The file is a comprehensive contract opportunity document for the Fairview Water Main Improvements project, issued by the Oakland County Water Resources Commissioner (OCWRC) in Pontiac, Michigan. The project involves extensive water main infrastructure improvements, including approximately 1,850 linear feet of 6-inch CIPP water main, 1,100 linear feet of 8-inch CIPP water main, 1,650 linear feet of 16-inch CIPP water main, and 8,700 linear feet of 8-inch HDPE SDR 11 water main installed via horizontal directional drilling. Additional work includes 12,500 linear feet of water main abandonment, installation of 58 valve and wells (or boxes), 38 hydrants, and 29 connections to existing water mains. The project will also involve 31,300 square yards of 2-inch cold milling of existing HMA pavement and 40 sewer lateral connection repairs. Bids are scheduled to be received virtually on June 17, 2025, at 9:30 AM local time, with a pre-bid meeting planned for May 28, 2025, at 1:00 PM.

The project is federally funded through the Drinking Water State Revolving Fund (DWSRF) and requires compliance with several federal provisions, including Davis-Bacon Act wage rates, Disadvantaged Business Enterprise (DBE) requirements, and Build America, Buy America regulations. Prime contractors must document Good Faith Efforts to ensure DBE participation and must self-perform at least 51% of construction trade work. The contract includes specific requirements for labor standards, material sourcing, and telecommunications equipment restrictions. The total project is divided into two divisions: DWSRF Eligible Work and DWSRF Ineligible Work, with a comprehensive bid schedule detailing numerous line items for various construction activities. The project emphasizes local and federal compliance, with specific attention to labor standards, environmental considerations, and infrastructure improvement in the City of Pontiac.

View the file

Other files

File Type Posted
20250515_IFB_Plans_set.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

FAIRVIEW WATER MAIN IMPROVEMENTS

LOCATED IN:

CITY OF PONTIAC

OAKLAND COUNTY, MICHIGAN

OWNED BY:

COUNTY OF OAKLAND

OPERATED AND MAINTAINED BY:

OAKLAND COUNTY WATER RESOURCES COMMISSIONER�S OFFICE

MAY 2025

Oakland County Water Resources Commissioner

One Public Works Drive Building 95W

Waterford, MI 48328-1907

DWSRF Project #7863-01

HRC JOB NO. 20240256

555 Hulet Drive P.O. Box 824

Bloomfield Hills, Michigan 48303-0824

[Page Intentionally Left Blank]

OCWRC - CITY OF PONTIAC TABLE OF CONTENTS

FAIRVIEW WATER MAIN IMPROVEMENTS 00010 / 1

DWSRF Project #7863-01

Hubbell, Roth & Clark, Inc. Job 20240256

TABLE OF CONTENTS

NUMBER SECTION NAME PAGE NUMBER

BIDDING REQUIREMENTS - CONTRACT PROVISIONS

00001 Title Page ......................................................................................................................... 1 and 2

00010 Table of Contents .............................................................................................................1 thru 4

WRC AD Advertisement (DC-116) ..................................................................................................1 and 2

00200 Coordination Clause.........................................................................................................1 thru 6

WRC IB Information for Bidders (DC-119).................................................................................1 thru 10

WRC Q Experience and Qualification Statement (DC-118) .......................................................1 thru 20

WRC P Proposal (DC-123) .........................................................................................................1 thru 14

WRC A Agreement (DC-117) .....................................................................................................1 thru 18

WRC LMB Labor and Material Bond (DC-132) .................................................................................1 and 2

WRC MGB Maintenance and Guarantee Bond (DC-133) ...................................................................1 and 2

WRC PB Performance Bond (DC-134)............................................................................................1 and 2

WRC GC General Conditions ........................................................................................................1 thru 72

WRC SC Supplementary Conditions...............................................................................................1 thru 6

WRC Oakland Full Unconditional Lien Waiver and Release ....................................................1 and 2

WRC Oakland Partial Unconditional Lien Waiver and Release ................................................1 and 2

WRC GS General Specifications ...................................................................................................1 thru 18

WRC CSC Certification for Safety Compliance (DC-029) ................................................................1 and 2

WRC EP Oakland County E-Verify Policy......................................................................................1 and 2

WRC Notice of Claim Form.......................................................................................................1 and 2

00850 DWSRF � Wage Decision Schedule............................................................................. 1 thru 14

00851 DWSRF - DBE and Debarment Certification...................................................................1 and 2

00852 DWSRF � Build America, Buy America..........................................................................1 and 2

00853 DWSRF � Prohibition on Certain Telecommunication and Video Surveillance............. 1 and 2

DIVISION 1 GENERAL REQUIREMENTS

01039 Meetings ...........................................................................................................................1 and 2

01220 Bid Item Description......................................................................................................1 thru 24

01300 Submittals ......................................................................................................................1 thru 12

01700 Contract Closeout.............................................................................................................1 thru 4

01900 Soil Conditions and Boring Logs .....................................................................................1 and 2

DIVISION 2 SITE WORK

02140 Dewatering .......................................................................................................................1 thru 4

02200 Earthwork.........................................................................................................................1 thru 8

