FA910115R0038_001_Hydraulic_Skid_Amend.pdf
PDF 136 KB Posted
- Attached to
- Hydraulic Skid
- Solicitation number
- FA9101-15-R-0038
About this file
FA910115R0038 0001 Hydraulic Skid Amend 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA910115R0038_0003_Hydraulic_Skid_Amend.pdf | ||
| FA910115R0038_0002_Hydraulic_Skid_Amend.pdf | ||
| FA910115R0038_Hydraulic_Skid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
y
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
See Block #2
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
19 AUG 2015
4. REQUISITION/PURCHASE REQ.NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY AFTC/PZI ARNOLD CODE FA9101 7. ADMINISTERED BY (If other than Item 6) CODE
AEDC/PZI
100 KINDEL DRIVE, SUITE A-332
ARNOLD AFB, TN 37389-1332
MIRIAM J. HARRIS 931-454-5139
miriam.harris.1@us.af.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
FA9101-15-R-0038
X
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, X is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X )
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: ( ) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. ITEM
10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment provides clarifications to questions received regarding the Equipment Specification. See the Schedule.
The due date and time are not extended. Proposals are due 10 September 2015, 2 pm CST.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print).
16A. NAME AND TITLE OF SIGNER (Type or print)
TONY CLAYBORNE
15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
16C. DATE SIGNED
(Signature of person authorized to sign)
BY________________________________________
(Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA ConWrite Version 6.14.5 FAR (48 CFR) 53.243 Created 19 Aug 2015 10:31 AM
SCHEDULE
FA9101-15-R-0038 0001
The following provides clarifications to questions received regarding the Equipment Specification are hereby incorporated for clarification purposes.
Clarification: 3.10.8. The bypass on the high pressure filter should be low enough that the pressure delta does not damage the element in the filter. If a filter element can withstand higher pressure drop than the 15 psid in the specification, we could entertain allowing for higher pressure during the design reviews that occur after the contract. However, we would not want to accept a loss of 100 psi of system pressure due to the filter. For now, the bidders should base their quotation on a system that can meet this specification, but it could be a point of discussion during design reviews.
Clarification: 3.10.26 / 3.10.27. Under normal operation, the accumulators will not provide flow to the users.
Clarification: 3.10.28. The bidders are expected to provide a hydraulic schematic as a deliverable of this project. AEDC has provided a basic algorithm for how we want the cabinet to operate and it is up to the bidder to design a cabinet that will perform in the way we described. Note that the bidders are limited to using the types of elements and components we specified (for example, DIN/ISO port pattern sandwich valves bolted to a manifold in a stack arrangement).
Inquiry regarding the availability of electrical schematics for HPU, Accumulator skis, and valve control cabinets. Response: The electrical schematics on the AEDC end will be designed to interface with the hardware supplied by the successful offeror.
File details come from the government source that posted it. Updated .