Green_Waste_Processing_and_Grinding.pdf

PDF 604 KB Posted

Attached to
PLANNING CONSULTING SERVICES POOL State and local contract opportunity
Solicitation number
26-020
Issued by
Broward County, Florida

About this file

Santa Rosa County Green Waste Processing and Grinding Services - Invitation to Bid 26-020

This Invitation to Bid (ITB) document issued by the Santa Rosa County Board of County Commissioners, Florida, solicits sealed bids from properly licensed and insured contractors to provide green waste processing and grinding services. The project encompasses the mobilization, operation, and demobilization of grinding equipment to process accumulated green waste stockpiled at the Santa Rosa County Central Landfill located at 6337 Da Lisa Road, Milton, Florida, and at other county-owned or county-controlled properties as directed. Green waste materials include vegetative debris such as grass clippings, leaves, brush, tree branches, tree trunks, roots, stumps, logs, and burls of any size. A mandatory pre-bid meeting is scheduled for March 10, 2026, at 9:00 a.m. at the Central Landfill. Written questions must be submitted through the Santa Rosa County Procurement Portal by 12:00 p.m. on Tuesday, March 17, 2026. All proposals must be submitted electronically through the procurement portal by 10:00 a.m. on Tuesday, March 24, 2026, with public opening via Microsoft Teams. Services shall be performed on an as-needed basis, with contractors required to acknowledge requests within seventy-two hours and mobilize within thirty calendar days. Once mobilized, all designated materials must be fully processed within twenty-one calendar days unless written extension is approved by the Environmental Manager. Grinding operations must occur during normal facility operating hours, typically Monday through Saturday, 7:00 a.m. to 5:00 p.m., excluding county-recognized holidays. The contract will include provisions for renewal options as determined by the county.

Pricing shall be provided on a per-ton and per-cubic-yard basis, with the county's scale records and volume measurements serving as the final determination for payment. All estimated quantities provided are for informational purposes only, and actual payment will be based on quantities determined by Santa Rosa County. The contractor bears sole responsibility for all material handling, equipment operation, dust control, fire prevention, personnel supervision, contaminant removal, and equipment damage resulting from contamination. Contractors must provide proof of minimum insurance coverage including Workers' Compensation ($100,000 per accident, $500,000 per policy), Commercial General Liability ($1,000,000 per occurrence, $2,000,000 aggregate), and Business Auto Liability ($500,000 per occurrence). Santa Rosa County must be named as an additional insured on all applicable policies with thirty days' written notice required before policy cancellation or modification. Bidders must demonstrate a minimum of five years of relevant experience in commercial or municipal green waste processing, submit three project references, provide an Operations Plan, submit resumes for key personnel, and verify compliance history with applicable regulations. The solicitation encourages participation from small businesses, minority-owned businesses, women-owned businesses, and disadvantaged business enterprises and includes federal compliance requirements regarding debarment, procurement of recovered materials, Buy America provisions, equal employment opportunity, and domestic preference for United States-produced materials.

View the file

Other files for this state and local contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

26-020

GREEN WASTE PROCESSING AND GRINDING

February 23, 2026

OWNER:

BOARD OF COUNTY COMMISSIONERS

SANTA ROSA COUNTY, FLORIDA

BOBBY BURKETT – DISTRICT I

KERRY SMITH – DISTRICT II

RHETT ROWELL – DISTRICT III

RAY EDDINGTON – DISTRICT IV

COLTEN WRIGHT – DISTRICT V

26-020

INVITATION TO BID

GREEN WASTE PROCESSING AND GRINDING

Solicitation advertised utilizing Santa Rosa County Procurement & Purchasing Ordinance 2023-06 adopted June 19, 2023

I. Notice to Respondents II. Bid Instructions, Submittal Requirements, and General Requirements

III. FEDERAL LANGUAGE

IV. Insurance V. Scope of Work

VI. Pricing Table VII. Vendor Questionnaire and Submission

Attachments:

A - 26-020 Draft Contract Services

3 | P a g e

1. Notice to Respondents

1.1. Summary

MEMORANDUM

TO: Company Addressed DATE: Monday, February 23, 2026

FROM: Santa Rosa County Procurement Office

SUBJECT: 26-020 Green Waste Processing and Grinding

Notice is hereby given that the Santa Rosa County Board of County Commissioners will receive sealed bids from properly licensed and insured contractors for Green Waste Processing and Grinding Services.

A pre-bid meeting will be held on March 10, 2026 at 9:00 a.m. at the Santa Rosa County Central Landfill, 6337 Da Lisa

Road, Milton, FL 32583. Please meet in the front parking lot for further instructions.

Specifications may be secured through the Santa Rosa County Procurement Portal at https://procurement.opengov.com/portal/santarosafl Questions concerning this request should be submitted through the procurement portal by 12:00 pm on Tuesday, March 17, 2026.