02214 Roadway Excavation, Backfill, and Compaction ............................................................1 thru 4

02220 Soil Erosion and Sedimentation Control ..........................................................................1 and 2

02315 Utility Trench, Backfill and Compaction ......................................................................1 thru 14

02336 Horizontal Directional Drilling - Water Main ...............................................................1 thru 14

02370 Geogrid Soil Reinforcement ..........................................................................................1 thru 12

02511 Hot Mixed Asphalt Pavement .......................................................................................1 thru 20

02520 Concrete Paving Materials .............................................................................................1 thru 12

02540 Quality Control and Quality Assurance of Portland Cement Concrete (PCC) ..............1 thru 10

TABLE OF CONTENTS OCWRC - CITY OF PONTIAC

00010 / 2 FAIRVIEW WATER MAIN IMPROVEMENTS

NUMBER SECTION NAME PAGE NUMBER

DWSRF Project #7863-01

Hubbell, Roth & Clark, Inc. Job 20240256

02660 Water Systems � General...............................................................................................1 thru 20

02661 Ductile Iron Water Main Pipe........................................................................................1 thru 12

02662 High Density Polyethylene Water Main Pipe ................................................................1 thru 16

02668 Water Mains � Polyethylene Encasement........................................................................1 thru 6

02703 Internal Pipeline Inspection ...........................................................................................1 thru 10

02704 Internal Sewer Inspection...............................................................................................1 thru 12

02730 Open -Cut Sanitary Sewers ............................................................................................1 thru 16

02742 Cured-in-Place Pipe .......................................................................................................1 thru 24

02745 Cured-in-Place Sewer Lateral ........................................................................................1 thru 20

02751 Cleaning of Sewer Lines ..................................................................................................1 thru 4

02836 Property Protection Fence.................................................................................................1 and 2

02990 Permits ..............................................................................................................................1 and 2

SPECIAL PROVISIONS

1�x3� Crushed Concrete������������������������������ .....1 and 2

Aggregate Base, 21AA...............................................................................................................................1 thru 4

Cold Milling Existing Pavement.................................................................................................................1 and 2

Color Audio-Video Recording of Construction Areas...............................................................................1 thru 4

Concrete Curb and Gutter ...........................................................................................................................1 and 2

Concrete Pavement Repair..........................................................................................................................1 and 2

Eastern Massasauga Rattlesnake................................................................................................................1 thru 2

Exploratory Excavation and Utility Locating ............................................................................................1 thru 4

Maintaining Traffic ....................................................................................................................................1 thru 6

Structure, Adjust .........................................................................................................................................1 and 2

Subgrade Undercutting and Geogrid ..........................................................................................................1 and 2

Temporary Water Supply System ..............................................................................................................1 thru 4

Tracer Wire for Non-Conductive Underground Piping .............................................................................1 thru 8

Tree Removal and Clearing ........................................................................................................................1 and 2

Turf Restoration..........................................................................................................................................1 and 2

Underdrain, 6 Inch, Special .......................................................................................................................1 and 2

MDOT Special Provision for Curb Ramp Opening, Concrete ...................................................................1 and 2

MDOT STANDARD TRAFFIC DETAILS

101-GEN-SPACING-CHARTS Tables for �L�, �D�, and �B� Values .......................................1 thru 4

102-GEN-NOTES Traffic Control Typicals Note Sheet .........................................1 and 2

103-GEN-SIGN Traffic Control Typicals Sign Sheet .........................................1 thru 4

112-TR-CLT 1-Lane and CLTL Closure Utilizing Traffic Regulators on a 3-Lane

Undivided Roadway .................................................................1 and 2

123-NFW-1LC-(R) 1 Right Lane Closure on a 4-Lane Undivided Roadway...........1 and 2

137-CLT-SHIFT-OLC Lane Shift on a 3-Lane Undivided Roadway ............................1 and 2

OCWRC - CITY OF PONTIAC TABLE OF CONTENTS

FAIRVIEW WATER MAIN IMPROVEMENTS 00010 / 3

NUMBER SECTION NAME PAGE NUMBER

DWSRF Project #7863-01

Hubbell, Roth & Clark, Inc. Job 20240256 y d e s i g n p r o j e c t d o c s s p e c s m a s t e r s p e c t o c d o c x A M

MDOT STANDARD PLANS

R-28-J Sidewalk Ramp and Detectable Warning Details ............................................................1 thru 8

R-29-I Driveway Openings & Approaches, and Concrete Sidewalk ..........................................1 thru 4

R-30-G Concrete Curb and Concrete Curb & Gutter ....................................................................1 and 2

R-44-F Concrete Pavement Repair ..............................................................................................1 thru 6

R-83-C Utility Trenches ...............................................................................................................1 thru 6

R-126-I Placement of Temporary Concrete Barrier and Temporary Steel Barrier .......................1 thru 6

ATTACHMENTS

OCWRC �Requirements for Changing the Elevation of Manhole Covers� ..............................................1 thru 4

Fairview Water Main Improvements Project Geotechnical Report .........................................................1 thru 62

Unanticipated Discoveries Plan .................................................................................................................1 thru 6

OCWRC Water Main Extension Permit .....................................................................................................1 and 2

Michigan Department of Transportation�s R.O.W. Permit........................................................................1 thru 4

