General_and_Special_Provisions_-_Compiled_20221202_(2).pdf

PDF 608 KB Posted

Attached to
Frazier Street Steps Construction
Solicitation number
2022-IFB-285
Issued by
Allegheny County, Pennsylvania

About this file

The document is a compiled set of General and Special Provisions for the Frazier Street Stairs Construction project by the City of Pittsburgh's Department of Mobility and Infrastructure. The project involves removing the existing deteriorating concrete stairs connecting Bates Street, Frazier Street, and Romeo Street, and constructing new concrete stairs along a new alignment. The new stairs will consist of cast-in-place jumper walk stairs and elevated precast stairs, located near the I-376 interchange in the South Oakland neighborhood. The work includes tasks such as traffic control planning, construction surveying, clearing and grubbing, demolition of existing stairs, excavation, foundation and column construction, installation of precast stair sections, placement of engineered fill, construction of jumper walk steps and sidewalk, and fabrication and installation of hand railings and bike runnels.

The special provisions outline detailed specifications for various components of the project, including materials, construction methods, measurement, and payment. Key materials include Class AAA cement concrete, stainless steel or aluminum railings, and specific aggregates. The provisions emphasize precise requirements for concrete mixing, reinforcement, protective coatings, and installation techniques. The project requires compliance with PennDOT standards and City of Pittsburgh specifications, with careful attention to aesthetic and functional details such as using white cement, specific aggregate colors, and ADA-compliant railing designs. The contract appears to be funded by the City of Pittsburgh and will require detailed engineering and construction expertise to meet the specified standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREFACE TO CONTRACT SPECIAL PROVISIONS

Special Provisions for the Frazier Street Stairs Contract reference the Pennsylvania Department of transportation (PennDOT) Publication 408, 2020 through Change No. 5, effective October 7, 2022, as located online as follows:

https://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2020/408_2020_5/408 _2020_5.pdf

Section references and specific paragraph references in the Contract Special Provisions correspond to Publication 408. Notations indicated in the Contract Special Provisions as “add the following”, “revise as follows”, or other similar notations mean that the referenced section or paragraph in Publication 408 is being modified by adding, revising, or as otherwise stated.

The first four digits of item numbers refer to the section number in Publication 408 that provides the corresponding specification for the work. In this case, the PennDOT standard specification govern the work that is to be performed. When the first number begins with a “4”, this indicates that the following three numbers refer to a section number and it is being modified. When the first number begins with a "5", this indicates that the following three numbers refer to a section number that begins with a 1 and it is being modified. When the first four digits of the item number begin with an “8” or “9”, the work is governed by the special provision.

https://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2020/408_2020_5/408_2020_5.pdf https://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2020/408_2020_5/408_2020_5.pdf

Frazier Street Stairs Description of Work Section 0030 0030-1

SECTION 0030

DESCRIPTION OF WORK

REPLACEMENT OF FRAZIER STREET STAIRS

4TH WARD – CITY OF PITTSBURGH

ALLEGHENY COUNTY, PENNSYLVANIA

This work is to remove the existing deteriorating concrete stairs that connect Bates Street, Frazier Street, and Romeo Street, and to construct new concrete stairs (along a new alignment).

The new stairs consist of a combination of cast-in-place jumper walk stairs and elevated precast stairs. The project is located near the intersection of Bates Street and the I-376 interchange in the South Oakland neighborhood in the 4th Ward of the City of Pittsburgh.

The existing concrete stairs ascend approximately 75 feet in elevation from Bates Street (approximately 250 feet north of its intersection with the I-376 westbound off-ramp) to the west end of Frazier Street. At about the midpoint of the stairs, a second set of stairs ascend approximately 50 feet in elevation to the south end of Romeo Street. The existing elevated concrete stair stringers and platforms rest on concrete piers that are believed to be supported by shallow spread footings, although no design drawings or construction drawings of the existing stairs are available.

The proposed stairs will be accessed off Bates Street approximately 200 feet south of the existing stairway access point and will ascend to Frazier Street through vacant City properties. Based on historical maps and photographs, the vacant properties were once occupied by residential structures. The proposed concrete stairs will be constructed using a combination of on-grade cast-in-place jumper walk stairs and elevated precast stairs. The import and placement of engineered fill (AASHTO No. 1’s) will be required to accommodate the proposed grade of the jumper walk stairs. The precast elevated stairs will be supported by cast-in-place columns and shallow spread footings. Due to the presence of highly weathered claystone and “red beds” on the slope below Frazier Street, the subgrade beneath the spread footings will likely require several feet (or more) of undercut and AASHTO No. 1 backfill.

