Frazier_Street_Construction_Schedule_(Revised_NTP_4-27).pdf

PDF 738 KB Posted

Attached to
Frazier Street Steps Construction
Solicitation number
2022-IFB-285
Issued by
Allegheny County, Pennsylvania

About this file

This document is a detailed project schedule for the Frazier Street Stairs Construction project for the City of Pittsburgh's Department of Mobility and Infrastructure (DOMI). The comprehensive Gantt chart outlines a construction timeline spanning from April 27, 2023, to November 29, 2023, with a total project duration of 218 days. Key construction activities include pre-construction tasks like advance notices, concrete quality control plans, and precast component procurement, followed by on-site construction activities such as mobilization, implementing maintenance of traffic (MPT) plans, installing erosion and sediment controls, clearing and grubbing, demolishing existing structures, excavating foundations, pouring concrete landings and columns, installing drainage systems, and constructing new stairs and sidewalks.

The project schedule breaks down the construction process into detailed phases with specific durations for each task, including installing precast stringers, pouring jumper stairs and sidewalks, restoring pavement, installing railings, and final project closeout. The timeline indicates critical path activities, predecessor tasks, and precise start and finish dates for each construction phase. The project culminates with final inspection and punchlist items, with project completion scheduled for November 29, 2023. The schedule suggests careful sequencing of construction activities to ensure efficient progress and minimal disruption, with tasks ranging from 1 to 15 days in duration across various stages of the Frazier Street Stairs reconstruction project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Mode

Task Name Duration Start Finish PredecessorsTask Calendar

1 Notice to Proceed 0 days Thu 4/27/23 Thu 4/27/23 None

2 Pre-Construction Activities 107 days Thu 4/27/23 Sat 9/23/23 None

3 Advance Notices 14 days Thu 4/27/23 Wed 5/10/23 1 7-day

4 Concrete QC Plans 36 days Thu 4/27/23 Thu 6/1/23 1 7-day

5 Precast Components 90 days Thu 4/27/23 Tue 7/25/23 1 7-day

6 Railing Procurement 150 days Thu 4/27/23 Sat 9/23/23 1 7-day

7 Design MPT 60 days Thu 4/27/23 Wed 7/19/23 1 5-day

8 Construction 84 days Thu 7/20/23 Tue 11/14/23 None

9 Mobilization 1 day Thu 7/20/23 Thu 7/20/23 7 5-day

10 Implement MPT 1 day Fri 7/21/23 Fri 7/21/23 9 5-day

11 Install E&S Controls 3 days Mon 7/24/23 Wed 7/26/23 10 5-day

12 Clearing and Grubbing 3 days Thu 7/27/23 Mon 7/31/23 11 5-day

13 Demolish Existing Deteriorated Brick Wall 1 day Tue 8/1/23 Tue 8/1/23 12 5-day

14 Excavate for Elevated Stair Landing Foundations

2 days Tue 8/1/23 Wed 8/2/23 12 5-day

15 Install Collection Drain and Endwall 1 day Thu 8/3/23 Thu 8/3/23 14 5-day

16 Prepare Landing Foundation Subgrade 2 days Fri 8/4/23 Mon 8/7/23 15 5-day

17 Form, Tie, and Pour Landing Foundations 5 days Tue 8/8/23 Mon 8/14/23 16 5-day

18 Form, Tie, and Pour Landing Columns 5 days Tue 8/15/23 Mon 8/21/23 17 5-day

19 Install Inlet Box and Thermoplastic Pipe 3 days Tue 8/22/23 Thu 8/24/23 18 5-day

20 Fill Placement 5 days Fri 8/25/23 Thu 8/31/23 19 5-day

21 Form, Tie, and Pour Landings 6 days Fri 9/1/23 Fri 9/8/23 20 5-day

22 Curing Time for Landings, Prepare Crane Pad, and Mobilize Crane.

7 days Sat 9/9/23 Fri 9/15/23 21 7-day

23 Install Precast Stringers 6 days Mon 9/18/23 Mon 9/25/23 5,22 5-day

24 Prepare Subgrade and Subbase for Jumper Stairs and Sidewalk

1 day Tue 9/26/23 Tue 9/26/23 23 5-day

25 Form, Tie, and Pour Jumper Stairs and Sidewalk

15 days Wed 9/27/23 Tue 10/17/23 24 5-day

26 Restore Pavement/Pavers Along Frazier Street

1 day Wed 10/18/23 Wed 10/18/23 25 5-day

27 Intall Jumper Stair Collection Drain 1 day Thu 10/19/23 Thu 10/19/23 26 5-day

28 Install Stair Railings and Bike Runnel 5 days Fri 10/20/23 Thu 10/26/23 27,6 5-day

29 Demolish Existing Frazier Street Stairs 10 days Fri 10/27/23 Thu 11/9/23 28 5-day

30 Restore Grade to Original Configuration and Seed Disturbed Areas

2 days Fri 11/10/23 Mon 11/13/23 29 5-day

31 Remove E&S Controls 1 day Tue 11/14/23 Tue 11/14/23 30 5-day

32 Remove MPT 1 day Tue 11/14/23 Tue 11/14/23 30 5-day

33 Project Closeout 11 days Wed 11/15/23 Wed 11/29/23 31 None

34 Final Inspection 1 day Wed 11/15/23 Wed 11/15/23 31 5-day

35 Project Punchlist Items 10 days Thu 11/16/23 Wed 11/29/23 34 5-day

36 Project Completion 0 days Wed 11/29/23 Wed 11/29/23 35 5-day

4/27

11/29

23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 May '23 Jun '23 Jul '23 Aug '23 Sep '23 Oct '23 Nov '23 Dec '23

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Project: Frazier Street Stairs By: BTP/ZSG Date: 2/24/23 DOMI Project No. 210076