EGLE Part 399 Permit ...............................................................................................................................1 thru 4

TABLE OF CONTENTS OCWRC - CITY OF PONTIAC

00010 / 4 FAIRVIEW WATER MAIN IMPROVEMENTS

NUMBER SECTION NAME PAGE NUMBER

DWSRF Project #7863-01

Hubbell, Roth & Clark, Inc. Job 20240256

Form DC-116 ADVERTISEMENT

JIM NASH

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page ADV-1 of ADV-2 05/27/2020

Fairview Water Main Improvements

CITY OF PONTIAC

OAKLAND COUNTY, MICHIGAN

Proposals will be received virtually by the Office of the Oakland County Water Resources Commissioner, (�Owner�) via www.bidnetdirect.com on Tuesday, June 17, 2025 at 9:30 am, local time for the construction of certain facilities and structures, including the following approximate primary items and quantities:

• 1,850 LFT of 6-inch CIPP Water Main

• 1,100 LFT of 8-inch CIPP Water Main

• 1,650 LFT of 16-inch CIPP Water Main

• 8,700 LFT of 8-inch HDPE SDR 11 Water Main installed via HDD

• 2,300 LFT of 8-inch DIWM CL54 Water Main installed via OC

• 375 LFT of 12-inch DIWM CL54 Water Main installed via OC

• 225 LFT of 16-inch DIWM CL54 Water Main installed via OC

• 12,500 LFT Water Main Abandonment

• 58 Valve and Wells (or boxes), 38 Hydrants, 29 Connections to Existing Water Main (6�, 8� and

16�)

• 34,000 SYD of 2-inch Cold Milling Existing HMA Pavement

• 40 Sewer lateral connection repairs

Prime contractors bidding on this project must follow, document, and maintain documentation of their Good Faith Efforts (GFE), to ensure that Disadvantaged Business Enterprises (DBEs) have the opportunity to participate in the project by increasing DBE awareness of procurement efforts and outreach. In addition, Labor Standards Provisions for Federally Assisted Projects, including Davis- Bacon Act compliance, must be adhered to. Lastly, applicable materials for this project must meet the �Build America, Buy America� requirements of federally funded projects.

PROPOSALS TO BE RECEIVED AT THE FOLLOWING DATE AND TIME:

June 17, 2025 at 9:30AM, local time

PROPOSALS WILL BE PUBLICLY OPENED AND READ AT THE FOLLOWING DATE AND TIME:

June 17, 2025 at 9:30AM, local time

Bidders shall review and comply with the Information for Bidders, which is incorporated by reference, and carefully review all Contract Documents, as defined in the Information for Bidders. Bids submitted after the exact time specified for receipt will not be considered.

Bidding Documents must be obtained online from the Michigan Inter-Governmental Trade Network (MITN) website via BidNet Direct (www.bidnetdirect.com). For questions about MITN, refer to https://www.oakgov.com/government/purchasing/bidder-registration/bid-solicitation-public-search

All information regarding the bidding for this project must be obtained on the BidNet Direct/MITN website only.

Form DC-116 ADVERTISEMENT

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page ADV-2 of ADV-2 05/27/2020

A pre-bid meeting is scheduled for Wednesday May 28, 2025 at 1:00 PM, local time, virtually via Microsoft Teams for all prospective bidders. To join the Pre-Bid Meeting, click the link below or go to the Teams website, download the Windows app and manually type in the Meeting ID and Passcode. All Prospective Bidders are strongly encouraged to attend the Pre-Bid Meeting, however, the meeting is not mandatory.

website: https://teams.microsoft.com/ Meeting ID: 284 816 560 022 3 Passcode: Pf9Ec699 Phone: 248-333-6396 Phone Conference ID: 281 276 565#

Questions, comments, or concerns of any Bidder regarding bidding or the Contract Documents or the project, must be submitted through the BidNet Direct/MITN website. Inquiries must be received by 12:00 PM on June 6, 2025. No inquiry received after 12:00 PM on Friday, June 6, 2025 will be given consideration.

Addenda issued to Bidders prior to the date of receipt of proposals shall become a part of the Contract Documents and all proposals shall include the work described in each and every Addenda issued.

Addenda will only be made available through the BidNet Direct/MITN website. It is the responsibility of the Prospective Bidder to check this website prior to the bid submission deadline to ensure all addenda issued have been acknowledged.

IMPORTANT: Bids will be received electronically on the BidNet Direct/MITN website on or before the time and date given above. The bid opening will be conducted virtually via Microsoft Teams at the time listed above and meeting information listed below.

website: https://teams.microsoft.com/ Meeting ID: 248 445 537 576 6 Passcode: xz7Gy9Bi Phone: 248-333-6396 Phone Conference ID: 371 487 610#

A certified or cashier's check or bid bond for a sum not less than five percent (5%) of the amount of the proposal will be required for each proposal. A pdf version of this Certified Check or Bid Bond must be included with your Electronic Bid Submission Response. The successful bidder will be required to furnish the original certified bid check, satisfactory performance, labor and material, and maintenance and guarantee bonds in the amount of 100% of the project prior to award.

Owner reserves the right to accept any proposal, to reject any proposal and to waive irregularities in the proposals.