The work will generally consist of the following tasks:

• Design and implementation of a traffic control plan.

• Construction surveying.

• Installation of compost filter sock and rock construction entrance.

• Clearing and grubbing within the immediate work area.

• Demolition/disposal of existing concrete stairs.

• Class 3 excavation for jumper walk stairs and elevated stair footings.

• Construction of cast-in-place foundations, columns, and landings.

• Installation of precast stair sections.

• Preparation of subgrade and placement of engineered fill (AASHTO. No. 1).

• Construction of on-grade cast-in-place jumper walk steps and sidewalk.

• Fabrication and installation of hand railings and bike runnels.

• Removal of E&S Controls and site restoration.

Frazier Street Stairs Description of Work Section 0030 0030-2

ALL WORK IS TO OCCUR IN ACCORDANCE WITH THE CONTRACT DRAWINGS

AND SPECIFICATIONS.

ALTERNATIVE METHODS WILL ONLY BE CONSIDERED AFTER THE BID

OPENING. THE CITY OF PITTSBURGH IS NOT OBLIGATED TO ACCEPT

ALTERNATIVE METHODS OR VALUE ENGINEERED SOLUTIONS.

END OF DESCRIPTION OF WORK

Frazier Street Stairs Control of Material Section 0106 0106-1

SECTION 0106

CONTROL OF MATERIAL

In accordance with Section 0106 and as follows:

106.03(b)1Responsibility.

Add the following to the first paragraph:

The following table identifies materials for the Project and the party(ies) responsible for sampling and testing, or certification.

Item/Section and

Material

Quality Control Testing by Contractor

Acceptance Testing by

Owner/Owner’s Representative

Manufacturer’s or Supplier’s

Certification

Aggregate X

- Subbase X X

Cement Concrete X X

Reinforcing Steel X

Precast Concrete X

Polyethylene Pipe X

Geotextile X

Seed and Soil Supplements *

Topsoil X

* Certification by the Pennsylvania Department of Agriculture, Bureau of Plant Industry.

Include costs for tests and certifications in the bid price for the bid items on the Schedule of Prices.

Provide a copy of each certification for each item requiring certification to the City’s representative at the time of material delivery to the site, and one (1) copy of each certification for each item to the Owner’s Engineer for approval at least 2 weeks prior to delivery of material to the site.

END OF SPECIAL PROVISION

Frazier Street Stairs Aggregate Section 0703 0703-1

SECTION 0703

AGGREGATE

In accordance with Section 0703 and as follows:

703.1(a) 2. Manufactured Sand.

Delete section

703.1(b) Production Testing.

Delete section

703.2(a) 3. Blast Furnace Slag.

Delete section

703.2(a)4. Steel Slag.

Delete section

703.2(a)5. Granulated Slag.

Delete section

703.2(b). Production Testing.

Delete section

703.2(c) 1. Soundness.

Delete the following sentence:

703.3(a). General.

Delete the following words in the first sentence: “or slag”

Frazier Street Stairs Structure Demolition, Modified Item 4202-0001 4202-1

ITEM 4202-0001 – STRUCTURE DEMOLITION, MODIFIED

In accordance with Section 202 and as follows:

202.1 DESCRIPTION – Add the following:

This work includes the demolition, sorting, and disposal of the existing concrete steps from Bates Street to Romeo and Frazier Streets. This work also includes partial removal of an existing deteriorated brick retaining wall along the proposed steps alignment to allow for installation of a new stormwater inlet and culvert.

202.3 CONSTRUCTION – Add the following:

Prior to existing stair demolition and excavation, sample, and test railing paint for lead. If lead is found, excavate and test concrete and soil areas centered below railing measuring two feet in width and one foot deep. If lead levels exceed allowable limits for clean fill properly dispose according to PADEP guidelines.

Coordinate with overhead utilities prior to commencing demolition work.

Remove existing stairs and landings to the extents shown on the plans. Excavate and remove foundations to 1 foot (min.) below the ground surface and backfill with suitable material.

Excavation and backfill are considered incidental to this item.

Crush all existing concrete such that the largest dimension is not greater than 18-inches. Remove all existing reinforcing bars and fixtures from crushed concrete.

Dispose of crushed concrete debris at an on-site location designated by the City of Pittsburgh Department of Mobility and Infrastructure.

Dispose of all other debris and waste stair/landing concrete larger than 18-inches, reinforcement materials, etc. in accordance with Section 105.14 regarding waste and borrow areas. Do not place any of these materials in the proposed fill embankment. Excavated soils can be used for backfilling demo excavations, if suitable (free of all concrete, reinforcement, and railing materials and other debris).