Please submit all proposals through the procurement portal at https://procurement.opengov.com/portal/santarosafl by 10:00 am on Tuesday, March 24, 2026, at which time will be publicly opened via Teams.

Santa Rosa County Board of County Commissioners encourages all segments of the business community to participate in its procurement opportunities, including small businesses, minority/women owned businesses, and disadvantaged business enterprises. The Board does not discriminate on the basis of race, color, religion, national origin, disability, sex, or age in the administration of contracts.

The Board of County Commissioners reserves the right to waive irregularities in bids, to reject any or all bids for sound documented reasons, and to award the bid that it determines to be in the best interest of Santa Rosa County.

By order of the Board of County Commissioners of Santa Rosa County, Florida.

2. Bid Instructions, Submittal Requirements, and General Requirements

2.1. Pre-Bid Activity

Except as provided in this section, respondents are prohibited from contacting or lobbying the County, County

Administrator, Commissioners, County staff, or any other person authorized on behalf of the County related or involved with the solicitation. All inquiries on the scope of work, specifications, additional requirements, https://procurement.opengov.com/portal/santarosafl

4 | P a g e attachments, terms and general conditions or instructions, or any issue must be directed in writing, via the County e-Procurement Portal located at https://procurement.opengov.com/portal/santarosafl.

All questions or inquiries must be received no later than the last day for questions stated in 26-020Green Waste

Processing and Grinding & Legal Notice. Any addenda or other modification to the bid documents will be issued by the County prior to the date and time of bid closing, as written addenda, and will be posted to the Santa Rosa

County e-Procurement Portal hosted by OpenGov. Once the bidder has completed registration, they will receive addenda notifications to their email by clicking “Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at https://procurement.opengov.com/portal/santarosafl.

Such written addenda or modification shall be part of the bid documents and shall be binding upon each respondent. Each respondent is required to acknowledge receipt of all addenda. No respondent may rely upon any verbal modification or interpretation.

2.2. Preparation of Bid

The respondent shall submit bids in accordance with the public notice. The respondent shall submit bids in accordance with bid documents and must be listed on the Division of Corporations website (Sunbiz) for the FEIN provided.

Any proposal which contains any omissions, erasures, alterations, additions, irregularities of any kind, or items not called for which shall in any manner fail to conform to the conditions of public notice may be rejected.

A bid submitted by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature). The official address of the partnership shall be shown below the signature.

A bid submitted by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown below the signature.

A bid submitted by an individual shall show the respondent’s name and official address.

A bid submitted by a joint venture shall be executed by each joint venture in the manner indicated on the bid form.

The official address of the joint venture must be shown below the signature.

The bid shall contain an acknowledgement of receipt of all addenda, the numbers of which shall be filled in on the form. The address and telephone number for communications regarding the bid shall be shown.

If the respondent is an out-of-state corporation, the bid shall contain evidence of respondent’s authority and qualification to do business as an out-of-state corporation in the State of Florida. A state contractor license number for the State of Florida shall also be included on the bid form. Respondent shall be licensed in accordance with the requirements of Chapter 489, Florida Statutes.

The bid shall be based upon the completion of the Work according to the drawings and specifications, together with all addenda thereto.

2.3. Submittal of Bid

A bid shall be submitted no later than the date and time prescribed in the solicitation and shall be accompanied by the bid security and other required documents. Applicable bond documents may be uploaded, but any physical checks presented must be delivered to the Procurement Office prior to the Bid Opening. Offers by email, facsimile, or telephone will NOT be accepted.

5 | P a g e

2.4. Electronic Document Format Requirement

All electronic documents submitted in response to this solicitation shall be provided in searchable PDF format. The

County reserves the right to deem proposals that do not comply with this requirement as non-responsive or to require resubmission in the proper format within a specified timeframe. This requirement applies to all attachments, forms, and supporting documentation uploaded to the County’s Procurement Portal or otherwise submitted electronically.

2.5. Integrity of Bid Documents

Respondents shall use the original documents provided on the Santa Rosa County e-Procurement Portal and enter information only in the spaces where a response is requested. Respondents may use an attachment to the documents if sufficient space is not available. Any modifications or alterations to the original documents by the respondent, whether intentional or otherwise, will constitute grounds for rejection of a submittal. Any such modification or alteration that a respondent wishes to propose must be clearly stated in the respondent’s response in the form of an addendum to the original bid documents.

2.6. Withdrawal of Submittals

Any Respondent may withdraw its Submittal, either personally or by written request, at any time prior to the scheduled time for opening Submittals.

2.7. Interpretation

No oral interpretation will be made to any Respondent as to the meaning of the drawings or specifications. Every interpretation made to a Respondent will be in the form of an Addendum to the specifications. Addenda will be furnished to each Respondent, but it shall be the Respondent’s responsibility to make inquiry as to Addenda issued.