Jim Nash Oakland County Water Resources Commissioner

NOTICE TO BIDDERS

COORDINATION CLAUSE

HRC 1 of 6 1/21/2025

Description The Contractor must conduct operations so as to cooperate with and interfere as little as possible with activities of other contractors, utilities, or City of Pontiac staff on or near the project area in conformance with the General Conditions of the Contract Article 9 �Other Work � Coordination� and the General Specifications of the Contract Article 8 �Public and Private Utilities � Road Permits�.

This clause summarizes the currently known conflicts, cooperation and coordination to aid in the successful construction of the project.

As an acknowledgement that this Coordination Clause has been reviewed and understood, a signature line has been provided at the end of this Section which must be completed and submitted with the Bid to be considered complete and responsive.

a. Meetings

A comprehensive list of meetings and agendas is provided in Section 01039.

A preconstruction meeting will be scheduled within two (2) weeks of the Notice to Proceed.

Progress meetings will be held every two (2) weeks during active construction of the project at a time and location to be determined at the preconstruction meeting or virtually.

b. Public Utilities

Comply with Public Act 174 of 2013 (MISS DIG Underground Facility Damage and Protection Act) to reduce the incidences of damage to underground facilities

The Project Notes (Sheet B) of the drawings shows a list of utility companies that have facilities located within the Project Area.

Refer to the Special Provision for Exploratory Excavation and Utility Locating for requirements during horizontal directional drilling operations on exposing and documenting the location of existing utilities, monitoring of the bore head through existing utilities in close proximity to the proposed utility and the backfill requirements.

c. Known Utility Conflicts:

Utility conflicts are based on review of record documents and information disclosed by various utility companies and are shown on the Drawings utilizing the best available information. No guarantee is given as to the completeness or accuracy of the utilities shown on the Drawings.

d. Known Road Projects in the Area

The follow is a listing of known road construction projects within the local vicinity that may have an impact on this project. Please note that this listing may not be complete and the Contractor shall verify any other projects within the local vicinity that may impact this project.

• Woodward Ave (M-1) Loop Conversion Project (MDOT JN 210599A)

HRC 2 of 6 5/22/2024

The Contractor shall coordinate its work on this project with that by the Contractor on other projects, and as directed by the Engineer. No additional compensation will be allowed for costs incurred by the Contractor due to coordinating with or delays caused by other projects.

e. Permits

Oakland County Water Resources Commissioner�s Office (WRC) Water� will be issued following the execution of the Agreement. This is a no fee permit, Contractor is required to pick up the permit at the WRC offices (One Public Works Dr, Bldg 95 E, Waterford MI, 48328). Special conditions shall be reviewed but as represented do not change or alter the plans and specifications.

EGLE Part 399 � permit has been received and is included in the Contract Documents. This is a no fee permit and requires no further action by the Contractor. Special conditions shall be reviewed but as represented do not change or alter the plans and specifications.

MDOT ROW � This is a no fee permit, however requires further action from the Contractor.

Special conditions shall be reviewed in the Contract Documents, however the following items shall be noted:

Contractor shall notify MDOT 72 hours prior to work commencing in the MDOT R.O.W.

Hassan Alwan (313-500-4277) or Wioletta Bilan (248-388-0020)

Backfill within the MDOT R.O.W. shall be completed in accordance with the MDOT Standard Detail for Utility Trench Backfill, R-83-Series.

The stability of any trenchwork/excavation pits must be ensured by using appropriate and adequate means per MDOT 2020 Standard Specifications for Construction, such as trench-boxes, sheet piling, etc. The sheeting/shoring design shall adhere to MDOT standards, shall be completed by a licensed Professional Engineer in the State of Michigan, and shall be submitted to the Permit Agent for verification.

a. In the case that the Contractor will be developing the Temporary Earth Retention System (TERS) for any open cut/bore pit section the TERS plans shall be signed and sealed by a licensed PE in the State of Michigan.

b. The TERS shall be provided to the MDOT Inspector to coordinate MDOT review.

c. MDOT requires a minimum three-week review time frame.

d. MDOT approval of the TERS is required prior to start of work.

No mainline pavement removal is allowed from November 15 to April 15 unless emergency work.

City of Pontiac ROW � Once the Agreement is Executed, the Contractor is required to pick up the permit at the City of Pontiac Department of Public Works Office (47450 Woodward Ave., Pontiac, MI 48342). Special Conditions shall be reviewed in the Contract Documents, however the following items shall be noted:

Forty-eight (48) hours advance notice shall be given to the Engineering Division prior to the commencement of any proposed work within City Right-of-Way.

Oakland County SESC � Once the Agreement is Executed, the Project Engineer will apply for the permit. This is a no fee permit, Contractor is required to pick up the permit at the WRC offices (One Public Works Dr, Bldg 95 E, Waterford MI, 48328). The SESC Plan and details associated with the permit are located on the Drawings.

HRC 3 of 6 5/22/2024

f. Project Area Considerations

A representative of the Oakland County Water Resources Commissioner�s Office (WRC) is required to be present during the filming of the pre-construction video. Coordinate with the WRC Project Manager for staff assignment.

