3. Airfield Striping Specs.pdf
PDF 247 KB Posted
- Attached to
- Airfield Pavement Striping Federal contract opportunity
- Solicitation number
- FA9401-12-R-0017
About this file
Attachment 3
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA9401-12-R-0017 Amendment 2.pdf | ||
| Response to Bidder Questions Airfield Pavement Striping.pdf | ||
| Site Visit Sign in Sheet.pdf | ||
| Amendment 1 to Solicitation.pdf | ||
| 10. Wage Determination NM120047 NM47.pdf | ||
| 8. AF_3000.pdf | ||
| 2. Drawing 100068C1.pdf | ||
| FA9401-12-R-0017.pdf | ||
| 9. Construction AF Form 66 - Airfield Striping.pdf | ||
| 1. Statement of Work-MHMV100068.pdf | ||
| 5. AF 3064-Progress Schedule.xls | XLS spreadsheet | |
| 12. Past Performance Information Form.pdf | ||
| 7. Permit Requirement Memorandum.pdf | ||
| 6. AF 3065 Progress Report.pdf | ||
| 4. AF Form 3052 Contractor Proposal Form.xlsx | XLSX spreadsheet | |
| 11. KAFB Map for Site Visit Location | — |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Airfield Pavement Striping MHMV 100068 Kirtland AFB, NM
Project Table of Contents Page 1
PROJECT TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT REQUIREMENTS
00 01 15 LIST OF DRAWINGS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 16.00 20 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
-- End of Project Table of Contents --
Document 00 01 15 Page 1
SECTION 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. TITLE
C-1 Airfield Pavement Striping
-- End of Document --
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E 2114 (2008) Standard Terminology for
Sustainability Relative to the Performance of Buildings
GREEN BUILDING INITIATIVE (GBI)
Green Globes (2004) Green Globes(tm) US Green Building
Rating System
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star (1992; R 2006) Energy Star Energy Efficiency
Labeling System
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED (2002; R 2005) Leadership in Energy and
Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC)
LEED AF SDD Implementing Guidance dated 02 Jun
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E 2114, Section 01 35 40.00 20 ENVIRONMENTAL MANAGEMENT, and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services.
This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
Section 01 11 00 Page 2
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Submit the following items to the Contracting Officer:
Safety Plan
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The work includes the following and incidental related work.
This project will re-stripe portions of the KAFB Airfield including ramps B, C, D and E. Repairs include restriping taxilines, access road designation lines, stop bars, hold lines, parking designations, AGE equipment areas, toolbox tie-down boxes as well as any additional striping related items deemed necessary to provide a satisfactory project. Major work to be accomplished includes, but is not limited to furnishing all plant, labor, equipment and materials for materials testing, working drawing preparation, site preparation, striping and construction. Refer to drawing and specifications for further information.
Contractor will be responsible for obtaining and maintaining a Traffic Control Plan to allow for the safe and efficient movement of vehicular and pedestrian traffic during construction.
1.4.2 Location
The work shall be located at Pad 5, KAFB. The exact location will be shown by the Contracting Officer.
1.5 WORK RESCHEDULING
Contractor shall allow for a maximum of zero calendar days where construction activity is prohibitive. Further allowance for zero calendar days of excavation and subsurface activity abeyance shall be imposed where other construction activities are permitted. Government will provide 24 hour notification each time the restrictions are invoked.
Normal duty hours for work shall be from 7:00 a.m. to 4:00 p.m., Monday through Friday. Requests for additional work shall require written approval from the Contracting Officer 7 calendar days in advance of the proposed work period.
1.6 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability.
Specifically:
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.
Section 01 11 00 Page 3
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
c. Use environmentally preferable products and decrease toxicity level of materials used.
d. Use renewable energy and material resources.
e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.
Consider the durability, maintainability, and flexibility of building systems.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.
g. Reduce construction waste through reuse, recycling, and supplier take-back.
1.7 OCCUPANCY OF PREMISES
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access and space for storage of materials and equipment.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Preconstruction Submittals
List of Contact Personnel
Personnel List
Vehicle List
Statement of Acknowledgement Form SF 1413
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear proper PPE in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.
The Contractor's equipment shall be conspicuously marked for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines.
1.2.2 Working Hours
Regular working hours shall consist of a 9 hour period established by the Contractor Officer, between 7 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
Section 01 14 00 Page 2
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3 SECURITY REQUIREMENTS
1.3.1 Parking
Do not park on or block the marked fire lanes at any time. Do not park on established landscape, vegetation, or undisturbed topsoil except as approved by Contracting Officer. Contractor shall be responsible for any damage done due to vehicle parking.