All such addenda shall become part of the contract and all Respondents shall be bound by such Addenda whether received by the Respondent.

2.8. Bids to Remain Subject to Acceptance

All responses will remain subject to acceptance or rejection by Santa Rosa County for sixty (60) calendar days after the day of the response opening. The County may, in its sole discretion, release any response and return the bid security prior to the end of this period.

2.9. Conditional and Incomplete Bids

Santa Rosa County specifically reserves the right to reject any conditional response.

2.10. Addition/Deletion of an Item

The County reserves the right to add or delete any item from this response or resulting contract when deemed to be in the County’s best interest.

2.11. Specification Exceptions

Specifications are based on the most current literature available. Respondent shall clearly list any change in the manufacturer’s specifications which conflict with the proposal specifications. Respondent must also explain any deviation from the proposal specification in writing. Failure of the respondent to comply with these provisions will result in respondents being held responsible for all costs required to bring the equipment in compliance with bid specifications.

2.12. Familiarity with Laws

All applicable Federal and State laws, County and municipal ordinances, orders, rules, regulations and General

Terms and Conditions of all authorities having jurisdiction over the project shall apply to the solicitation

6 | P a g e throughout, and they will be deemed to be included in the contract the same as though they were written in full therein.

2.13. Examination of Documents and Site

It is the responsibility of the respondent to inspect the site, scope of the work, and to understand the relevant documents, such as drawings, specifications, addenda, and any other information that may affect the execution of the work and the resources needed. Respondents should ensure that they have a clear and comprehensive knowledge of all the conditions and requirements that may impact the performance of the work under the contract.

2.14. Right to Reject

The County reserves the right to waive informalities in a submission, to reject any or all submissions with or without cause, and accept the submission that in its judgment is in the best interest of the County.

2.15. Disqualification of Respondents

Any of the following reasons may be considered as sufficient for the disqualification of a respondent and the rejection of its response:

• Submission of more than one response for the same work from an individual, firm, or corporation under the same or different name. Evidence that the respondent has a financial interest in the firm of another respondent for the same work.

• Evidence of collusion among respondents. Participants in such collusion will receive no recognition as respondents for any future work of the County until such participant has been reinstated as a qualified respondent.

• Incomplete work which in the judgment of the County might hinder or prevent the respondents prompt completion of additional work if awarded.

• Failure to pay or satisfactorily settle all bills due for labor and material on contracts in effect at the time of issuing the solicitation or default under previous contract.

• Listing of the respondent by any Local, State or Federal Government/Agency on its debarred/suspended vendor list.

2.16. Discrimination

An entity or affiliate who has been placed on the discriminatory vendor list may not submit a response on a contract to provide goods or services to a public entity for the construction or repair of a public building or public work, may not submit responses on leases of real property to a public entity, may not award or perform work as a contractor, supplier, subcontractor, or consultant under contract with any public entity, and may not transact business with any public entity.

2.17. Review of Procurement Documents

Per Section 119.071 (1)(b)-2., Florida Statutes, sealed bids, proposals, or replies received by the County pursuant to a competitive solicitation are exempt from public disclosure until such time as the County provides notice of an intended decision or until 30 days after opening the bids, proposals, or final replies, whichever is earlier.

7 | P a g e

2.18. Compliance with Florida Statute 119.0701

The Respondent shall comply with all the provisions of section 119.0701, Florida Statutes relating to the public records which requires, among other things, that the Respondent: (a) Keep and maintain public records; (b) Provide the public with access to public records on the same terms and conditions that the public agency would provide the records; (c) ensure that public records that are exempt or confidential and exempt from public records disclosure requirements are not disclosed except as authorized by law; and (d) Meet all requirements for retaining public records and transfer, at no cost, to the public agency all public records in possession of the respondent upon termination of the contract.

IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO

THE CONTRACTOR’S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT THE

CUSTODIAN OF PUBLIC RECORDS AT (850) 983-1857, susant@santarosa.fl.gov; 6495 CAROLINE STREET, SUITE M, MILTON, FLORIDA 32570.

2.19. Suspension or Termination for Convenience

The County may, at any time, without cause, order Respondent in writing to suspend, delay or interrupt the work in whole or in part for such period as the County may determine, or to terminate all or a portion of the Contract for the County’s convenience. Upon such termination, the Contract Price earned to the date of termination shall be paid to Respondent, but Respondent waives any claim for damages, including loss of profits arising out of or related to the early termination. Those Contract provisions which by their nature survive final acceptance shall remain in full force and effect. If the County orders a suspension, the Contract price and Contract time may be adjusted for increases in the cost and time caused by suspension, delay, or interruption. No adjustment shall be made to the extent that performance is, was or would have been so suspended, delayed or interrupted by reason for which

Respondent is responsible; or that an equitable adjustment is made or denied under another provision of this

Contract.