Active excavations within the roadway (defined as excavations that have not been backfilled to grade) require barricades in accordance with WRC Standard Water Main Details and General Conditions Article 14 �Protection of Work and Property� and Article 19 �Safety and Protection�.

Active excavations with workers present that restrict the roadway to one lane of two-way traffic also require traffic regulators in accordance with General Specifications Article 16 �Maintenance of Traffic�.

The General Contractor will be responsible for coordination of the activities between contractors.

g. Special Conditions � Winter Work and Temporary Pavement

Accumulated snowfall of over 3-inches must be removed from the roadway within all working areas and areas barreled/barricaded for traffic control purposes.

All HMA pavement removed between November 16th and April 30th in any given year during construction, shall be backfilled, compacted, and temporarily resurfaced with approved asphaltic patching materials (defined hereinafter as �temporary pavement�) in accordance with the detail on Sheet H. Temporary pavement shall be placed within 14 days of pavement removal from November 16th to April 30th.

Temporary pavement will be required to be maintained, to the satisfaction of the City of Pontiac and the Engineer, until a permanent pavement repair or final paving in accordance with the Local HMA Road Repair section located on Sheets I - L can be made.

Maintenance gravel is an acceptable form of temporary pavement to maintain traffic before final Temporary Pavement can be placed. Maintenance gravel may be used from May 1st through November 15th in any given year during construction only. Maintenance gravel may be used as temporary pavement for a maximum of 12 weeks from the time the pavement is removed from May 1 through November 15 only. Once the 12-week period has expired, a two-inch (min) layer of hot mixed asphalt must be used for temporary pavement at no additional cost to the Owner and regardless of time before permanent roadway rehabilitation is scheduled.

h. Special Conditions � Scheduling & Sequencing of Roadway Rehabilitation

There is over 16,000 linear feet of road right-of-way within the project area. No more than 60% of the project area will be allowed to be under �full construction� at one time unless otherwise authorized by the Engineer and Owner. �Full construction� in this context is defined as the contractor commencing water main installation activities. The intent of this sequencing requirement is to reduce the duration of construction activities for portions of the project area and to limit the time roadways within the project area are maintained with temporary pavement and maintenance gravel. The contractor shall plan to mobilize their roadway rehabilitation crews at least two (2) times between the Notice to Proceed and Substantial Completion Dates to accommodate this sequencing and scheduling.

i. Temporary Water Supply

The installation of a temporary water supply is required for the CIPP rehabilitation of the water main along Baldwin, Virgina, Home and Tregent. The temporary water supply may only be in operation between May 1st through October 1st. Prior to any temporary water setup, any new water main proposed to be completed as part of this project (except the water main being rehabilitated using the Cured-in-Place (CIPP) Method), shall be tested, connected and fully integrated into the distribution system.

HRC 4 of 6 5/22/2024

Before commencing any lining work along Virginia, the contractor shall coordinate with the local fire department to ensure that 29 W. Rundell Street will have proper fire coverage while the water main along Virginia is being rehabilitated. 29 W. Rundell Street has a 6 inch fire service off of Virginia that will be turned off due to the water main�s rehabilitation.

j. Hydrant Installation Details

Updated hydrant installation detail has been provided on Sheet C. Installations for traffic rated models require a concrete collar be installed around the riser at or near ground level.

k. Tracer Wire

An updated special provision has been added for tracer wire design, installation and testing. The special provision requires more defined connection points, grounding, termination details and more thorough testing requirements, specifically testing before and after �subsequent� work is completed to locate potential breaks in continuity.

l. Information on Sewer Laterals in the Project Area

Information on the sewer laterals in the project area has been provided on the Drawings. This information is the best data available at this time and was collected between January 2025 and April 2025. Mainline and lateral CCTV videos and mainline PACP inspection reports noting lateral locations and cursory information on the tap condition will be made available to the awarded contractor for their use during the project. Laterals that were televised were located during the televising process, marked at the surface and recorded a depth from ground surface at the marked location. The plan views and tables provided on the Sewer System Improvements Drawings incorporate, to the best of the Engineers ability, the existing lateral information as interpreted from the CCTV information provided. There will be no additional payment for the televising of sewer laterals as part of this project. All contractor driven sewer lateral televising shall be included in the cost of the project.

m. Horizontal Directional Drilling Depths (Water Main Installations)

In general, water mains shall be installed with a minimum depth of cover of six (6) feet to the top of pipe and shall not be installed at a depth greater than nine (9) feet to the top of pipe unless otherwise noted on the plans or authorized by the Owner�s field representative. Upon locating utilities along the bore path in which the depth is unknown or assumed (typically utilities with a diameter of 12-inches or less as utilities larger than that have more available as-built information), the Contractor shall record depths and make the general decision that horizontal directionally drilled water main shall go under utilities with a depth of cover at seven (7) feet or less and shall go over utilities that are greater than seven (7) feet in depth. Contractor shall work with the Owner�s field representative to modify the planned profile as necessary to accommodate the specified decision model and stay within the depth of cover limits as described.

