About this file

These General Provisions documents are for the Soil Stabilization Above Greenleaf Street project by the City of Pittsburgh, located in the 19th Ward of Allegheny County, Pennsylvania. The project aims to stabilize a hillside slope that was part of a 2018 landslide that destroyed a house and closed Greenleaf Street and the South Main Street ramp. The work includes installing deep soil mixing panels, a rock buttress, soil nails, micropiles, and a geosynthetically-stabilized soil trail. Additional tasks involve construction surveying, erosion control, traffic management, site preparation, testing, and reconstructing a portion of Greenleaf Street pavement.

The contract requires the contractor to obtain comprehensive insurance coverage, including general liability with $1,000,000 per occurrence and $2,000,000 aggregate, automotive liability insurance of $2,000,000, umbrella liability insurance of $5,000,000, and statutory workers' compensation. The project has specific noise restrictions, limiting work to Monday-Saturday from 7 a.m. to 8 p.m. and prohibiting work on specified city holidays. Materials used in the project will require quality control testing by the contractor, observation by the owner's representative, and manufacturer or supplier certification. The city emphasizes that alternative methods will only be considered after bid opening and is not obligated to accept alternative methods or value-engineered solutions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Provisions Cover

SOIL STABILIZATION ABOVE GREENLEAF STREET

19TH WARD – CITY OF PITTSBURGH, ALLEGHENY COUNTY, PENNSYLVANIA

GENERAL PROVISIONS

Section 0030 Page 1 of 1

SECTION 0030

DESCRIPTION OF WORK

SOIL STABILIZATION ABOVE GREENLEAF STREET

19TH WARD – CITY OF PITTSBURGH, ALLEGHENY COUNTY, PENNSYLVANIA

This work will install stabilizing treatments on the hillside slope above the western, bottom portion of Greenleaf Street. The work, indicated on the Project documents, generally consists of deep soil mixing and installation of rock buttress, adjacent Greenleaf St, at the toe of the slope and . Work on the upper slope, adjacent the Emerald View Park Trail, includes excavation and installation of soil nails, installation of a line of micropiles with concrete cap and installation of geosynthetically-stabilized soil trail. Work also includes reconstructing a portion of Greenleaf St adjacent the historic slide area.

As background, the existing earthen slope above Greenleaf Street was part of a 2018 slide that destroyed at least one house and closed Greenleaf Street and the South Main Street ramp. To mitigate the risk of a future landslide and its potential detrimental effects on transportation networks, the City seeks to further stabilize the hillside with several landslide remediation techniques.

The work will generally include the following tasks, not necessarily in this order. Some necessary tasks may be omitted from this list:

Design Soil Nail Work Plan, Deep Soil Mixing Work Plan.

Perform Construction surveying.

Install Limit of Disturbance (LOD) work area boundary stakes.

Install erosion and sedimentation measures and rock construction entrance.

Design and implement a Traffic Control Plan.

Perform general site preparations for deep soil mixing work.

Perform deep soil mixing bench scale testing program.

Install deep soil mixed test panel and collect QA/QC samples from the test panel.

Construct the deep soil mixed panels.

Construct rock buttress above the upper row of deep soil mixed panels.

Stabilize the slope around the emerald view trail by installing soil nails and mesh, micropiles and geogrid reinforced slope treatment and the final trail surface.

Reconstruct a portion of the Greenleaf street pavement.

Topsoil, seed and mulch disturbed areas. Remove erosion and sedimentation measures.

Removal of any traffic control measures.

ALL WORK IS TO OCCUR IN ACCORDANCE WITH THE CONTRACT DRAWINGS,

SPECIFICATIONS, GENERAL AND SPECIAL PROVISIONS.

ALTERNATIVE METHODS WILL ONLY BE CONSIDERED AFTER THE BID

OPENING. THE CITY OF PITTSBURGH IS NOT OBLIGATED TO ACCEPT

ALTERNATIVE METHODS OR VALUE ENGINEERED SOLUTIONS.