2.20. Failure of Performance/Delivery

In case of default by the Vendor, the County after due notice (oral or written) may procure the necessary supplies or services from other sources and hold the Vendor responsible for difference in cost incurred. Continuous instances of default shall result in cancellation of the award and removal of the Vendor from the response list for duration of one (1) year, at the option of the County.

2.21. Audit

If requested, respondent shall permit the County or an authorized, independent audit agency to inspect all data and records of respondent relating to its performance and its subcontracts under this bid from the date of the award through three (3) years after the expiration of contract.

2.22. Non-Collusion

Respondent certifies that it has entered into no agreement to commit a fraudulent, deceitful, unlawful, or wrongful act, or any act which may result in an unfair advantage over other respondents. See Florida Statute 838.22.

2.23. Public Entity Crime Information

Pursuant to Florida Statute 287.133, a respondent may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity; and may not transact business with any public entity more than the threshold amount provided in s. 287.017 for CATEGORY TWO for a period of 36 months following the date of being placed on the convicted vendor list.

mailto:SUSANT@SANTAROSA.FL.GOV

8 | P a g e

Note: For respondent’s convenience, this certification form is enclosed and is made a part of the solicitation package.

2.24. Investigation of Respondent

The County may make such investigations, as it deems necessary to determine the stability of the respondent to perform the work and that there is no conflict of interest. The respondent shall furnish to the County any additional information and financial data for this purpose as the County may request.

2.25. Form of Agreement

The Contract form shall be provided by the Procurement Office. The successful contractor shall, within 10 days after receipt of the Notice of Award and the contract forms or documents, sign and return to the County

Procurement Office all required contract documents. The awarded contractor shall also provide the policies of insurance or insurance certificate as required. All insurance documents shall be approved by Santa Rosa County

Risk Management before the successful contractor proceeds with the work.

The contractor is responsible for submitting along with their response any exceptions it has to the standard terms of contract, within the attached sample contract. Failure to submit exceptions at time of submittal of the bid will be considered a waiver by the respondent to contest or request exception to the contract provisions. Any exceptions to the standard terms of contract will be taken into consideration as part of the County’s review of the response. The County reserves the right to reject bids depending on the substance of the exceptions.

3. FEDERAL LANGUAGE

The following special conditions apply to the Agreement and are incorporated herein by reference:

3.1. Misc. Federal Requirements

All respondents should be aware that some federal funds may be utilized int he course of services being performed under this agreement, as such, respondent agrees that it shall adhere to all necessary federal regulations and the

Uniform Administrative Guidance (2 CFR 200). Further, the respondent acknowledges that the Federal government is not a party to this agreement and is not subject to any obligations or liabilities to the non-federal entity, Respondent, or any other party pertaining to any matter resulting from any award. Should a federal awarding agency require adherence to Supplemental Standard Terms and Conditions relevant to any award hereunder, such conditions will be included for review and approval as a condition of any amendment or task order.

3.2. Procurement of Recovered Materials

Contractor and any subcontractors agree to comply with Section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act, and the regulatory provisions of 40 CFR Part 247. In the performance of this contract and to the extent practicable, the Contractor and subcontractors are to use products containing the highest percentage of recovered materials for items designated by the Environmental Protection

Agency (EPA) under 40 CFR Part 247 whenever:

1) The contract requires procurement of $10,000 or more of a designated item during the fiscal year; or

2) The contractor has procured $10,000 or more of a designated item using Federal funding during the previous fiscal year.

The list of EPA-designated items is available at www.epa.gov/smm/comprehensive-procurement-guidelines-construction-products.

Section 6002(c) establishes exceptions to the preference for recovery of EPA-designated products if the contractor can demonstrate the item is:

9 | P a g e

a) Not reasonably available within a timeframe providing for compliance with the contract performance schedule;

b) Fails to meet reasonable contract performance requirements; or

c) Is only available at an unreasonable price.

3.3. Debarment and Suspension

Contractor as part of the procurement response, Attachment “A” has submitted to the County a certification that

Contractor and its principals, if applicable, are not presently debarred or suspended by any Federal department or agency from participating in this transaction. Contractor now agrees to verify, to the extent applicable, that for each lower tier subcontractor that exceeds $25,000 as a “covered transaction” under the Services to be provided is not presently disbarred or otherwise disqualified from participating in the federally assisted services. The

Contractor agrees to accomplish this verification by:

1) Checking the System for Award Management at website: http://www.sam.gov.

2) Collecting a certification statement similar to the Certification of Offeror/Bidder Regarding Debarment, above.

3) Inserting a clause or condition in the covered transaction with the lower tier contract.