n. Sewer Lateral Replacement

The age and condition of the sewer laterals in the project area and the impacts of exposing these laterals during the required pre-HDD exploratory excavation may be an issue during construction and is a concern. Soft excavation methods are required when exposing these sewer laterals, however, a quantity of the bid item �Remove and Replace Sewer Lateral� has been provided in the Proposal for laterals that appear to have been damaged prior to the Contractor exposing the utility. Consequently, sewer laterals damaged by careless excavation or other contractor related activities, at the discretion of the Owner�s field representative, shall not be paid for separately but shall be removed and replaced at no additional cost to the Owner.

o. Water Service Line Replacements

Ahead of this project, the WRC is completing a Lead Service Line Replacement (LSLR) project to replace all full LSLs (where both public and private side were lead or galvanized steel) or where the private-side only was lead or galvanized steel. All public-side only LSLs (meaning the existing private-side service line is copper or plastic) were left to be completed as part of this project. All

HRC 5 of 6 5/22/2024 full LSLRs received a new curb stop and stop box under the LSLR project. The addresses in which full LSLRs were completed will be recorded and updated on the plans sheets as �Replaced 2025�. All other public service lines will be replaced with new Type K copper tubing and a new curb stop and stop box connected to the new water main.

The addresses with full LSLRs completed will still need to be reconnected to any new water main installed (except for any CIPP lined water main). Short side connections will intercept the new copper service line and connect directly to the new main. Long side services will need to be extended to meet the new copper service line. Long side service line connections from 0� to 10� long shall connect at the location of the existing water main. Long side service line connection greater than 20� long shall be drilled beneath the road and connected to the curb stop in the opposing green belt. The connection point for long side service line connections between 10� long and 20� long shall be at the discretion of the Owner�s field representative based on field conditions, location of the exiting water main in the roadway and impediments in the opposing green belt.

p. Unanticipated Discoveries Plan

The Fairview neighborhood of the City of Pontiac sits adjacent to historical sites. Prior to the start of the project, the WRC received clearance from Michigan�s State Historic Preservation Office (SHPO) to excavate in the Public Right of Way within the project area. However, during construction if the contractor encounters unanticipated archaeological material or human remains, they must stop work and follow the Unanticipated Discoveries Plan (UDP) document located in the attachments section of this contract. The conditions outlined in the UDP shall be reviewed prior to the start of the project and observed by the agency, municipality, project managers, those working on construction activities, heavy equipment operators, excavators, planners/designers, landscapers, and those planting or removing trees, laying or removing water lines, soil, fill, asphalt, and concrete, including during the removal and installation of sidewalks.

The Contractor shall acknowledge that they have reviewed and agree to the coordination and special conditions described in this Section by signing below.

Acknowledged By:

Company:

Signature:

Printed Name:

Title:

Date:

HRC 6 of 6 5/22/2024

Form DC�119 INFORMATION FOR BIDDERS

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-1 of IB-10 05/27/2020

1. 0200SCOPE OF WORK

The work under this Contract shall consist of the items listed in the Bidding Documents, including all incidentals necessary to fully complete the project in accordance with the Contract Documents.

2. RECEIPT AND OPENING OF BID PROPOSALS

A. Proposals will be received virtually by the Office of the Oakland County Water Resources Commissioner, (�Owner�) via www.bidnetdirect.com.

B. Bids must be submitted only on forms provided by Owner. All blank spaces for bid prices must be filled in, in ink or typewritten, and the bid form must be fully executed when submitted and not modified in any way.

D. Bids shall be made in full conformity with all the instructions, requirements and conditions set forth in the Information for Bidders and in the Drawings, Specifications and other Contract Documents. Bids are firm, and no bid may be withdrawn for a period of 120 days after opening of bids. Withdraw of the bid will result in the forfeiture of the Bidder�s Bid Bond.

E. Any bid received after the exact time specified for receipt will not be considered.

This material requirement is not subject to waiver by Owner.

4. DEFINITIONS

Certain terms used in the Contract Documents shall have the meanings indicated in the General Conditions and Supplementary Conditions which are part of the Contract Documents.

5. INSPECTION OF SITE, INSPECTION OF CONTRACT DOCUMENTS, PLANNING AND

ANALYSIS

A. Before submitting a Bid, each Bidder is responsible for inspecting the site of the proposed work, and the surrounding premises, to arrive at a clear understanding of the conditions under which the work is to be performed.

B. Before delivery of its Bid, each Bidder is held to have compared the conditions of the site where work is to be performed with the Contract Documents and to have satisfied itself as to the conditions of the site and surrounding premises, including any obstructions, all excavating, filling in, and quantities, and any other conditions affecting the carrying out of the work, including the weather conditions of the project area. Each Bidder must obtain first-hand information concerning the available facilities for receiving, transporting, handling and storing construction equipment and materials and concerning other local conditions that may affect its work. Each Bidder must acquaint itself with the character and extent of the operations of the Owner and any other contractors in the area of the work, so that the Bidder can plan its work accordingly.

C. Bidders must estimate the quantity of materials, labor and equipment required for the work by examination of the site and a review of the Contract Documents including

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-2 of IB-10 05/27/2020

Addenda, and by carefully considering all other relevant factors. Bidder warrants that by submitting its Bid, it had no misunderstanding concerning the quantities or nature of the work to be performed, and the Bidder will assert no such claim asserting such a misunderstanding.