Frazier Street Stairs 6” Pipe Underdrain, Type I Backfill, Modified 4610-0002 4610-1

ITEM 4610-0001 – 4” PIPE, JUMPER STAIRS UNDERDRAIN

In accordance with Section 610 except as follows:

610.1 DESCRIPTION – Revise as follows:

This work is installation of 4” corrugated Polyethylene (PE) Pipe, Type SP beneath the jumper stairs.

610.2 MATERIAL – Revise as follows:

610.2(a)1.a Type. – Use Corrugated Polyethylene (PE) Pipe, AASHTO M 252 Type SP

610.3 CONSTRUCTION - Revise as follows:

(a) Pipe. Place pipes in subbase beneath jumper stairs as shown on the contract drawings.

(b) Geotextiles, Class 1. Delete.

610.4 MEASUREMENT AND PAYMENT - Revise as follows:

(a) 4" Pipe Underdrain. Linear Foot

Frazier Street Stairs 6” Pipe Underdrain, Type I Backfill, Modified 4610-0002 4610-1

ITEM 4610-0002 – 6” PIPE UNDERDRAIN, TYPE I BACKFILL, MODIFIED

In accordance with Section 610 except as follows:

610.2 MATERIAL – Revise as follows:

610.2(a)1.a Type. – Use Corrugated Polyethylene (PE) Pipe, AASHTO M 252 Type SP

610.3 CONSTRUCTION - Revise as follows:

(a) Pipe, Trench, and Backfill. Place geotextile against the excavated soil face, as indicated. Place pipe underdrains as shown on the Drawings. Lay the pipe after the lower 2 inches of compacted backfill has been placed. Place geotextile against the excavated soil face, as indicated. Make the joints according to the manufacturer’s recommendations.

For perforated pipe, place the perforations down, unless otherwise directed. Seal the upgrade end of the pipe to prevent entry of foreign material.

Do not leave trenches open during periods of precipitation or overnight.

Within 2 feet of the installed pipe, place AASHTO No. 57 coarse aggregate, Type

I Backfill, in uniform, horizontal layers of not more than 12 inches in depth and compact to 70 percent relative density in accordance with ASTM D4253 requirements.

Complete backfilling with AASHTO No. 57 coarse aggregate, Type I Backfill to the elevations indicated on the drawings. Install Geotextile as indicated on the Drawings.

610.4 MEASUREMENT AND PAYMENT - Revise as follows:

(a) 6" Pipe Underdrain, Type I Backfill. Linear Foot No. 57 Coarse aggregate, underdrain collection pipes (perforated), backfilling, and compaction will be considered incidental to pipe underdrain installation and will not be paid for separately.

(b) Geotextiles, Class 4, Type A. Item 0212-0014

(c) 6” Subsurface Drain Outlets. Item 0615-0022

(d) Subsurface Drain Outlet Endwall. Item 0615-0040

Frazier Street Stairs Concrete Deep Curb, 7” Reveal Item 4630-0041 4630-1

ITEM 4630-0041 - CONCRETE DEEP CURB, 7” REVEAL

In accordance with Section 630 and as follows:

630.1 DESRIPTION – Replace with the following:

This work is the construction of a concrete deep curb with 7” reveal including the procurement of all required materials as indicated on the City of Pittsburgh Standard Drawing SC-100 from the City of Pittsburgh Department of Public Works Right-of-Way Procedures Policy manual revised June 1, 2017 excluding the 4” diameter perforated pipe underdrain.

630.2 MATERIAL – Add the following:

Utilize materials in accordance with City of Pittsburgh Standard Drawing SC-100 from the City of Pittsburgh Department of Public Works Right-of-Way Procedures Policy manual revised June 1, 2017.

630.3 CONSTRUCTION – Add the following:

Construct concrete curb in accordance with City of Pittsburgh Standard Drawing SC-100 from the City of Pittsburgh Department of Public Works Right-of-Way Procedures Policy manual revised June 1, 2017. The reveal of the curb may vary based on existing roadway grades, but in general the curb shall have 7” reveal. Match the existing curb reveal at each end of the project area.

630.4 MEASUREMENT AND PAYMENT – Revise as follows:

(c) Class 1 Excavation. Class 1 excavation is considered incidental to this item and will not be paid for separately.