3.4. Minority/Women’s Business Enterprises

Contractor must take all necessary affirmative steps to assure that minority businesses, women’s business enterprises, and labor surplus area firms are used when possible, in accordance with 2 CFR 200.321. If subcontracts are to be let, prime contractor will require compliance by all sub-contractors. Information regarding certified

M/WBE firms can be obtained from (the following list is not exhaustive):

• Florida Department of Management Services (Office of Supplier Diversity);

• Florida Department of Transportation;

• Minority Business Development Center in most large cities; and

• Local Government M/DBE programs in many large counties and cities.

3.5. Special Conditions – Additional Federal Requirements

As some or all of the Services to be provided under this Agreement may be funded with federal funds. Contractor agrees to adhere to the required additional federal requirements set forth in Attachment “E” and incorporated herein by reference.

3.6. Grant or Agreement Requirements

Through the course of this Agreement the County may be awarded state or federal grants that may fund some or all of the Services to be provided under this agreement. Contractor will be provided a copy of the executed grant agreement should one be awarded for all or part of the project and agrees to comply with all the requirements of the grant agreement.

3.7. Access to Records. The following access to records requirements apply to this contract

1. The Contractor agrees to provide (insert name of state agency or local or Indian tribal government), (insert name of recipient), the FEMA Administrator, the Comptroller General of the United States, or any of their authorized representatives access to any books, documents, papers, and records of the Contractor which are http://www.sam.gov/

10 | P a g e directly pertinent to this contract for the purposes of making audits, examinations, excerpts, and transcriptions.

2. The Contractor agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

3. The Contractor agrees to provide the FEMA Administrator or his authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

4. In compliance with the Disaster Recovery Act of 2018, the (write in name of the non- federal entity) and the Contractor acknowledge and agree that no language in this contract is intended to prohibit audits or internal reviews by the FEMA Administrator or the Comptroller General of the United States.

The contractor shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA pre- approval.

This is an acknowledgement that FEMA financial assistance will be used to fund all or a portion of the contract. The contractor will comply with all applicable Federal law, regulations, executive orders, FEMA policies, procedures, and directives.

The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the non-

Federal entity, contractor, or any other party pertaining to any matter resulting from the contract.

The Contractor acknowledges that 31 U.S.C. Chap. 38 (Administrative Remedies for False Claims and Statements) applies to the Contractor’s actions pertaining to this contract.

3.8. System of Award Management (SAM)

All respondents must be registered with the Federal System of Award Management (SAM) and be up to date on all registration of requirements at the time of contract award. Noncompliance will result in no award of contract for this submission.

3.9. Procurement of Recovered Materials

All respondents must comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource

Conservation and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the Environmental Protection Agency (EPA) at 40 CFR part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement program for procurement of recovered materials identified in the EPA guidelines.

3.10. Domestic preference

Although the County has no local preference, in accordance with 2CFR 200.322, the County may consider preference for the use of products and materials produced in the United States.

3.11. Contract with the Enemy

In accordance with 2CFR 200.215, it is acknowledged that no services under this contract are to be performed outside the United States and its territories nor in support of a contingency operation in which members of the

Armed Forces are actively engaged in hostilities.

11 | P a g e

3.12. Unauthorized Aliens/Patriot's Act

Knowing employment by respondent or its subcontractors of any alien not authorized to work by the immigration laws is prohibited and shall be a default of the contract. If the respondent is notified or becomes aware of such default, the respondent shall take steps as are necessary to terminate said employment with 24 hours of notification or actual knowledge that an alien is being employed. Respondent's failure to take such steps as are necessary to terminate the employment of any said alien within 24 hours notification or actual knowledge that an alien is being employed shall be grounds for immediate termination of the contract. Respondent shall take all commercially reasonable precautions to ensure that it and its subcontractors do not employ persons who are not authorized to work by the immigration laws.

3.13. Protection of Resident Workers

The Santa Rosa County Board of County Commissioners actively supports the immigration and Nationality Act (INA) which includes provisions addressing employment eligibility, employment verifications, and nondiscrimination.

Under the INA, employers may hire only persons who may legally work int he United States (i.e., citizens and nationals of the U.S.) and aliens authorized to work in the U.S. The employer must verify the identity and employment eligibility of anyone hired, which includes completing the Employment Eligibility Verifications. The respondent shall establish appropriate procedures and controls so no services or products under the Contract

Documents will be performed or manufactured by any worker who is not legally eligible to perform such services or employment. Santa Rosa County reserves the right to request documentation shoeing compliance with the requirements.

Respondents doing construction business with Santa Rosa County are required to use the Federal Government

Department of Homeland Security's website and use the E-Verify Employment Eligibility Verifications System to confirm eligibility of all employees to work in the United States.