D. No allowances or extra payment will be made to Contractor because of costs or expenses occasioned by Contractor�s failure to comply with the provisions of this section, or by reason of error or oversight on the part of the Bidder, or on account of interference by the activities of the Owner or any other contractor where those activities are apparent, or are made known to the Bidders during the bidding process.

E. For bidding purposes, the Bidder is responsible for evaluating the compatibility of proposed construction methods with the Contract Documents, and soil and site information. Bidders must carefully study and compare all portions of the Contract Documents and must notify the Engineer, in writing, prior to the deadline for pre-bid questions, of any concerns, questions, apparent ambiguities, conflicts, incompatibilities, apparent errors, or other discrepancies evident in the Contract Documents.

F. The successful Bidder must complete the work under whatever conditions it may create by its own actions or inactions, sequence of construction, construction means and methods, or other conditions it may create or cause to be created at no additional cost to Owner.

6. UNDERGROUND CONDITIONS

A. The Engineer performed investigations and issued reports which are available to the Contractor.

B. Each Bidder and the Contractor awarded the project shall draw their own conclusions as to site, underground or soil conditions from their own experience, independent knowledge and investigation of the site, and they should each secure such other and additional information and data as they consider necessary or desirable to check and supplement the provided underground data for specific locations. The Contractor is required to complete the work under any job or field condition which was present and/or ascertainable prior to Bidding.

C. All Bidders that seek to conduct any additional underground or site exploration or testing must do so at their own expense as necessary. Such Bidders must contact the Owner and obtain its written permission before proceeding.

D. Any additional exploration conducted by Bidders must be performed in a manner which precludes unnecessary disruption of the soils or which impedes construction operations and must be performed in compliance with the Mineral Well Act, Act No. 315 of the Public Acts of 1969, as amended, MCL 319.211, et. seq. Any Bidder performing exploration work must restore all areas of exploration to its original condition. By entering the site to conduct such investigation and testing, the Bidder agrees to indemnify, defend and hold harmless all of the persons identified in the indemnity provisions of the General and Supplementary Conditions to the full extent of the indemnity obligation set forth in those Contract Documents.

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-3 of IB-10 05/27/2020

7. AWARD OF CONTRACT

A. The Contract, if awarded, will be awarded to the lowest, responsive, and responsible bidder, subject to the final approval by the Oakland County Water Resources Commissioner. The Contract will be awarded subject to receipt of funds to finance the project and acquisition of easements, during which time the Bid guarantees of the lowest three responsive, responsible Bidders will be held.

B. The party to whom the Contract is awarded will be required to execute the Agreement and obtain the Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and shall provide proofs of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award to the successful Bidder. The necessary Agreement and Bond forms shall accompany the Notice of Award. If the Contractor awarded the project fails to execute the Agreement, submit Performance Bond, Labor and Material Bond and Maintenance and Guarantee Bond and provide proofs of insurance coverage in accordance with the Contract Documents within ten (10) calendar days of the delivery date of the Notice of Award, the Owner may declare the Contractor in default, in which case the Bid Bond accompanying the Bid will be forfeited to the Owner.

8. INTERPRETATION OF CONTRACT DOCUMENTS

A. Neither Owner nor the Engineer will give verbal instructions prior to the award of the Contract. Any verbal statements regarding the Contract by any person are not authorized and do not constitute representations, warranties, modifications, agreements, or promises, express or implied, and may not be relied upon by Bidders.

B. Bidders seeking explanations regarding the project or the Contract Documents must submit written requests through the Michigan Inter-Governmental Trade Network (MITN) website via BidNet Direct, and if explanations are necessary an Addendum will be issued and posted to the Bidnet Direct/MITN website with answers. The determination of the necessity of explanations will be in the sole discretion of the Engineer and Owner and no obligation to provide an addendum will be implied.

C. Questions, comments, or concerns of any Bidder regarding bidding or the Contract Documents or the project, must be submitted via BidNet Direct/MITN and in advance of the opening of bids per the time period specified in the Advertisement

D. Addenda issued to Bidders prior to the date of receipt of bids shall become a part of the Contract Documents and all bids shall include the work described in each and every Addenda issued.

9. NAME AND STATUS OF BIDDER

A. The name and legal status of the Bidder, that is, as a corporation, limited liability company, partnership, limited partnership or individual, must be stated in the Bid Form.

B. The place of residence of Bidder, or the office address in the case of a firm or company with county and state, must be stated in the Bid Form.

C. Unless the legal status of the Bidder is an Individual, the signature(s) of the signing

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-4 of IB-10 05/27/2020 official(s) must be accompanied by the appropriate Resolution or Certificate Form found at the end of the Bid Form, properly executed, authorizing the official(s) to sign both the Bid Form and the Contract. Failure to submit this form is basis for rejecting the Bid.

10. QUALIFICATION OF BIDDERS AND SUBCONTRACTORS

A. Except as otherwise reserved herein, Owner will only award the Contract to a responsible Bidder. A finding that the Contractor is not responsible in connection with this project shall not necessarily preclude the Bidder from bidding and performing work on other projects for the Owner.