Frazier Street Stairs 4” Reinforced Cement Concrete Sidewalk Item 4676-0001 4676-1

ITEM 4676-0001 - 4” REINFORCED CEMENT CONCRETE SIDEWALK

In accordance with Section 676 and as follows:

676.1 DESCRIPTION – Add the following sentence:

Welded wire fabric reinforcement, Class 1A excavation, placement of aggregate base and integration of sidewalk with new and existing curbs and sidewalk is incidental to this work. The proposed concrete sidewalk shall match the width of the existing sidewalk at each end of the project area and shall butt up directly to the proposed concrete deep curb. Other than minimum widths, the sidewalk shall be constructed in accordance with the City of Pittsburgh Standard Drawing SC-500 included in the DPW Right-of-Way Procedures and Policy Manual.

676.2 MATERIAL – Revise as follows:

Replace Class A Cement Concrete with Class AA Cement Concrete

Add the following:

• 6” X 6” – W1.4 X 1.4 Welded Wire Fabric

• Air-Entraining Admixture – Section 704

676.3 CONSTRUCTION –Revise as follows:

(e) Expansion Joints.

Add the following Sentence:

Expansion joints shall be installed at an interval no greater than every 15 feet of sidewalk and control joints are to be spaced at 5-foot intervals, as shown on the contract drawings and the City of Pittsburgh Standards of Construction.

676.4 MEASUREMENT AND PAYMENT – Revise as follows:

(b) Class 1A Excavation. Square Yard Class 1A excavation is considered incidental to the construction of the sidewalk and will not be paid for separately.

Frazier Street Stairs Maintenance & Protection of Traffic Item 4901-0001 4901-0001-1

ITEM 4901-0001 –MAINTENANCE & PROTECTION OF TRAFFIC DURING

CONSTRUCTION, MODIFIED

In accordance with Section 901 and as follows:

901.1 DESCRIPTION – Add the following:

This work is the furnishing, installing, maintaining, and protection of traffic adjacent to and within the Work Zone including the Active Work Zone, and relocating of traffic control devices.

It is the Contractor’s responsibility to develop the Traffic Control Plan. The Traffic Control Plan Shall be submitted to the City for approval. The contractor is responsible for securing all permits and coordinating with nearby construction activity and events.

901.3 CONSTRUCTION – Add the following:

Provide two (2) weeks advance notice to affected municipality, emergency services, City of Pittsburgh Police (412-323-7800), City of Pittsburgh Department of Mobility and Infrastructure (412-255-2597), City of Pittsburgh Department of Public Works (412-255-8850), City of Pittsburgh Public Schools (Administration 412-529-4357), Allegheny County Port Authority, Chuck Rompala (412-566-5321). Also provide advance notice to PennDOT, as required.

Obtain an obstruction permit from the City of Pittsburgh Department of Mobility and Infrastructure, Permits Division as needed.

Outline the Active Work Zone with construction fencing and channelizing devices and obtain approval from the Representative on the layout prior to performing any work.

Maintain traffic on Bates Street at all times.

901.4 MEASUREMENT AND PAYMENT – Revise as follows:

(a) Maintenance and Protection of Traffic During Construction. Lump Sum The Department will measure and pay for this item in a proportionate manner based on current estimates. If an item or device is required for maintenance and protection of traffic, the cost of the item or device is incidental.

(b) Design MPT. Item 9000-0006

Frazier Street Stairs Precast Concrete Item 9000-0001 9000-0001-1

ITEM 9000-0001 – PRECAST CONCRETE

DESCRIPTION – This item is for the precast stair sections.

In accordance with Sections 714 and 1001 and as follows:

714.1 GENERAL REQUIREMENTS –

(b) Shop Drawings – Add the following:

Shop drawings and supporting calculations shall be submitted to the City for review and approval prior to fabrication.

Shop drawings shall include all connections of the precast concrete components to cast-in-place components.

Shop drawings must indicate that existing dimensions that relate to the affected work have been field verified before shop drawings can be approved.

714.2 PRECAST CONCRETE UNITS – Add the following:

• Stairs

• Deck Panels

714.3 MATERIAL – Add the following:

• Cement Concrete. Class AAA Cement Concrete per Section 704 except as follows:

1. Use normal weight concrete only.

2. Use minimum 28-day compressive strength of 4,000 psi.

Frazier Street Stairs Precast Concrete Item 9000-0001 9000-0001-2

• Reinforcement Steel. Use epoxy coated or galvanized reinforcement bars or welded wire fabric per Section 709.

714.7 CONCRETE – Add the following:

Apply a broom finish to all walking surfaces of the precast components.

Include a non-slip tread for each step.

Include threaded inserts as indicated for the attachment of the railing posts.

Provide 3/8” radius nosing for all stairs and landing treads.