1.3.2 Vehicle Searches
Vehicles are subject to search while entering, remaining in, or leaving
KAFB.
1.3.3 Access to Unclassified Information
Access to unclassified technology and related technical information manuals, documents, drawings, plans, specifications, and other unclassified information is restricted to official need-to-know basis, designated by physical markings to show the appropriate control designations. Handle, control, and safeguard to prevent oral, visual, and documentary disclosure to the public, to foreign sources, and to personnel not having an official need-to-know. Return this information to the Contracting Officer upon completion of contracted work, except when specific retention authorization is granted by the Contracting Officer's Security Representative.
1.3.4 Photographs
Unofficial photography is prohibited. When operationally required, submit a written request containing specific justification and details to the Contracting Officer prior to release.
1.3.5 Personnel List
Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Date and place of birth
c. Citizenship
Section 01 14 00 Page 3
d. Home address
e. Social security number
f. Current pass expiration date
g. Naturalization or Alien Registration number
h. Passport number, place of issue, and expiration date
i. Other information as requested by Contracting Officer at time of desired access.
The request for personnel passes shall be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."
Signature/Firm Name
1.3.6 Vehicle List
Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:
a. Make
b. Year
c. Model
d. License number
e. Registered owner
1.3.7 Passes
Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.
1.3.7.1 Control
Maintain strict accountability over passes. Immediately report, to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.
1.3.8 Inspection
Section 01 14 00 Page 4
Personnel, equipment and plant are subject to inspection. Personnel are also subject to physical searches at random intervals.
Not Used
Section 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
View location map
Draft Waste Management Plan
1.2 PRE-EXISTING CONDITION PHOTOS
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from locations identified on the View Location Map approved by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch.
The view location sketch shall also be provided on the CD as digital file.
All file names shall include a date designator. Photographs shall be provided for unrestricted use by the Government.
1.3 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.4 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.5 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of shop drawings or planning documents related to the referenced contract subject to the following terms and conditions. Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of shop drawings for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government or Designer of Record. The Contractor shall make no claim and waives to the fullest extent
Section 01 30 00 Page 2 permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing shop drawings. Data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.6 E-MAIL ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
Section 01 32 16.00 20 Page 1
SECTION 01 32 16.00 20
CONSTRUCTION PROGRESS DOCUMENTATION
11/09
PART 1 GENERAL
1.1 SUBMITTALS
Construction schedule (AF3064)
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of an AF3064 in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract. Acceptance of an error free AF3064 and updates is a condition precedent to processing the Contractor's pay request.
1.3 SCHEDULE FORMAT
1.3.1 AF3064
The AF3064 shall show submittals, government review periods, material/equipment delivery, utility outages, material lead times, on-site construction, inspection, testing, and closeout activities. Follow the directions as printed on the AF3064.
1.4 UPDATED� SCHEDULES
Update the Construction schedule at monthly intervals or when the schedule has been revised. The updated schedule shall be kept current, reflecting actual activity progress and plan for completing the remaining work as well as delays and modifications to the contract duration. Submit copies of purchase orders and confirmation of delivery dates as directed.
1.5 CORRESPONDENCE AND TEST REPORTS:
All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs, etc.) shall reference Schedule activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure, etc.) shall reference schedule activities that are being addressed.
Section 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken.
Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
Submittals are to be submitted and approved prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions
Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description titles as follows:
Submittals which are required prior to start of construction (work):
Certificates of insurance Surety bonds List of Subcontractors
AF3064
Project-Specific AF66 Schedule of Prices Health and Safety plan Quality Control(QC) plan Waste Management Plan Preliminary AF1354 Preconstruction Submittals as listed in other Sections
Shop Drawings
Section 01 33 00 Page 2
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Section 01 33 00 Page 3
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS) concerning impedances, hazards and safety precautions.
Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment.
This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Section 01 33 00 Page 4
Special requirements necessary to properly close out a construction contract.
For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD- 01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Submit the following in accordance with this section.
Project-Specific AF66
1.4 VARIATIONS
Variations from contract requirements require Government approval and will be considered where advantageous to Government.
1.4.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.4.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
1.4.3 Warranting That Variations Are Compatible
Section 01 33 00 Page 5
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 14 calendar days will be allowed for consideration by the Government of submittals with variations.
1.5 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
d. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 15 days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from Contractor.
e. Period of review for each resubmittal is the same as for initial submittal.