3.14. Buy America (Build America, Buy America Act (Public Law 117-58, 29 U.S.C. § 50101.

Executive Order 14005)

Applies to purchases of iron, steel, manufactured products and construction materials permanently incorporated into infrastructure projects, where federal grant funding agency requires it or if the grant funds which may come from any federal agency, but most commonly: the U.S. Environmental Protection Agency (EPA), the U.S. Federal

Transit Administration (FTA), the US Federal Highway Administration (FHWA), the U.S. Federal Railroad

Administration (FRA), Amtrack and the U.S. Federal Aviation Administration (FAA). Requirement: All iron, steel, manufactured products and construction materials used under a federally grant funded project must be produced in the United States. Additional requirements may apply depending on the Federal Granting Agency provisions.

Proposers shall be required to submit a completed Buy America Certificate with this procurement, an incomplete certificate may deem the proposer’s submittal non-responsive.

3.15. Equal Employment Opportunity (2 CFR Part 200, Appendix II(C); 41 CFR § 61-1.4; 41 CFR 61-4.3; Executive Order 11246).

During the performance of this contract, the Contractor agrees as follows:

(1) The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to their race, color, religion, sex, sexual orientation, gender identify, or national origin. Such action shall include, but not be limited to, the following:

employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff, or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees

12 | P a g e to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.

(2) The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive considerations for employment without regard to race, color, religion, sex, or national origin.

(3) The Contractor will send to each labor union or representative of workers with which it has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers’ representatives of the Contractor’s commitments under this section and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

(4) The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.

(5) The Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.

(6) In the event of the Contractor’s noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.

(7) The Contractor will include the portion of the sentence immediately preceding paragraph (1) and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The Contractor will take such action with respect to any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions, including sanctions for noncompliance: Provided, however, that in the event a contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency the Contractor may request the United States to enter into such litigation to protect the interests of the United

States.

3.16. § 200.322 Domestic preferences for procurements

(a) The recipient or subrecipient should, to the greatest extent practicable and consistent with law, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States

(including but not limited to iron, aluminum, steel, cement, and other manufactured products). The requirements of this section must be included in all subawards, contracts, and purchase orders under Federal awards.

(b) For purposes of this section:

(1) “Produced in the United States” means, for iron and steel products, that all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

(2) “Manufactured products” means items and construction materials composed in whole or in part of non-ferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe; aggregates such as concrete; glass, including optical fiber; and lumber.

13 | P a g e

(c) Federal agencies providing Federal financial assistance for infrastructure projects must implement the Buy

America preferences set forth in 2 CFR part 184.

3.17. § 200.216 Prohibition on certain telecommunications and video surveillance equipment or services.

(a) Recipients and subrecipients are prohibited from obligating or expending loan or grant funds to:

(1) Procure or obtain covered telecommunications equipment or services;

(2) Extend or renew a contract to procure or obtain covered telecommunications equipment or services; or

(3) Enter into a contract (or extend or renew a contract) to procure or obtain covered telecommunications equipment or services.

(b) As described in section 889 of Public Law 115-232, “covered telecommunications equipment or services” means any of the following:

(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);

(2) For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua

Technology Company (or any subsidiary or affiliate of such entities);

(3) Telecommunications or video surveillance services provided by such entities or using such equipment;

(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the

Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal

Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country;

(c) For the purposes of this section, “covered telecommunications equipment or services” also include systems that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

(d) In implementing the prohibition under section 889 of Public Law 115-232, heads of executive agencies administering loan, grant, or subsidy programs must prioritize available funding and technical support to assist affected businesses, institutions, and organizations as is reasonably necessary for those affected entities to transition from covered telecommunications equipment or services, to procure replacement equipment or services, and to ensure that communications service to users and customers is sustained.

(e) When the recipient or subrecipient accepts a loan or grant, it is certifying that it will comply with the prohibition on covered telecommunications equipment and services in this section. The recipient or subrecipient is not required to certify that funds will not be expended on covered telecommunications equipment or services beyond the certification provided upon accepting the loan or grant and those provided upon submitting payment requests and financial reports.

(f) For additional information, see section 889 of Public Law 115-232 and § 200.471.

https://www.ecfr.gov/current/title-2/part-184 https://www.govinfo.gov/link/plaw/115/public/232 https://www.govinfo.gov/link/plaw/115/public/232 https://www.govinfo.gov/link/plaw/115/public/232 https://www.ecfr.gov/current/title-2/section-200.471

14 | P a g e

3.18. PART 401—RIGHTS TO INVENTIONS MADE BY NONPROFIT ORGANIZATIONS AND

SMALL BUSINESS FIRMS UNDER GOVERNMENT GRANTS, CONTRACTS, AND

COOPERATIVE AGREEMENTS

Authority:35 U.S.C. 206; DOO 30-2A.

Source:52 FR 8554, Mar. 18, 1987, unless otherwise noted.

§ 401.1 Scope.