Grout used to fill lifting loop holes or for patching of precast units should match the color of the cured precast concrete as closely as possible. Submit a sample of cured grout to the Representative for acceptance prior to placing on the completed structure.

714.8 CURING AND PROTECTIVE COATING – Add the following:

(a) Protective Coating. Add the following:

Apply boiled linseed oil to all precast walking surfaces.

MEASUREMENT AND PAYMENT – Lump Sum

Includes delivery and erection.

Frazier Street Stairs Elevated Stair Railing Item 9000-0002 9000-0002-1

ITEM 9000-0002 – ELEVATED STAIR RAILING

DESCRIPTION –

This item is to supply and install the ADA compliant handrail to be post mounted to the side of the landing/stairs.

Manufacturer is to be listed in Bulletin 15 or to comply with sections 105 and 106 for fabrication and be approved for the manufacturing of handrails by the city.

In accordance with Section 1022 – STEEL BRIDGE HAND RAILING or 1023 – ALUMINUM BRIDGE HAND RAILING. Comply with Section 105 and 106 for fabrication and as follows:

MATERIALS – Add the following:

• Handrails and Guardrails: 1½-inch diameter Schedule 40, Type 304 Stainless Steel pipe OR Schedule 40, ASTM B241-Alloy 6061-T6, 6063-T6 or ASTM B429-Alloy 6061-T6, 6063T6 Aluminum pipe suitable for outdoor use.

• Posts: 1½-inch diameter Schedule 80, Type 304 Stainless Steel pipe OR Schedule 80, ASTM B241- Alloy 6061-T6, 6063-T6 or ASTM B429-Alloy 6061-T6, 6063T6 Aluminum pipe suitable for outdoor use,

• Open steel mesh: Stainless steel, Type 304, Woven.

• Mounting plates, frames, and tabs and bolts for connection of frame housing open steel mesh to the posts and railing are to be stainless steel or aluminum.

• Paint and Primer: Use exterior grade latex or acrylic paint and self-etching primer suited for this application and as recommended by the manufacturer. Handrails, guardrails, and posts shall be purple. Open steel mesh shall be lavender. Provide a sample color paint chip for each color of paint indicated to the City Representative for review and approval prior to painting.

CONSTRUCTION –

• As indicated on the plans.

• Railing shall be shop assembled in lengths not to exceed 24 feet for field erection.

• Handrail is to be post mounted to side of landings/stairs. Fabricator to detail connection plate and fasteners per the precast insert locations indicated on the plans.

• Post spacing shall be a maximum of 6’-6”.

• Open steel mesh shall be used between the rails. Welding open steel mesh directly to the rails and posts is not permitted. Open steel mesh must be housed in a frame that is bolted to tabs that are welded to the rails.

• Intermediate railings and open steel mesh shall be provided such that a 4-inch diameter sphere cannot pass through any opening up to a height of 34 inches. From a height of 34 inches to 42 inches above the adjacent walking surface, a sphere 8 inches in diameter shall not pass. The triangular openings formed by the riser, tread, and bottom rail at the open side of a stairway shall be of a size such that a sphere of 6 inches in diameter cannot pass through the opening. Mesh spacing shall prevent climbing.

Frazier Street Stairs Elevated Stair Railing Item 9000-0002 9000-0002-2

• Install expansion joints as directed. Locate expansion joint weld to prevent water intrusion into the railing.

• Posts shall not interrupt the continuation of the top rail at any point along the railing, including corners and end terminations (OSHA 1910.23). The top surface of the top railing shall be smooth and shall not be interrupted by projected fittings.

• Handrails shall be made of pipes. Field sections shall be joined together with component fittings or field welded. Samples of all components, bases, toe plates and pipes shall be submitted for approval at the request of the engineer. Pop-riveted or glued components are unacceptable. All components must be mechanically fastened with stainless steel hardware. Any handrail fasteners must be flush with the railing.

• Guardrails and handrails shall be designed to withstand a 200 lb concentrated load applied in any direction and at point on the top rail. Guardrails and handrails shall also be designed to withstand a uniform load of 50 lb/ft applied horizontally to the top rail.

Uniform loads are not to be applied simultaneously with the concentrated loads.

• Intermediate railings and open steel mesh shall be designed to withstand a horizontally applied normal load of 50 lb on an area not to exceed one square foot including openings and space between rails.

• The mid-rail at a corner return shall be able to withstand a 200 lb load without loosening.

The manufacturer is to determine this dimension for their system and provide physical laboratory tests to confirm compliance.

• The manufacturer shall submit calculations for approval at the request of the engineer.