1.6 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received from Contractor.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions listed on AF3000 and with markings appropriate for action indicated.
Upon completion of review of submittal, stamp and date approved submittals.
3 copies of the approved submittal will be retained by the Contracting
Section 01 33 00 Page 6
Officer and 1 copy of the submittal will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above.
1.7 DISAPPROVED SUBMITTALS
Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.8 APPROVED SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check and indicates only that the general method of construction, materials, detailing and other information are satisfactory.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, compliance with the drawings, specifications and amendments etc., and the satisfactory construction of all work.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.9 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples including those which may be damaged in testing, will be returned to the Contractor upon completion of the contract. Samples not approved will also be returned to the Contractor if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of
Section 01 33 00 Page 7 the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.
Contractor to replace such materials or equipment to meet contract requirements.
Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.
1.10 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
Section 01 35 26 Page 1
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
02/10
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are both national regulations and standards incorporated by reference.
29 CFR 1926 OSHA Construction Standards 29 CFR 1910 OSHA General Industry Standards NFPA Standards (National Fire Protection Association) ASSE/SAFE A10.34 Protection of Public on/Adjacent to Construction Sites Chapter 65 NMSA 1978 Motor Carriers Chapter 66 NMSA 1978 Motor Vehicles CFR Title 49 DOT Federal Motor Carrier Safety Regulations NMAC Title 16 Chapter 43 Part 2 – Hoisting Operators
It is the responsibility of the contractor to familiarize themselves with and perform all work in accordance with all applicable regulations as well as any and all non-regulatory standards which are incorporated by reference through Federal, State and local regulations.
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
Preconstruction Submittals
Site-Specific Safety Plan
Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."
Accident Reports
1.3 REGULATORY REQUIREMENTS
Contractor will perform all work in accordance with all national, state and local regulations and standards to include safety, environmental and transportation requirements.
1.4 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.4.1 Personnel Qualifications
1.4.1.1 Site Safety Representative
The contractor shall provide the name and identity of at least one employee who shall be designated as the site safety representative. This
Section 01 35 26 Page 2 person will be the contact person for the contractor should any questions or concerns arise with regard to health, safety or environmental.
a. Conduct safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily [production][quality control] report.
b. Ensure sub-contractor compliance with safety and health requirements.
1.4.1.2 Crane/Hoist Operators
Crane/hoist operators must be certified and licensed through the State of New Mexico in accordance with NMAC Title 16 Chapter 43 Part 2.
1.4.2 Meetings
1.4.2.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference.
b. Discuss the details of the scope of the work and the contractor-submitted Site-Specific Safety Plan. SSSP will include incorporated plans, programs, procedures and specific actions and requirements that may be encountered during the performance of the contract.
c. Deficiencies in the submitted Site-Specific Safety Plan will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted Site-Specific Safety Plan.
d. The functions of a Preconstruction conference may take place at the
Post-Award Kickoff meeting for Design Build Contracts.
1.4.2.2 Safety Meetings
Conduct and document work site/tailgate safety meetings at least once per week. Attach minutes showing contract title, presenter, signatures of attendees and a list of topics discussed to the contractor’s daily report.
1.4.2.3 Pre-Outage Coordination Meeting
Pre-Outage Coordination Meeting Contractors are required to apply for utility outages at least 14 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting
Section 01 35 26 Page 3 with the Contracting Officer and the Installation representative to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
1.5 SITE SPECIFIC SAFETY PLAN (SSSP)
Contractor shall submit and maintain a Site-Specific Safety Plan which shall describe the methods that will be utilized in addressing/mitigating hazards that are expected to be encountered during the work phase. The SSSP shall interface with the contractor’s overall Safety & Health Program. The government considers the prime contractor to be the “controlling authority” for all work site safety and health concerns regarding their subcontractor. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for non-compliance, coordinating the work to prevent on craft from interfering with or creating hazardous working conditions for other crafts and inspecting subcontractor operations to ensure that hazard prevention responsibilities are being carried out.
Submit the SSSP to the Contracting Officer 10 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted SSSP.
Once accepted by the Contracting Officer, the SSSP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified.
Once work begins, changes to the accepted SSSP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control manager. Should any severe hazard exposure, i.e. imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.
Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site.
Continuously review and amended the SSSP, as necessary and providing the Contracting Officer with the amended SSSP, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original SSSP as they are discovered.