B. Factors to be considered in determining whether Owner�s standard of responsibility has been met shall include, but not be limited to, whether the Contractor has:

1) The appropriate financial, material, equipment, facilities, and personnel resources and expertise available, or the ability to obtain them, necessary to indicate it is capable of meeting all contractual requirements;

2) A satisfactory record of performance;

3) A satisfactory record of integrity;

4) Qualified legally to contract with Owner and has supplied all necessary information in connection with the inquiry concerning responsibility.

5) If Contractor has been deemed non-responsible in the past, provided a detailed explanation of its remedial actions subsequent to the determination to address any concerns expressed by the authority making the declaration such that the authority would consider awarding a contract to the Contractor, notwithstanding past concerns about Contractor�s performance.

C. The Contractor must supply information requested by Owner concerning the responsibility of the Bidder. If the Bidder fails to supply the requested information, the Owner must base the determination of responsibility upon any available information or may find the Bidder non-responsible if such failure is unreasonable. A finding that the Bidder has failed to make a required disclosure or submitted false information may result in immediate disqualification of the Bidder.

D. Within 10 days after bids are received by the Owner, the Contractor who has submitted the low bid must, upon request of the Owner, complete and submit to the Owner the following:

1) MIOSHA Form 300 � �Log of Work-Related Injuries� for the last 3 years.

2) MIOSHA Form 300A - �Summary of Work-Related Injuries & Illnesses� for the last 3 years.

E. In addition to meeting the criteria set forth in this Article, and the submission of the required information requested herein, the ability of the Contractor and its identified Subcontractors to proficiently handle technical issues, safety, scheduling, and

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-5 of IB-10 05/27/2020 administrative issues as demonstrated by its past performance on projects for the Owner, as well as projects for other public agencies, will be considered in determining whether a Contractor is a responsible contractor for this project. Past performance issues to be considered include, but are not limited to, the following:

1) Failure to adhere to and/or comply with Contractor�s obligations in the Contract Documents

2) Failure to follow administrative procedures and provisions in the Contact Documents

3) Submission of false claims or falsely inflated claims

4) Failure to prosecute the work in accordance with the Plans and Specifications included in the Contract Documents

5) Failure to follow bidding instructions.

F. The Bidder shall promptly submit upon request by the Owner, any additional information necessary to satisfy the Owner that the Bidder is adequately prepared to fulfill the Contract.

G. The existence of any judgment, citation, default, finding of non-responsibility or other negative information disclosed by Contactor in its Experience and Qualification Statement or independently discovered by Owner, or Contractor�s failure to provide the certifications required by this Article, will be considered, among all other factors, in determining whether a Contractor is a responsible Bidder for this project. As part of its response, Contractor may submit an explanation of the facts giving rise to the judgment, citation, default, or negative finding, or reasons why the required certifications cannot be provided, and ask Owner to deem the Contractor both responsive and responsible notwithstanding such facts or omissions.

H. The requirements identified above are not an exhaustive or exclusive list of all qualifications required of the Contractor, its Subcontractors, or personnel. The minimum requirements indicated above are in addition to any other requirements contained elsewhere in the Contract Documents and/or typically considered under state or federal procurement law.

I. Owner may, when circumstances warrant, accept any Bidder as a responsible Bidder despite its failure to meet all of the minimum standards set out herein. To the extent that special circumstances exist which a Bidder believes render the Bidder a qualified and responsible Bidder for this project, despite the failure to meet one or more of the standards for qualification set out herein, the Bidder may submit a notarized sworn statement explaining the special circumstances and requesting consideration of its Bid.

Notwithstanding the foregoing, Owner has no obligation to consider such special circumstances, or to disregard the requirements set forth in this Article and elsewhere in the Contract Documents and deem the Bidder responsible.

J. Bidder must attend a pre-award conference to satisfy the Owner that the Bidder is adequately prepared to fulfill the Contract.

OAKLAND COUNTY WATER RESOURCES COMMISSIONER

Page IB-6 of IB-10 05/27/2020

K. If a Bidder who otherwise would have been awarded a contract is found non-responsible, a written determination of non-responsibility setting forth the basis of the finding will be prepared by the Owner upon request. A copy of the determination will be sent promptly to the non-responsible Bidder. The final determination will be made part of the bid file.

L. The Contractor must self-perform at least 51% of the construction trade work as determined by dollar value. This does not include General Conditions.

11. CONTRACTOR AND SUBCONTRACTOR INFORMATION AND LISTING

A. Bidder must provide a completed Experience and Qualification Statement (DC-118) with its bid. Additional qualification information as requested by Owner shall be submitted within 10 days after bids are received by the Owner including but not limited to a completed Experience and Qualification Statement (DC-118) for each and every Subcontractor who will work on the project.

B. Bidders shall submit with their bid a list by name, trade and scope of work each and every Subcontractor who will perform Work with a value in excess of 10 % of Bid Total.

12. PRELIMINARY SCHEDULE

A. Each Bidder shall submit with their bid a Preliminary Schedule demonstrating the Bidder�s plan to complete the construction work within the time allowed in the Agreement and to achieve the completion of any milestones identified in the Contract Documents.

The requirements of the Preliminary Schedule are described in the General Specification.

B. Failure to provide the requested schedule may result in the Contractor being declared non-responsive.

C. The Bidder�s Preliminary Schedule shall be based on a Notice to Proceed date identified in the bidding documents.