Testing of base castings or base extrusions by an independent lab or manufacturer’s lab will be an acceptable substitute for calculations. Calculations will be required for approval of all other design aspects. Submit design calculations signed and sealed by a professional engineer registered in the Commonwealth of Pennsylvania.

• Stainless steel surfaces in contact with concrete, grout or dissimilar metals will be protected with a coat of bituminous paint, Mylar isolators or other approved material.

• Prior to ordering, provide shop drawings for guard railings, handrails, posts, mounting plates, mesh, metal frame, and connection of mesh to metal frame/metal frame to posts to the City Representative for review and approval.

• Apply paint and primer in accordance with the manufacturer’s guidelines.

• Install railing and apply touch-up paint as necessary. Installed railing and handrails shall meet specifications for ANSI and ADA.

MEASURMENT AND PAYMENT – Linea1 Foot (LF)

Measured horizontally from center to center of end posts.

Handrail installation includes all posts, handrails, guard rails, open mesh, paint, bolts, anchors, mounting plates, gates, drilling, fittings, and other hardware as required for the final installation of the railings.

Frazier Street Stairs Elevated Stair Bike Runnel Item 9000-0003 9000-0003-1

ITEM 9000-0003 – ELEVATED STAIR BIKE RUNNEL

DESCRIPTION –

This item is to supply and install a bike runnel along the edge of the stairs and landings adjacent to the handrails.

Manufacturer is to be listed in Bulletin 15 and approved for the manufacturing of aluminum channels by the City.

In accordance with Section 1023 and as follows:

MATERIALS –

a) Runnel

i. Channel, C6x13 Aluminum Alloy 6061-T6, or Approved Equal.

ii. Plate, Aluminum Alloy 6061-T6 Plate

d) Bolts, nuts, washers, Section 1105.02(c), (galvanized)

e) Paint and Primer – Use white colored exterior grade latex or acrylic paint and self-etching primer suited for this application and as recommended by the manufacturer.

Provide a sample color paint chip for each color of paint indicated to the City Representative for review and approval prior to painting.

• Prior to installing bike runnel, apply paint and primer in accordance with the manufacturer’s guidelines.

• Install bike runnel at the right side of the steps when looking “UP” the stairway.

• Provide runnel and runnel anchors as shown on the plans.

• Complete installation of the bike runnel, as indicated, and apply touch-up paint as necessary.

• Any construction outside of runnel must allow enough clearance for bike pedals and handlebars without interfering with movement.

MEASURMENT AND PAYMENT – Lineal Foot (LF)

Runnel installation includes all rails, bolts, anchors, drilling, plates, treads, paint/primer, etc.

necessary for the full, final installation of the bicycle runnel.

Frazier Street Stairs 1 ½” Diameter Welded Pipe Railing Item 9000-0004 9000-0004-1

ITEM 9000-0004 – 1 1/2” DIAMETER WELDED PIPE RAILING

DESCRIPTION –

This item is the furnishing and placement of handrail and handrail posts for the jumper stairs, including welding and joints, as directed.

MATERIALS –

• Railing and Posts: 1½-inch diameter Schedule 40, Type 304 Stainless Steel pipe OR Schedule 40, ASTM B241-Alloy 6061-T6, 6063-T6 or ASTM B429-Alloy 6061-T6, 6063T6 Aluminum pipe suitable for outdoor use.

• Grout: Cementitious, non-shrink, non-staining grout from manufacturers listed in Bulletin 15.

• Caulking: Sikaflex 1-A Caulking or equal.

• Paint and Primer: Use purple colored exterior grade latex or acrylic paint and self-etching primer suited for this application and as recommended by the manufacturer.

Provide a sample color paint chip to the City Representative for review and approval prior to painting.

• Install expansion joints as directed. Locate expansion joint weld to prevent water intrusion into the railing.

• Grind all welds smooth prior to painting.

• Prepare surfaces and apply one shop coat of primer after fabrication. Follow the manufacturer’s directions.

• For posts, core a 3” diameter hole or use a 3” diameter PVC sleeve insert, as directed.

When installing posts, mound grout at base of posts to prevent water ponding around column. In situations where the post is mounted in a sleeve, the joint is to be caulked to maintain a watertight seal.

• Apply paint and primer in accordance with the manufacturer’s guidelines. Apply touch-up paint as necessary.

MEASUREMENT AND PAYMENT – Lineal Foot (LF)

Measured horizontally from center to center of end posts. Includes joints, welding, coring of concrete or sleeve inserts for posts, expansion sleeve, paint, and removal/disposal of all surplus material.