END OF DESCRIPTION OF WORK

Section 0040 Page 1 of 1

SECTION 0040

DEPARTMENT REFERENCES

Where "Department" is referenced in the Special Provisions, Specifications, Plans or other

Project documents, unless specifically noted otherwise, the intent of this Project is to reference the Department of Mobility and Infrastructure, City of Pittsburgh, and unless the referenced activity, document or service is not provided by the City of Pittsburgh and only provided by the

Pennsylvania Department of Transportation.

END OF DEPARTMENT REFERENCES

Section 0050 Page 1 of 1

SECTION 0050

NOISE RESTRICTION

Except as permitted explicitly by the City, restrict noise-producing work to Monday-Saturday, 7a.m. to 8 p.m. and do not work on Sunday’s or City observed Holidays including:

New Year's Day Martin Luther King's Birthday Good Friday Memorial Day Juneteenth Independence Day Labor Day Veterans' Day Thanksgiving Day The day after Thanksgiving Day Christmas Day

When a holiday falls on a Saturday, observe the Holiday on the preceding Friday. When a holiday falls on a Sunday, observe the Holiday on the following Monday.

END OF NOISE RESTRICTION

Section 0060 Page 1 of 1

SECTION 0060

ADDITIONAL INFORMATION AVAILABLE

Additional Information Made Available to the Bidder (‘User’) by the Department.

Information, data, files, or samples (‘Information’) made available to the User during the advertisement period is provided in accordance with Publication 408 Section 102 and is provided “AS IS.” The Department makes no warranty or representation, either express or implied, with respect to the quality, accuracy, performance, merchantability or fitness of the Information for a particular purpose. The opinions expressed in the Information may not be those of the Department. The Department cannot guarantee that the Information provided is in accordance with the Department’s standards. The User assumes the entire risk as to the quality of the Information and the Department shall not be responsible or liable for any damages, caused, in whole or in part, by use of the Information. The User shall immediately notify the Department in the event that it discovers that the Information contains vague, ambiguous, or contradictory information via the Bid system Questions and Answers function.

The Information is not a substitute for the sound engineering judgment of the User. The User shall indemnify and hold harmless the Department, its officials, and employees for any injury to the person or property of third parties arising out of the use of or any defect in the Information.

In addition to the “Info_Only-“ documents attached to the Solicitation, the following Information is available:

Subsurface Boring sample Core Boxes: Sample material core boxes are available for inspection in Pittsburgh. Contact Mr. Tom Samstag at the Department of Mobility and Infrastructure 412.915.7312 to arrange for a date and time to inspect the core boxes.

END OF ADDITIONAL INFORMATION AVAILABLE

Section 0080 Page 1 of 1

SECTION 0080

ADDITIONAL INSURANCE REQUIREMENTS

In addition to any other insurance or bond required elsewhere in this solicitation, Contractor shall obtain and maintain for the entire duration of all work performed under any contract arising from this solicitation an insurance policy providing the following minimum coverages:

GENERAL LIABILITY - Single limit of Bodily Injury and Property Damage (including environmental damage) Combined: $1,000,000.00 each occurrence; $2,000,000.00 aggregate.

AUTOMOTIVE LIABILITY INSURANCE - Combined single limit of $2,000,000.00.

UMBRELLA LIABILITY INSURANCE - Five Million Dollars ($5,000,000) excess liability, each occurrence/aggregate.

WORKERS’ COMPENSATION: STATUTORY LIMITS.

Insurance coverage must be an “OCCURRENCE POLICY". "Claims made” policies are unacceptable. City of Pittsburgh, the Federal Emergency Management Agency and Pennsylvania Emergency Management Agency must be named as "Additional Insured' on the insurance certificate on all general, automobile, and umbrella policies. The insurance policies shall also contain a provision that the coverages afforded thereunder shall not be cancelled or changed unless at least thirty (30) days prior written notice has been given to the City of Pittsburgh. The policy shall insure against the liability of the City of Pittsburgh arising out of or in connection with Contractor’s acts, errors, omissions and work performance.