1.5.1 29 CFR 1926 & 1910 Contents In addition to the Site Safety Plan requirements the following is required:
Section 01 35 26 Page 4
a. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection;
cranes, structural steel assembly, underground construction, health hazard recognition, and evaluation and control of chemical, physical and biological agents.
b. Confined Space Entry Plan. Develop a confined space entry plan in accordance with applicable OSHA standards 29 CFR 1926 and 29 CFR 1910, OSHA Directive 2.100, and any other federal, state and local regulatory requirements identified in this contract. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)
c. Crane Critical Lift Plan. Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist (or lifts over 50 percent of the capacity of a barge mounted mobile crane's hoists) at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel; and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. Submit 15 calendar days prior to on-site work and include the requirements of the applicable national, state and local standards.
(1) For lifts of personnel, demonstrate compliance with the requirements of 29 CFR 1926.550(g).
d. Fall Protection and Prevention Plan (FPPP). The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person for fall protection shall prepare and sign the FPPP. Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, rescue procedures, training requirements, and monitoring methods. Revise the Fall Protection and Prevention Program documentation as necessary reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Program documentation at the job site for the duration of the project.
Include the Fall Protection and Prevention Program documentation in the Site Specific Safety Plan.
e. Lead Compliance Plan. The safety and health aspects of lead work, prepared in accordance with national, state and local requirements.
f. Asbestos Hazard Abatement Plan. The safety and health aspects of asbestos work, prepared in accordance with national, state and local requirements.
g. Site Demolition Plan. The safety and health aspects prepared in accordance with national, state and local requirements.
Section 01 35 26 Page 5
1.6 DISPLAY OF SAFETY INFORMATION
Within 1 calendar day after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by Federal, State and local regulations. Additional items that may be posted include:
a. Confined Space Entry Permit
b. Burn Permit
c. List of Emergency Contact Numbers
1.7 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project at the project site. Maintain applicable equipment manufacturer's manuals as well as material safety data sheets for all hazardous materials.
1.8 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment.
Government has no responsibility to provide emergency medical treatment.
1.9 REPORTS, PERMITS AND CERTIFICATES
1.9.1 Accidents
a. Conduct an accident investigation for all injuries and illnesses which require or result in the need for professional medical treatment. This includes any injuries which result in a trip to an emergency room or urgent care center. Contractor will complete their own accident/incident report and will forward a completed copy of the report to the contracting officer within 48 hours.
b. Conduct an accident investigation for any incident which results in damage to contractor or government property. Contractor will complete their own accident/incident form and will forward a completed copy of the report to the contracting officer within 48 hours.
1.9.1.1 Accident Notification
Notify the Contracting Officer as soon as practical, but not later than four hours, after any accident which results in injury (as described in 1.9.1a above) or damage to property (as described in 1.9.1b above).
Preserve the conditions and evidence on the accident site until the
Section 01 35 26 Page 6
Government investigation team arrives on-site and Government investigation is conducted.
1.9.2 Certificate of Compliance
Provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate).
State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. Also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices).
1.9.3 Hot Work
Submit and obtain a written Burn Permit prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, from the KAFB Fire Department. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A BURN PERMIT IS ISSUED. The Contractor will provide an ABC rated extinguisher for normal "Hot Work".
All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.
1.10 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
Section 01 35 26 Page 7
PART 2 EXECUTION
2.1 Confined Space Entry Requirements
Contractors entering and working in confined spaces performing shipyard industry work are required to follow the requirements of OSHA 29 CFR 1926 & 1920. All permitted-confined space entries must be coordinated through the contracting office prior to commencement.
2.2 Fall Protection Anchorage
Leave in place fall protection anchorage, conforming to ASSE/SAFE Z359.1, installed under the supervision of a qualified person in fall protection, for continued customer use and so identified by signage stating the capacity of the anchorage (strength and number of persons who may be tied-off to it at any one time).
2.3 Construction and/or Other Work
Comply with Federal, State and local regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
2.4 Hazardous Material Use
Each hazardous material must receive approval from the Contracting Office or their designated representative prior to being brought onto the job site or prior to any other use in connection with this contract.
The submittal for hazardous materials must include container sizes/types, total quantities per material and the most current material safety data sheet for each substance. Allow a minimum of 10 working days for processing of the request for use of a hazardous material.
2.5 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e. 29 CFR Part 1910.1000). If additional material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. The Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
Section 01 35 26 Page 8
2.6 Control of Hazardous Energy (Lockout/Tagout)
Contractor shall ensure that each employee is familiar with and complies with the requirements of CFR 1926.417 and NFPA 70E.
No person, regardless of position or…