM.

8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.

10. Smoking is not permitted in or around the building, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

WORK RESTRICTIONS 011400 - 2

11. No parking will be available on site during working hours for building occupants. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site. One parking space approximately forty (40) feet in depth can be made available for contractor use, for dumpster or vehicle.

12. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be “on vibrate” at all times. If a telephone begins audibly ringing, the building guards will take the cell phone and hold until the end of the working day prior to the con-tractor leaving the property. Cell phones are only permitted in construction area and contractor’s office space.

13. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.

14. Permits: Refer to FAR 52.236-7

15. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

16. Coordinate with the GSA Building Manager and the COR for site access.

17. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.

18. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.

19. Protect building site from flying debris.

20. The use of cameras is not permitted in occupied areas of the building.

1.2 GOVERNMENT OCCUPANCY

A. The Government will occupy the site and the existing building during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.

B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

WORK RESTRICTIONS 011400 - 3

1.3 WORKING HOURS

A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays 6:00 AM to 5:00 PM.

B. Government Unoccupied Hours: Government personnel are not scheduled to occupy the building during times not indicated as Government Occupied Hours.

C. Contractor's General Working Hours: The Contractor working hours shall be generally established to occur during Government Occupied Hours.

D. Contractor's Required Working Hours: The following work shall be performed during Government Unoccupied Hours:

1. Noisy and/or odor-producing work that may disrupt tenant operations in adjacent spaces.

2. All work that may disrupt or affect any existing building systems.

E. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the Contracting Officer's approval at least 48 hours before proceeding with any work during Government Unoccupied Hours.

1. Any work which may affect Government operations, access for use and access to required exits.

2. Any work which requires a disconnection or shut-down of building systems or utilities.

3. Work during unoccupied hours must be scheduled a minimum of one week in advance to allow the Government to provide guard service.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011400

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUBSTITUTION PROCEDURES 012500 - 1

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 016000 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 49 Sections for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner

1.4 SUBMITTALS for Cause or Convenience:

A. Substitution Requests: Per Submittal Procedures Section 013300 submit electronic copies through Google Drive folder of each request for consideration. Notify GSA COR and A/E concurrently via email of any transmittal or upload of information to the Google Drive folder.

Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUBSTITUTION PROCEDURES 012500 - 2

1. Substitution Request Form: GSA product substitution request form.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.

b. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource performance goals, warranties, and specific features and requirements indicated.

Indicate deviations, if any, from the Work specified.

c. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested.

e. Certificates and qualification data, where applicable or requested.

f. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

h. Research reports evidencing compliance with building code in effect for project, when applicable for the proposed substitution.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. The Contracting Officer may require the Contractor to provide a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR) Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUBSTITUTION PROCEDURES 012500 - 3

1.5 Failure by the government to respond does not constitute acceptance of the proposed substitution.

1.6 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.7 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than (15) fifteen days prior to time required for preparation and review of related submittals.

1. Conditions: The Contracting Officer (CO) will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the Contracting Officer (CO) will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan. .

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within (20) twenty days after the Notice of Award. Requests received

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SUBSTITUTION PROCEDURES 012500 - 4

after that time may be considered or rejected at discretion of the Contracting Officer (CO) or the Contracting Officer Representative (COR).

1. Conditions: The Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied.

a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Requested substitution does not adversely affect the Contract Schedule.

e. Substitution request is fully documented and properly submitted.

If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 EXECUTION (Not Used)

END OF SECTION 012500

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and to process Requests for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A detailed written statement (masterformat/uniformat) furnished by the Contractor outlining the portions of the contract sum, which allocates values (price & percentage) for the various parts of the work and used as the basis for payment application and reviewing progress payments. The Agreement provides further details.

B. Request for Payment: A contractor’s invoice and request for progress payment with substantiating information consistent with approved schedule of values.

1.3 SCHEDULE OF VALUES

1. Coordination: Submit completed Schedule of Values no later than [14] calendar days prior to scheduled date of initial Requests for Payment.

2. Schedules for Phased Work: Where the work is separated into phases, provide Schedules showing values correlated with each phase using the standard format referenced below.

A. Format and Content: Contractor shall be responsible to complete the GSA Schedule of Values Workbook and compile the values into project schedule folder on the Google Drive. Contractor will enter values into workbook prior to Google Drive folder input and provide associated electronic baseline copy to contracting officer for record. Contractor will follow guidelines in the Schedule of Values workbook to support Google Drive folder upload.