Frazier Street Stairs Class AAA Reinforced Cast-in-Place Concrete Item 9000-0005 9000-0005-1

ITEM 9000-0005 – CLASS AAA REINFORCED CAST-IN-PLACE CONCRETE

In accordance with Section 1001 except as follows:

1001.1 DESCRIPTION –

This work is construction of all cast-in place components as indicated.

1001.2 MATERIAL –

(a) Cement Concrete. Class AAA Cement Concrete per Section 704 except as follows:

(b) Reinforcement Steel. Use epoxy coated reinforcement bars or welded wire fabric per Section 709.

(c) Protective Coating. Per Section 1019. Use boiled linseed oil on all non-walking surfaces

(d) Joint Material. Use expansion joint filler and asphalt rubber sealing compound per Section

705.

Frazier Street Stairs Class AAA Reinforced Cast-in-Place Concrete Item 9000-0005 9000-0005-2

1001.3 CONSTRUCTION – In accordance with Section 1001.3 and 1002.3 and as follows:

(a) Section 1001.3(t). Add the following:

Apply boiled linseed oil per Section 1019 to all cast-in-place walking surfaces and cast-in-place landing structures.

1001.4 MEASUREMENT AND PAYMENT – In accordance with Section 1001.4 and as follows:

Epoxy coated reinforcement bars, welded wire fabric, joint material and sealer, and protective coating are incidental to this item.

Frazier Street Stairs Design MPT Item 9000-0006 9000-0006-1

ITEM 9000-0006

DESIGN MPT

DESCRIPTION - This work is the design and plan preparation for required maintenance and protection of the traveling public approaching the construction area and within the limits of construction.

DESIGN –

(a) General. Design, prepare, and submit Maintenance and Protection of Traffic Control

Plans. The submittal must comply with Pennsylvania Department of Transportation (PennDOT) Design Manuals for presentation and must be signed by a registered Professional Engineer by the Commonwealth of Pennsylvania. The Department (City DOMI) will review the plans and either approve or return comments within review times as defined in Section (c)2 of this specification.

Designer Qualifications - Have the design completed by a Professional Engineer licensed in the Commonwealth of Pennsylvania and according to the "Design Activities Qualifications and Requirements".

(b) Design Specifications. Design a Traffic Control Plan (TCP) in accordance with the most current edition of all PennDOT Standards, Specifications, and Regulations. These include, but are not limited to the following:

• Temporary Traffic Control Guidelines, (PennDOT Publication 213)

• Design Manual Parts 2 & 3 (PennDOT Publication 13M and 14M)

• Design Manual Part 1, (PennDOT Publication 10C, Chapter 3, Section

3.3.B.13 on pgs. 3-27 to 3-33, esp. Figure 3.1)

• Specifications, PennDOT Publication 408/2011

• Traffic Signing Standards TC-8600 / TC-8700 (PennDOT Publication 111M)

• Handbook of Approved Signs (PennDOT Publication 236M)

• Pa Code Title 67, Chapter 212, Official Traffic Control Devices

• MUTCD Manual on Uniform Traffic Control Devices (FHWA)

• Traffic Engineering Manual, (PennDOT Publication 46)

(c) Design Requirements.

1. Maintenance of Traffic During Construction. Design traffic control plan(s) to minimize impacts to traffic when bringing equipment and materials in and out of the project area. Develop a plan that maintains a single lane of traffic in both directions along Bates Street and does not restrict access to/from the I-376 ramps during all phases of construction. Notify and obtain approval from PennDOT of any proposed impacts to Bates Street and the I-376 ramps. Provide notices to PennDOT as required in advance of any traffic impacts to allow notification through the press.

This work also consists of the maintenance and protection of pedestrians approaching the construction area and within the limits of construction. The safety

Frazier Street Stairs Design MPT Item 9000-0006 9000-0006-2 for pedestrians must be maintained at all times. The steps should be closed to pedestrians from all access points during construction. Pedestrian access along Bates Street should be maintained throughout the project.

2. Submissions. Electronic submissions in PDF file format are acceptable. The plan will include the following review times for each submission:

a. Preliminary Submission. Fifteen (15) working days.

b. Final Submission. Fifteen (15) working days.

c. Revised Traffic Control Plan Submissions. Prepare and submit a revised

Traffic Control Plan for any proposed modification to the original approved plan. Submit the revised plan for review and approval at least fifteen (15) days prior to the implementation of the proposed modifications.