1. (a) Traditionally there have been no conditions imposed by the government on research performers while using private facilities which would preclude them from accepting research funding from other sources to expand, to aid in completing or to conduct separate investigations closely related to research activities sponsored by the government. Notwithstanding the right of research organizations to accept supplemental funding from other sources for the purpose of expediting or more comprehensively accomplishing the research objectives of the government sponsored project, it is clear that the ownership provisions of these regulations would remain applicable in any invention “conceived or first actually reduced to practice in performance” of the project. Separate accounting for the two funds used to support the project in this case is not a determining factor.

(1) To the extent that a non-government sponsor established a project which, although closely related, falls outside the planned and committed activities of a government-funded project and does not diminish or distract from the performance of such activities, inventions made in performance of the non-government sponsored project would not be subject to the conditions of these regulations. An example of such related but separate projects would be a government sponsored project having research objectives to expand scientific understanding in a field and a closely related industry sponsored project having as its objectives the application of such new knowledge to develop usable new technology. The time relationship in conducting the two projects and the use of new fundamental knowledge from one in the performance of the other are not important determinants since most inventions rest on a knowledge base built up by numerous independent research efforts extending over many years. Should such an invention be claimed by the performing organization to be the product of non-government sponsored research and be challenged by the sponsoring agency as being reportable to the government as a “subject invention”, the challenge is appealable as described in § 401.11(d).

(2) An invention which is made outside of the research activities of a government-funded project is not viewed as a

“subject invention” since it cannot be shown to have been “conceived or first actually reduced to practice” in performance of the project. An obvious example of this is a situation where an instrument purchased with government funds is later used, without interference with or cost to the government funded project, in making an invention all expenses of which involve only non-government funds.

2. (b) This part implements 35 U.S.C. 202 through 204 and is applicable to any funding agreement with a nonprofit organization or small business firm as defined by 35 U.S.C. 201, except for an agreement made primarily for educational purposes under 35 U.S.C. 212. This part also applies to any funding agreement with business firms regardless of size in accordance with section 1, paragraph (b)(4) of Executive Order 12591, as amended by

Executive Order 12618, unless directed otherwise pursuant to NASA or DOE vesting statutes.

3. (c) This regulation supersedes OMB Circular A-124 and shall take precedence over any regulations or other guidance dealing with ownership of inventions made by businesses and nonprofit organizations which are inconsistent with it. Only deviations requested by a contractor and not inconsistent with Chapter 18 of Title 35, United States Code, may be made without approval of the Secretary. Modifications or tailoring of clauses as authorized by § 401.5 or 401.3, when alternate provisions are used under § 401.3(a)(1) through (6), are not considered deviations requiring the Secretary's approval.

4. (d) This part is not intended to apply to arrangements under which nonprofit organizations, small business firms, or others are allowed to use government-owned research facilities and normal technical assistance provided to users of those facilities, whether on a reimbursable or nonreimbursable basis. This part is also not intended to apply to arrangements under which sponsors reimburse the government or facility contractor for the contractor employee's time in performing work for the sponsor. Such arrangements are not considered “funding agreements”

15 | P a g e as defined at 35 U.S.C. 201(b) and § 401.2(a).

[88 FR 17735, Mar. 24, 2023]

§ 401.2 Definitions.

In addition to the definitions in 35 U.S.C. 201, as used in this part—

5. (a) The term funding agreement means any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or research work funded in whole or in part by the Federal government. This term also includes any assignment, substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph.

6. (b) The term contractor means any person, small business firm or nonprofit organization, or, as set forth in section 1, paragraph (b)(4) of Executive Order 12591, as amended, any business firm regardless of size, which is a party to a funding agreement.

7. (c) The term invention means any invention or discovery which is or may be patentable or otherwise protectable under Title 35 of the United States Code, or any novel variety of plant which is or may be protectable under the Plant Variety Protection Act (7 U.S.C. 2321 et seq.).

8. (d) The term subject invention means any invention of a contractor conceived or first actually reduced to practice in the performance of work under a funding agreement; provided that in the case of a variety of plant, the date of determination (as defined in section 41(d) of the Plant Variety Protection Act, 7 U.S.C. 2401(d)) must also occur during the period of contract performance.

9. (e) The term practical application means to manufacture in the case of a composition of product, to practice in the case of a process or method, or to operate in the case of a machine or system; and, in each case, under such conditions as to establish that the invention is being utilized and that its benefits are, to the extent permitted by law or government regulations, available to the public on reasonable terms.

10. (f) The term made when used in relation to any invention means the conception or first actual reduction to practice of such invention.

11. (g) The term small business firm means a small business concern as defined at section 2 of Pub. L. 85-536 (15

U.S.C. 632) and implementing regulations of the Administrator of the Small Business Administration. For the purpose of this part, the size standards for small business concerns involved in government procurement and subcontracting at 13 CFR 121.5 will be used.

