SOW__Wet_Lab_Trench_Metal_Framework_NWL_and_Isolation_3-22-15.doc
DOC document 1 MB Posted
- Attached to
- Replace Metal Framework for Drains
- Solicitation number
- G15PS00271
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Release_of_Claims_DI-137.doc | DOC document | |
| NorthWetlanSketch_Modified_04212015.jpg | JPG image | |
| Standard_Form_1413.pdf | ||
| Sol_G15PS00271.pdf | ||
| Davis_Bacon_Wage_Determination_4-17-15.pdf | ||
| QuaratineRoomSketch2_Modified_4212015.jpg | JPG image | |
| Payroll_form_WH-347.pdf | ||
| image_of_2_foot_trench_modified_04212015.jpg | JPG image | |
| 4_foot_trench_picture_04212015.jpg | JPG image | |
| Payroll_form_WH-347.pdf | ||
| Standard_Form_1413.pdf | ||
| NorthWetlanSketch_Modified_04212015.jpg | JPG image | |
| QuaratineRoomSketch2_Modified_4212015.jpg | JPG image | |
| SOW__Wet_Lab_Trench_Metal_Framework_NWL_and_Isolation_3-22-15.doc | DOC document | |
| 4_foot_trench_picture_04212015.jpg | JPG image | |
| Davis_Bacon_Wage_Determination_4-17-15.pdf | ||
| Release_of_Claims_DI-137.doc | DOC document | |
| image_of_2_foot_trench_modified_04212015.jpg | JPG image |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Northern Appalachian Research Laboratory – Replace North Wet Lab Drain And Isolation Lab Framework I. Overview
The Northern Appalachian Research Laboratory has a need to replace the metal framework for the drains in its north and isolation wet labs II. Background The wet labs at the Northern Appalachian Research Laboratory were constructed in 1978. The top side metal framework is flush with the cast cement floor which supports grating made of aluminum, fiberglass, or steel openings to each trench.
III. Detailed Requirements
1) Contractor shall obtain all permits required by federal, state and local regulations prior to commencement of work. All required paperwork and calculations required to obtain any permits shall be provided to the Contracting Officer’s Representative (COR) and Facility Manager (FM) at time of submission as well as the permits themselves upon receipt of the documents from the permitting agencies.
2) Work Requirements:
a. The overall project will be performed in two phases. Each phase will consist of a continuous area of each lab. Scientific work will be performed during the construction in the other areas of the lab.
b. Remove grate support L-bracket and dispose of debris. Concrete dust must be maintained to an absolute minimum to protect the science being performed in the other areas of the lab.
c. Repair damaged concrete areas using 5,000psi concrete with bonding agent. Any new damage to the concrete due to the metal removal process will be the responsibility of the contractor to repair. See Appendix for details on type and quantity of concrete repairs required.
d. Replace with structure as shown in the Appendix Diagrams. The material shall be alloy-316 stainless steel.
e. Corner joints of L-brackets shall be welded.
f. Manufacturer’s processes are to be followed.
g. Replacements of the aluminum, fiberglass, or steel gratings are not part of this work requirement.
III. Deliverables
1. Submittals shall be provided for the following items:
a. L-bracket for grate support
b. Steel bar and extrusion
c. Nelson studs
d. 5,000psi concrete
e. Shop drawings for assemblies fabricated off site.
2. Timeline. Work may not begin without the approval of the timeline by the FM. The project schedule shall be a chart which graphically depicts the proposed sequence to accomplish each work feature or operation. It shall show start dates and completion dates for each event on a horizontal time scale. The progress schedule time scale shall begin with the Notice to Proceed and indicate the number of days to completion. The schedule will be the reference to which the contractor’s progress and efforts are compared. Three paper copies or one soft copy shall be submitted to the FM.
IV. Other Requirements Pre-Construction Meeting:
The contractor shall schedule and conduct a pre-construction meeting on-site with the FM and COR to review the requirements and conditions of this contract. The contractor shall have the project manager, field superintendent, and all subcontractors on site, or available by conference call, for the pre-construction meeting with Government officials prior to the commencement of work for this project.
Contractor shall be licensed to perform work in PA.
Outages and Interruptions:
The contractor is advised that the Science Center will continue to perform research functions during the contract. Work shall be conducted as to minimize interruption to service. Contractor shall notify FM at least 7 days prior to any and all outages and interruptions. Contractor shall not proceed with work without approval from FM. Changes to the schedule require the submission of a new schedule to the FM for review.
Normal working hours for the construction work at the Science Center shall be 7:30am- 4:00pm, Monday - Friday. The contractor and sub-contractors (if required) shall not work Saturdays, Sundays, legal holidays, or non-normal working hours, unless otherwise authorized by the FM. Request to work other than the normal hours shall be made, and approved, in writing through the FM. Work performed during “other than the normal hours” shall not change the total cost to the government.
Changes / Clarifications:
All work must be completed as shown in the contract documents. If ‘no cost’ change orders are to be made, a written request to the COR must be made detailing why the work can not be completed as shown, as well as the corrective action suggested by the contractor. For change orders which will alter the price or requirements of the contract, the Contracting Officer’s approval must be given in writing before beginning the work described.
Disposal and Transporting of Debris and Material:
All materials and construction debris shall be removed from the work area and placed in an approved dumpster or removed from the site daily by the contractor.
Organization and storage of contractor(s) items at the site:
The FM shall designate areas where the contractor can store or place materials and equipment for short-term storage in preparation for installation. There is limited space on site for the storage of contractor equipment. There is no inside storage space available. Storage and security of materials and equipment as required for the performance of the contract requirements are the responsibility of the contractor. The contractor shall be responsible for making all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site. Upon completion of the contract, the contractor shall remove all equipment and excess materials, and shall restore the site to its original condition, as approved by the FM, at no additional cost to the government.
Site Cleanliness:
The contractor shall maintain the site free of construction debris outside of approved containers (dumpsters). The contractor shall provide dust protection and shall maintain cleanliness of the work site by promptly removing debris, tools, and excess material.
Contractor Parking, Security, and Smoking Regulations:
The contractor shall maintain a daily log of all contractor and subcontractor employees (date, name, arrival time, departure time) and provide a copy of the log to the COR at least weekly. The FM or COR will designate a parking area (or areas) for the contractor to park vehicles. There shall be no smoking in any buildings at any time. All personnel that smoke will have to do so outside in designated smoking areas.
Environmental Protection:
The contractor and subcontractors shall perform all work and activities in accordance with local, state, and Federal environmental regulations.
Safety:
The contractor and subcontractors shall perform all work and activities in accordance with local, state, and Federal safety regulations, including OSHA, NEC, and USGS policy.
Notice to the Government of Delays:
In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the COR in writing, giving pertinent details. This data shall be informational only in character. Notice under this provision shall not be construed as a waiver by the Government of any delivery schedule or date or any rights or remedies provided by law or under this contract.
Other:
If the event of other committed construction projects during the busy construction season contractor to advised Facility Manager for any potential delays or extensions of time of contract during implementation stages. USGS Wellsboro will work with contractor for project times mutual to both parties.
See Appendixes
Figure #1: Isolation Lab Room 140: 42’ of 2’Trench 42’ of 1’Trench.
Figure # 2: North Wet Lab Rm.134: 50.5’ of 4’ Trench 74’ of 2’ Trench 74’ of 1’ Trench.
Diagram #1: Typical Section of Reconstructed 4’ Trench.
Diagram # 2: Typical Section of Reconstructed 2’ Trench.
Diagram # 3: Typical Section of Reconstructed 1’ Trench.
A-3: Details of 1’ channel metal working (not to scale)
A-4: Samples of damaged concrete
PAGE