If a submission is incomplete or otherwise requires additional information or data to properly complete the review, the review time will begin as specified for the submission when all required information is received. Additional contract time or price adjustment to any contract items will not be considered due to failure to obtain approvals within the specified review times resulting from incomplete or non-conforming submissions. Working days are weekdays, Monday through Friday.

The following official Department holidays will not be included as working days:

New Year's Day, Dr. Martin Luther King, Jr. Day, Good Friday, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving Day, and Christmas Day.

MEASUREMENT AND PAYMENT –

(a) Design MPT. Lump Sum

Payment for the design of the Traffic Control Plan will be made based on the following schedule:

Initial Submission – 15% Final Plan Approval – 70% Revisions During Construction – 15%

(b) Maintenance and Protection of Traffic During Construction. Item 4901-0001

Frazier Street Stairs Jumper Stairs Curb Item 9000-0007 9000-0007-1

ITEM 9000-0007 – JUMPER STAIRS CURB

In accordance with Section 630 and as follows:

630.1 DESRIPTION – Replace with the following:

This work is the construction of a reinforced concrete curb parallel to the concrete jumper stairs including the procurement of all required materials as indicated on the construction drawings.

630.2 MATERIAL – Revise as follows:

Replace the 1st, 2nd, 3rd, 5th, 7th, and 8th bullet with the following:

• Class AAA Cement Concrete – Section 704 except as follows:

1. Cement – Section 701, except use white Portland cement containing no more than

0.50% by weight of iron oxide.

Do not add fly ash or ground granulated blast furnace slag to concrete.

2. Fine Aggregate – Section 703.1, Type A, except add the following:

Provide white fine aggregate, from an approved source, of either crushed white marble, white limestone, or calcite. Provide aggregate that is clean, washed and free from dirt or any discoloring matter not containing more than 0.75% of ferric oxide.

3. Coarse Aggregate, Type A – Section 703.2 except add the following:

Use No. 8 Coarse Aggregate. Use only light-colored crushed stone or aggregate with at least three faces resulting from fracture. Do not use slag.

4. Water – Section 720.1 except add the following:

Potable and free from iron or other impurities which may cause staining.

5. Admixtures – Section 711.3 except add the following:

Use only those admixtures that do not discolor the white cement concrete. Obtain written assurance from the manufacturer that the admixture does not cause staining.

• Reinforcement Steel. Use epoxy coated reinforcement bars or welded wire fabric – Section 709.

• Protective Coating – Section 1019 o Use boiled linseed oil on all non-walking surfaces.

Frazier Street Stairs Jumper Stairs Curb Item 9000-0007 9000-0007-2

• Joint Material – Section 705 o Use expansion joint filler and asphalt rubber sealing compound.

630.3 CONSTRUCTION – Revise as follows:

(b) Forms. Add the following:

Use only form release oil that will not contribute to the discoloration of the white cement concrete. Obtain written assurance from the manufacturer that the product does not cause discoloration.

(c) Placing, Finishing, and Curing Concrete. Add the following:

Use only white, liquid membrane-forming curing compound. Cover barrier with white polyethylene sheeting after applying curing compound. Until forms are removed, protect exposed concrete by the water cure method using only new burlap that is free of sizing or any substance that will cause staining. Thoroughly rinse the new burlap in water to remove soluble substances before placing on concrete surfaces. Apply boiled linseed oil per Section 1019 to all cast-in-place walking surfaces and cast-in-place landing structures.

(d) Curb Machine. Delete Section.

630.4 MEASUREMENT AND PAYMENT – Revise as follows:

(a) Jumper Stairs Curb. Linear Foot.

(c) Class I Excavation. Incidental to Jumper Stairs Curb construction.

0001 - PREFACE TO CONTRACT SPECIAL PROVISIONS
0030 - Description of Work
0106 - Control of Material
0703 - Aggregates
Special Provisions - Compiled.pdf
4202-0100 - Structure Demolition, Modified
4610-0001 - 4-inch Pipe, Jumper Stairs Underdrain
4610-0002 - 6-inch Pipe Underdrain, Type I Backfill, Modified
4630-0041 - Concrete Deep Curb, 7 inch Reveal
4676-0001 - 4 inch Reinforced Cement Concrete Sidewalk
4901-0001 - Maint and Protect of Traffic modified
9000-0001 - Precast Concrete
9000-0002 - Elevated Stair Railing
9000-0003 - Elevated Stair Bike Runnel
9000-0004 - 1.5-inch Diameter Welded Pipe Railing
9000-0005 - Class AAA Reinforced Cast-in-Place Concrete
9000-0006 - Design MPT
9000-0007 - Jumper Stairs Curb