FAA
AJW-L910 FPS
Pedestal Main Bearing Statement of Work
Rev - 12-2-2020
AJW-L910 FPS Main Bearings Rev -
Statement of Work (SOW) For
Process Improvement Equipment, Freestanding Bridge Crane and Freestanding Articulating Jib Crane
1.0 Background
This solicitation is for the procurement of the following part:
• ANFPS-20 Pedestal Main Bearings, as per FAA drawing DE-B-2120, Rev G (see attached)
This part is required for continued support of the ANFPS-20 (Air Navigation Fixed Position System) Radar as currently deployed by the FAA.
2.0 Equipment Details
Details for the required part are noted below:
A. Fabricated, constructed and assembled in complete compliance with FAA drawing DE-B-2120, Rev G, including but not limited to:
i. All dimensions as denoted
ii. All heat treatments as denoted
iii. Roller requirements as denoted
iv. Eccentricity and runout as denoted
v. Pre-load as denoted
vi. Material requirements as denoted
vii. Rollers/cages as denoted
viii. Hardness as denoted
ix. Overall configuration as denoted
x. Each bearing shall be permanently stamped or engraved with the following part identification info:
1. P/N DE-B-2120, Rev G
2. Three (3) digit serial number. Serial numbers shall be sequential beginning with serial number for the First Article bearing
3. Date of bearing manufacture (month and year)
4. Manufacturer
B. Vendor shall provide printed documentation of compliance with the following for each bearing manufactured:
i. All dimensions as denoted. Measurement document shall include at a minimum:
1. Required dimension including tolerance
2. Dimension as measured
3. Pass/Fail determination of dimension measured
4. Date of measurement
5. A Coordinate Measuring Machine (CMM) shall be used to verify all dimensions. Proof of current CMM calibration shall be provided
ii. Housing fit as denoted
iii. Eccentricity and runout as denoted
iv. Diametreal pre-load as denoted
v. Magna flux and hardness inspections as denoted
3.0 First Article Inspection/Testing and Bearing Production
Vendor shall provide a First Article (FA) bearing to the FAA for inspection/testing prior to commencing full bearing production. Details associated with the FA bearing and bearing production processes are noted below:
A. FA bearing shall be shipped to the FAA no later than six (6) months
ARO
B. FA bearing will be inspected/tested by the FAA using documents issued with this solicitation
a. In the event issues are found with the bearing, the FAA will provide written notification to the vendor detailing the nature of all deficiencies. FA bearing will then be returned to the vendor and they shall have two (2) weeks to remedy all deficiencies. Repaired FA bearing shall then be return shipped to FAA for Follow-Up inspection.
i. If FA bearing fails Follow-Up inspection, the FAA has the option to return the bearing for further remediation or possibly terminate the contract for cause
C. The FAA will provide written notification to vendor in the event the FA bearing passes all inspections/tests. This will serve as a Notice to Proceed (NTP) with fabrication of all remaining bearings required as per contract.
D. Remaining production bearings shall be delivered in accordance with the following schedule:
i. First production bearing shall be delivered three (3) months following receipt of NTP
ii. Any remaining bearings shall be delivered at a rate of one (1) bearing per month beginning four (4) months following receipt of NTP
iii. All bearings shall be packaged and shipped to be FAA in accordance with Provision 61, Rev D (see attached)
E. All bearings shipped to the FAA or returned to the Vendor for remediation/repair shall be FOB FAA, Freight Prepaid
4.0 Required Documents and Warranty
Vendor shall provide the following documentation and warranty for each bearing supplied:
A. All documentation noted in paragraph 2.0 above B. Certificate of Compliance denoting complete compliance with all requirements detailed in the Statement of Work and all other design documents attached to this solicitation
C. Each bearing shall be fully warranted for one (1) year following date of formal acceptance of each bearing. Formal acceptance shall be provided by the FAA Contracting Officer.
| Statement of Work (SOW) For |
| 1.0 Background |
| 2.0 Equipment Details |
| Details for the required part are noted below: |
| A. Fabricated, constructed and assembled in complete compliance with FAA drawing DE-B-2120, Rev G, including but not limited to: |
| i. All dimensions as denoted |
| ii. All heat treatments as denoted |
| iii. Roller requirements as denoted |
| iv. Eccentricity and runout as denoted |
| v. Pre-load as denoted |
| vi. Material requirements as denoted |
| vii. Rollers/cages as denoted |
| viii. Hardness as denoted |
| ix. Overall configuration as denoted |
| x. Each bearing shall be permanently stamped or engraved with the following part identification info: |
| 1. P/N DE-B-2120, Rev G |
| 2. Three (3) digit serial number. Serial numbers shall be sequential beginning with serial number for the First Article bearing |
| 3. Date of bearing manufacture (month and year) |
| 4. Manufacturer |
| B. Vendor shall provide printed documentation of compliance with the following for each bearing manufactured: |
| i. All dimensions as denoted. Measurement document shall include at a minimum: |
| 1. Required dimension including tolerance |
| 2. Dimension as measured |
| 3. Pass/Fail determination of dimension measured |
| 4. Date of measurement |
| 5. A Coordinate Measuring Machine (CMM) shall be used to verify all dimensions. Proof of current CMM calibration shall be provided |
| ii. Housing fit as denoted |
| iii. Eccentricity and runout as denoted |
| iv. Diametreal pre-load as denoted |
| v. Magna flux and hardness inspections as denoted |
| 3.0 First Article Inspection/Testing and Bearing Production |
| Vendor shall provide a First Article (FA) bearing to the FAA for inspection/testing prior to commencing full bearing production. Details associated with the FA bearing and bearing production processes are noted below: |
| A. FA bearing shall be shipped to the FAA no later than six (6) months ARO |
| B. FA bearing will be inspected/tested by the FAA using documents issued with this solicitation |
| a. In the event issues are found with the bearing, the FAA will provide written notification to the vendor detailing the nature of all deficiencies. FA bearing will then be returned to the vendor and they shall have two (2) weeks to remedy all defici... |
| i. If FA bearing fails Follow-Up inspection, the FAA has the option to return the bearing for further remediation or possibly terminate the contract for cause |
| C. The FAA will provide written notification to vendor in the event the FA bearing passes all inspections/tests. This will serve as a Notice to Proceed (NTP) with fabrication of all remaining bearings required as per contract. |
| D. Remaining production bearings shall be delivered in accordance with the following schedule: |
| i. First production bearing shall be delivered three (3) months following receipt of NTP |
| ii. Any remaining bearings shall be delivered at a rate of one (1) bearing per month beginning four (4) months following receipt of NTP |
| iii. All bearings shall be packaged and shipped to be FAA in accordance with Provision 61, Rev D (see attached) |
| E. All bearings shipped to the FAA or returned to the Vendor for remediation/repair shall be FOB FAA, Freight Prepaid |
| 4.0 Required Documents and Warranty |
| Vendor shall provide the following documentation and warranty for each bearing supplied: |
| A. All documentation noted in paragraph 2.0 above |
| B. Certificate of Compliance denoting complete compliance with all requirements detailed in the Statement of Work and all other design documents attached to this solicitation |
| C. Each bearing shall be fully warranted for one (1) year following date of formal acceptance of each bearing. Formal acceptance shall be provided by the FAA Contracting Officer. |
File details come from the government source that posted it. Updated .