12. (h) The term nonprofit organization means universities and other institutions of higher education or an organization of the type described in section 501(c)(3) of the Internal Revenue Code of 1954 (26 U.S.C. 501(c) and exempt from taxation under section 501(a) of the Internal Revenue Code (26 U.S.C. 501(a)) or any nonprofit scientific or educational organization qualified under a state nonprofit organization statute.

13. (i) The term Chapter 18 means Chapter 18 of Title 35 of the United States Code.

14. (j) The term Secretary means the Director of the National Institute of Standards and Technology.

15. (k) The term electronically filed means any submission of information transmitted by an electronic system.

16. (l) The term electronic system means a software-based system approved by the agency for the transmission of information.

17. (m) The term patent application or “application for patent” may be the following:

(1) A United States provisional application as defined in 37 CFR 1.9(a)(2) and filed under 35 U.S.C. 111(b); or

(2) A United States nonprovisional application as defined in 37 CFR 1.9(a)(3) and filed under 35 U.S.C. 111(a); or

(3) A patent application filed in a foreign country or an international patent office; or

(4) An application for a Plant Variety Protection certificate.

18. (n) The term initial patent application means, as to a given subject invention:

(1) The first United States provisional application as defined in 37 CFR 1.9(a)(2) and filed under 35 U.S.C. 111(b); or

(2) The first United States nonprovisional application as defined in 37 CFR 1.9(a)(3) and filed under 35 U.S.C. 111(a);

16 | P a g e or

(3) The first patent application filed under the Patent Cooperation Treaty as defined in 37 CFR 1.9(b); or

(4) The first application for a Plant Variety Protection certificate.

19. (o) The term statutory period means the one-year period before the effective filing date of a claimed invention in a patent application during which exceptions to prior art exist per 35 U.S.C. 102(b) as amended by the

Leahy-Smith America Invents Act, Public Law 112-29.

[52 FR 8554, Mar. 18, 1987, as amended at 60 FR 41812, Aug. 14, 1995; 78 FR 4766, Jan. 23, 2013; 83 FR 15958, Apr. 13, 2018; 88 FR 17735, Mar. 24, 2023]

§ 401.3 Use of the standard clauses at § 401.14.

20. (a) Each funding agreement awarded to a contractor (except those subject to 35 U.S.C. 212) shall contain the clause found in § 401.14 with such modifications and tailoring as authorized or required elsewhere in this part.

However, a funding agreement may contain alternative provisions—

(1) When the contractor is not located in the United States or does not have a place of business located in the

United States or is subject to the control of a foreign government; or

(2) In exceptional circumstances when it is determined by the agency that restriction or elimination of the right to retain title to any subject invention will better promote the policy and objectives of Chapter 18 of Title 35 of the

United States Code; or

(3) When it is determined by a government authority which is authorized by statute or executive order to conduct foreign intelligence or counterintelligence activities that the restriction or elimination of the right to retain title to any subject invention is necessary to protect the security to such activities; or

(4) When the funding agreement includes the operation of the government-owned, contractor-operated facility of the Department of Energy primarily dedicated to that Department's naval nuclear propulsion or weapons related programs and all funding agreement limitations under this subparagraph on the contractor's right to elect title to a subject invention are limited to inventions occurring under the above two programs; or

(5) If any part of the contract may require the contractor to perform work on behalf of the Government at a

Government laboratory under a Cooperative Research and Development Agreement (CRADA) pursuant to the statutory authority of 15 U.S.C. 3710a; or

(6) If the contract provides for services and the contractor is not a nonprofit organization and does not promote the commercialization and public availability of subject inventions pursuant to 35 U.S.C. 200.

21. (b) When an agency exercises the exceptions at paragraph (a)(2), (3), (5), or (6) of this section, it shall use the standard clause at § 401.14 with only such modifications as are necessary to address the exceptional circumstances or concerns which led to the use of the exception. For example, if the justification relates to a particular field of use or market, the clause might be modified along lines similar to those described in paragraph (c) of this section. In any event, the clause should provide the contractor with an opportunity to receive greater rights in accordance with the procedures at § 401.15. When an agency justifies and exercises the exception at paragraph (a)(2) of this section and uses an alternative provision in the funding agreement on the basis of national security, the provision shall provide the contractor with the right to elect ownership to any invention made under such funding agreement as provided by the Standard Patent Rights Clause found at § 401.14 if the invention is not classified by the agency within six months of the date it is reported to the agency, or within the same time period the Department of Energy does not, as authorized by regulation, law or Executive order or implementing regulations thereto, prohibit unauthorized dissemination of the invention. Contracts in support of DOE's naval nuclear propulsion program are exempted from this paragraph (b).

22. (c) When the Department of Energy (DOE) determines to use alternative provisions under…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .