About this file
This is an Invitation to Bid (ITB) document issued by Truebeck Construction as the general contractor for a tenant improvement project at 1450 Owens Street in San Francisco, administered by the Office of Community Investment and Infrastructure (OCII). The project encompasses a 77,000 square foot Lab Office tenant improvement with a Vivarium at Level 1, requiring bids for six trade packages: Finish Carpentry, Demountable Partitions, Window Coverings, Carpet & Wood Flooring, Specialty Ceilings & Wall Panels, and Final Clean. A voluntary pre-bid conference is scheduled for Friday, July 17, 2026 at 10:00 AM PST via Webex. Questions must be submitted by Monday, July 20, 2026 at 5:00 PM PST, with prequalification questionnaires due by Monday, August 3, 2026 at 2:00 PM PST and final bids due on Tuesday, August 4, 2026 at 2:00 PM PST, all sent to Nicole.Mestice@Truebeck.com. The project is scheduled to commence in September 2026. Prospective bidders must submit the Initial Prequalification Questionnaire to access complete project documents.
The project is subject to the OCII's 50% Small Business Enterprise (SBE) participation goal for both subcontractors and suppliers, with priority given to SBEs and Local Business Enterprises (LBEs) certified by the City and County of San Francisco, the State of California, or other jurisdictions meeting size standards. The project is also governed by OCII's Construction Workforce Policy requiring 50% San Francisco resident participation calculated by work hours for each trade, prevailing wage requirements with certified payroll submission, and the Mission Bay Project Labor Agreement. SBE firms are encouraged to submit bids and must include valid SBE or LBE certification letters. Selected subcontractors are required to attend a preconstruction meeting with Truebeck, OCII, and the San Francisco Office of Economic and Workforce Development's CityBuild Division prior to commencing onsite work. All bidders must possess a current and valid California Contractor License and demonstrate financial capacity to perform their proposed work scope.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EXT_CII___ITB_Gladstone_Lab_TI_Bid_Package_3.pdf | ||
| EXT_CII___ITB_Gladstone_Lab_TI_Bid_Package_3.xml | XML file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
Gladstone Lab Tenant Improvement - 1450 Owens Street
San Francisco, CA July 7, 2026
Truebeck Construction (General Contractor) is requesting bids for the following trades:
Finish Carpentry Demountable Partitions Window Coverings Carpet & Wood Flooring Specialty Ceilings & Wall Panels Final Clean
SBE firms are encouraged to submit bids. This project has a 50% SBE Participation for subcontractors and suppliers.
Prequalification, Bid Date and Time:
If you would like access to the Project Documents, please reach out to Nicole.Mestice@Truebeck.com
Voluntary Pre-Bid Conference: Friday, July 17th, 2026 10:00AM PST
Webex Video Conference Link:
https://truebeckconstruction.webex.com/truebeckconstruction/j.php?MTID=m73a0141a505 b5f7cb64b297396da7908
Questions Due by: Monday, July 20th, 2026 at 5:00PM PST Email to: Nicole.Mestice@Truebeck.com
Bid Due Date: Tuesday, August 4th, 2026 at 2:00PM PST
Prequalification: Please submit the Initial Prequalification Questionnaire (Last Page of this Document) with your proposal no later than Monday, August 3rd, 2026 at 2:00PM PST.
All prequalifications, questions and bids should be emailed to Nicole.Mestice@truebeck.com
Schedule: Project is scheduled to start September 2026
Project Description:
The project is located at 1450 Owens St. The project consists of a 77,000 SF Lab Office TI with a Vivarium at Level 1.
mailto:Nicole.Mestice@Truebeck.com https://truebeckconstruction.webex.com/truebeckconstruction/j.php?MTID=m73a0141a505b5f7cb64b297396da7908 https://truebeckconstruction.webex.com/truebeckconstruction/j.php?MTID=m73a0141a505b5f7cb64b297396da7908 mailto:Nicole.Mestice@truebeck.com
The project is administered by the Office of Community Investment and Infrastructure, (OCII) and the agency’s Small Business Enterprise (SBE), Construction Workforce and prevailing Wage policies apply.
This project is also subject to the Mission Bay Project Labor Agreement (PLA).
Bid Documents:
In order to receive a complete set of Owner’s plans, specifications, and bid documents please submit the prequalification (last page of this document)
Nicole Mestice – Nicole.Mestice@Truebeck.com
Program in Diversity: SBE Subcontracting and Workforce Participation Goals:
The Owner of the project has committed to meeting the Office of Community Investment and Infrastructure (OCII) non-discrimination and equal opportunity hiring & local work force hiring participation goals. These equal opportunity program documents are part of the project documents and provided for review. These documents will be included as Contract documents in all subcontracts. In general, the project goals can be summarized as follows:
Small Business Enterprise Program:
This project is subject to OCII’s 50% Small Business Enterprise Policy (SBE Policy) which sets a 50% SBE participation goal for Construction, Professional Services, and Supplier contractors and subcontractors. First consideration for all relevant contracts and subcontracts shall be given in the following order: 1). SBEs/LBEs in Project Area, 2); Other San Francisco based SBEs/LBEs; 3).
Non-San Francisco-based SBEs which should be used to satisfy the 50% SBE participation goal only if San Francisco-based SBEs are not available, qualified, or if their bids or fees are significantly higher. To count towards the SBE goal, a business must be certified by the City and County of San Francisco’s Monitoring Division, the State of California or any other jurisdiction, so long as size standards are met. OCII will make the final determination on the consistency of the certification standards and acceptance or denial of certifications listed above. Please include your SBE or LBE Certification letter with your bid. There is also a 50% SBE goal for suppliers therefore list the involvement of any suppliers or lower tier-subcontractors that may be included in your bid as well as their SBE/LBE.
For more information on the SBE certification process with the City and County of San Francisco, please visit the following site:
https://www.sf.gov/14b-local-business-enterprise-lbe-program
For more information on the SBE Policy, and other OCII Policies, please visit the following site: https://sfocii.org/policies-and-procedures
Please contact Maria Pecot, Contract Compliance Specialist for additional information at Maria.Pecot@sfgov.org
Construction Workforce Policy:
mailto:Maria.Pecot@sfgov.org
This project is subject to OCII’s construction workforce program requirements of 50% San Francisco resident participation goal, which has calculated by work hours for each construction trade. See the Construction Workforce Policy for further information on the work force goals.
Prevailing Wage Provisions:
This project is subject to the OCII’s Prevailing Wage Policy (Labor Standards) and submission of certified payroll. These documents are also provided.
Preconstruction Meeting:
Selected subcontractors shall be required to attend a preconstruction meeting with Truebeck, OCII and the San Francisco Office of Economic and Workforce Development’s CityBuild Division. This meeting must be held prior to commencement of any subcontractor’s work onsite.
Project Labor Agreement:
This project is subject to the Mission Bay Project Labor Agreement.
Prequalification Questionnaire for 1st Tier Subcontractors Please fill out the following and submit to Nicole.Mestice@Truebeck.com
1) Firm Name :
2) Form Submitted By (Name/Title/Date) :
3) Bid Package Inquired to Obtain:
4) Street Address/City/State/Zip:
5) Phone / Fax :
6) How many years has your company been in business?:
7) List of preferred locations of work (by Counties):
8) Have you ever worked for Truebeck Construction in the past? (CircleOne) YES NO
9) How many people does your firm presently employ in the following categories :
a) Corporate :
b) Field Supervisory :
c) Trades People :
d) Other :
10) Please list all labor agreement commitments :
Union Local State
11) Please state your firm’s current and valid California Contractor License:
12) What trades do you normally subcontract? Please indicate separately each specification section which you are qualified to perform. Indicate the dollar amount which you are financially able to handle, bond andbid competitively.
Spec# Trade Name Subcontractor Max Value Spec# Trade Name Subcontractor Max Value
13) The value of your expected Revenue this year:
14) How many project comprise the value of this year expected Revenue:
15) Is your company a SBE/LBE qualified company? (CircleOne) YES NO
16) If your company qualifies as a SBE/LBE/MBE/WBE company, please list the certifications below :
Type of Certificate Certifying Agency Expiration Date
File details come from the government source that posted it. Updated .