1. Identification: Complete the following Project Identification fields in the Schedule of Values:

a. Project Name

b. Project Number

c. Project Location, City, State

d. Base Contract Number

e. Task Order Number

f. Modification Number

g. GSA Project Manager

h. Contractor's Name and contact information

i. Date of submittal

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PAYMENT PROCEDURES 012900 - 2

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Requests for Payment and progress reports.

a. Work activity – (by division or specific work activity)

b. Dollar value of each specific work activity – both with an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent. Adjust the amounts to total to the Contract Sum and the percentages to total 100 percent.

c. Each item in the schedule of values and Requests for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. (i.e. no stand alone item for Overhead, and Profit)

d. Modifications that affect value.

e. Update affected work branches and subordinate line items and

f. resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

g. Line item for mobilization and de-mobilization

h. Line item for close out (% to be negotiated with GSA COR)

3. Options: Provide a separate Schedule of Values for each exercised Option.

4. Each item in the Schedule of Values and Requests for Payment shall be complete. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.

5. Revise and update workbook in Google Drive folder with all items affecting scope, schedule or cost and resubmit within 14 calendar days as coordinated with project manager or contracting officer.

Contractor shall provide a final as-built schedule at project completion. Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

1.4 REQUESTS FOR PAYMENT

B. Requirements for Requests for Payment are in Section III, Terms and Conditions of the Agreement.

C. Each Request for Payment following the initial Request for Payment shall be consistent with previous Requests.

1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final Request for Payment involve additional requirements.

D. Payment Request Times: Submit Request for Payment to GSA by the last day of the month. The period covered by each Request for Payment is one month, ending on the last day of the month.

1. Enter draft (aka pencil copy) of Request for Payment in Google Drive folder along with construction progress report seven days prior to due date for review by GSA. Provide documentation evidencing the cost of work performed to be included in the Request for Payment. Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PAYMENT PROCEDURES 012900 - 3

E. Request Preparation: All payments must be executed by a person authorized to legally bind the Contractor.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.

3. Include amounts of Modifications issued before last day of construction period covered by Request.

F. Stored Materials: Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of effective date of previous Request for Payment.

b. Value of previously stored materials put in place after effective date of previous Request for Payment and on or before effective date of current Request for Payment.

c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.

G. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule per Agreement (startup if not final).

4. Products list (preliminary if not final).

5. Sustainable design submittal for project materials cost data.

6. Sustainable design action plans.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the

Work.

13. Initial progress report.

14. Report of preconstruction conference.

H. Request for Payment at Substantial Completion: After GSA issues the Notice of Substantial Completion, submit a Request for Payment less previous payments made for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PAYMENT PROCEDURES 012900 - 4

2. This Request shall reflect Notices of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.

I. Final Payment Request: The Agreement provides further details

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Conservation.

4. Administrative and supervisory personnel.

5. Conferences and meetings.

6. Utility service interruptions.

7. Cleaning and protection.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.

Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

3. Minimize roof penetrations.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.

Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal Protective Service (FPS), tenants, etc.)

4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.

5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.

6. Delivery and processing of submittals.

7. Progress meetings.

8. Project closeout activities.

9. Startup and adjustment of systems.

1.3 COORDINATION DRAWINGS

D. Prepare coordination drawings and/or BIM model and data where coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum use of the space for efficient installation of different components.

1. Show the relationship of components from the separate shop drawings. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems

2. Indicate required installation sequences.

3. Indicate minimum access space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

4. Show locations and sizes of all access doors on vertical and horizontal surfaces throughout the facility.

5. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

6. Comply with shop drawing requirements for sheet size and submittal methods specified in Division 1 Section "Submittal Procedures."

E. Refer to Divisions 23, and 26 Plumbing, Heating Ventilating and Air Conditioning, and Electrical for specific coordination drawing requirements for mechanical and electrical installations.

F. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

G. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk.

Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

H. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:

1. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).

1.3 CONSERVATION

A. Coordinate conservation of energy, water and materials in the conduct of construction operation.

Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Comply with Green Purchasing Plan requirements.

C. Waste Management Plan: Establish a program to maximize recycling of waste materials.

Program shall include the following:

1. Designation of a waste management coordinator.

2. Identification of recyclable materials.

3. Identification of available local recycling firms and agencies to receive recyclable materials.

4. Establishment of quantity goals for collection of each recyclable material.

5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.

6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.

7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.

a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.

b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant stakeholder of the project, including the Government.

1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.

B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

1. Scheduling and sequencing of Work.

2. Sharing access to work spaces.

3. Installations.

4. Protection of work.

5. Cutting and patching.

6. Selections for compatibility.

7. Preparation of coordination of drawings.

8. Inspection and tests.

9. Temporary services and facilities.

C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."

D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

1.5 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:

a. Government.

b. Architect.

c. Major design…