Contractor must submit a properly executed Insurance Certificate evidencing the issuance of adequate insurance.

Carry the specified insurance from the time physical work is started until all physical work required to be performed under the terms of the Contract is substantially completed. Failure to carry or keep such insurance in force until all work is substantially completed will constitute a violation of the contract and in such event, the Director may avail him/herself of the remedies provided under Publication 408, Section 108.08.

Unless addressed elsewhere in this solicitation, in accordance with Publication 408 Sections

103.06 and 107.14, carry regular Contractor's Public Liability and Property Damage Insurance of not less than two million dollars ($2,000,000).

If any work is subcontracted, furnish evidence to the City of Pittsburgh that regular Contractor's Protective Public Liability and Property Damage Insurance of not less than two million dollars ($2,000,000) is carried on the Contractor's behalf.

END OF ADDITIONAL INSURANCE REQUIREMENTS

Section 0106 Page 1 of 2

SECTION 0106

CONTROL OF MATERIAL

In accordance with Section 0106 and as follows:

106.03(b)1 Responsibility. Add the following to the first paragraph:

The following table identifies some of the materials for the Project and the party(ies) responsible for sampling and testing, or certification. Provide Testing and/or Certification of materials not identified here according to the 408 or Controlling PennDOT criteria.

Item/Section and

Material

Quality Control

Testing by

Contractor

Observance of or

Testing by

Owner/Owner’s

Representative

Manufacturer’s or

Supplier’s

Certification

Aggregate X

- Coarse X

- Subbase X X

Cast-In-Place Concrete X X X

Grout X X X

Reinforcing Steel X

Plastic Pipe X

PVC Pipe X

Geotextile X

Seed and Soil Supplements *

Micropiles system X X X

Soil Nail system X X X

Soil Nail Testing X X X

Wire Mesh X

Pavement X X X

Guide Rail X

Erosion and Sedimentation

Control Products X

Section 0106 Page 2 of 2

Item/Section and

Material

Quality Control

Testing by

Contractor

Observance of or

Testing by

Owner/Owner’s

Representative

Manufacturer’s or

Supplier’s

Certification

Borrow Excavation X X X

Granular Embankment X X

DSM Testing X X X

PTM 510 Rock X X X

Embankment Placement X X

Top Soil X X X

Tree Planting X

* Certification by the Pennsylvania Department of Agriculture, Bureau of Plant Industry.

Include costs for tests and certifications in the bid price for the bid items on the Schedule of

Prices.

Provide a copy of each certification for each item requiring certification to the City’s representative at the time of material delivery to the site, and one (1) copy of each certification for each item to the Owner’s Engineer for approval at least 2 weeks prior to delivery of material to the site.

END OF CONTROL OF MATERIAL

Section 0703 Page 1 of 1

SECTION 0703

AGGREGATE

In accordance with Section 0703 and as follows:

703.1(a) 2. Manufactured Sand.

Delete section

703.1(b) Production Testing.

Delete section

703.2(a) 3. Blast Furnace Slag.

Delete section

703.2(a)4. Steel Slag.

Delete section

703.2(a)5. Granulated Slag.

Delete section

703.2(b). Production Testing.

Delete section

703.2(c) 1. Soundness.

Delete the following sentence:

“The LTS may accept aggregate failing the test if it can be demonstrated in writing the aggregate has a satisfactory service record in both pavements and structures”

703.3(a). General.

Delete the following words in the first sentence:

“or slag”

END OF AGGREGATE

0040 - Department References
0050 - Noise Restrictions
0060 - Additional Informaton available
0080 - Additional Insurance Req-AB-r
0106 - Control of Material
0703 - Aggregates
0000 - General Provisions-Cover
0040 - Department References
0040 - Department References
0106 - Control of Material-2023-10-30
0106 - Control of Material-2023-10-31

File details come from the government source that posted it. Updated .