FA8818-13-R-0021_LSMA_SecL_B_FINAL.docx

DOCX document 82 KB Posted

Attached to
LAUNCH SERVICES MISSION ASSURANCE Federal contract opportunity
Solicitation number
FA8818-13-R-0021
Issued by
Department of the Air Force Space Command Space and Missile Systems Center

About this file

LSMA Final RFP Section L APPENDIX B - Proposal Cross Reference Matrix

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix B: L/M Cross-Reference Matrix

This Appendix provides a cross-reference table of Technical Volume Proposal Tabs (defined at Section L para 4.2) against the Performance Work Statement requirement(s) that Tab reflects and the Section M criterion which that Tab will be evaluated against. Offerors shall fill in the other 3 columns as follows: Under “CWBS Ref” the offeror shall cite the CWBS elements which are relevant to that tab; under “Proposal Reference” the offeror shall identify where in their proposal that Proposal Tab is located; under “Applicable CLINs” the offeror shall identify the proposed CLIN(s) to which that Proposal Tab is applicable. The completed Cross-Reference Matrix shall be provided as Tab 5h of the proposal.

Directed Proposal Tab (Per Section L Instructions)
PWS Requirement(s)
Section M Criterion
CWBS Ref
Proposal Ref
Applicable CLIN(s)
(1) Table of Contents
N/A
Not Evaluated; reference only
(2) Glossary
N/A
Not Evaluated; reference only
(3a) XBM Sustainment Engineering
3.1.x (any)*
2.2.1.8 – XBM Enhancements
(3a-1) XBM Refurbishment
3.1.9, 3.1.11, 3.1.13
2.2.1.1 – XBM Refurbishment
(3a-2) XBM AS and Sustainment Process
3.1.3, 3.1.4, 3.1.5, 3.1.6, 3.1.7, 3.1.12, 3.1.20, 3.1.21, 3.1.22, 3.1.23, 3.1.24, 3.1.25, 3.1.26, 3.1.27, 3.1.29, 3.1.30, 3.1.31, 3.1.32, 3.1.33, 3.1.34, 3.1.35, 3.1.37, 3.1.38, 3.1.39
2.2.1.2 – XBMAS and Sustainment Process
(3a-3) XBM AS Requirements
3.1.2
2.2.1.3 – XBM AS Requirements
(3a-4) XBM AS Planning
3.1.1, 3.1.10
2.2.1.4 – XBM AS Planning
(3a-5) XBM AS Analysis
3.1.14, 3.1.15, 3.1.16, 3.1.17, 3.1.18
2.2.1.5 – XBM AS Analysis
(3a-6) XBM AS Reporting
3.1.19
2.2.1.6 – XBM AS Reporting
(3a-7) XBM Refurbishment Procedures
3.1.28, 3.1.36
2.2.1.7 - XBM Refurbishment Procedures
(3b) Launch System IV&V
3.2.x (any)*
2.2.2.10 – IV&V Enhancements
(3b-1) Launch System IV&V Analysis
MA Cat 1/2/3 MIDS: 3.2.x.1, 3.2.x.2, 3.2.x.3, 3.2.x.4, 3.2.x.5, 3.2.x.6, 3.2.x.8, 3.2.x.9, 3.2.x.14, 3.2.x.15, 3.2.x.16, 3.2.x.17, 3.2.x.18, 3.2.x.19, 3.2.x.20, 3.2.x.24

Construct 2 MIDS:

3.2.4.1, 3.2.4.2, 3.2.4.4, 3.2.4.7

2.2.2.1 – Launch System IV&V Analysis

(3b-2) Launch System IV&V Reporting
MA Cat 1/2/3 MIDS:

3.2.x.10, 3.2.x.11, 3.2.x.26

Construct 2 MIDS:

3.2.4.3, 3.2.4.8

2.2.2.2 – Launch System IV&V Reporting

(3b-3) Launch System Risk Assessment
MA Cat 1/2/3 MIDS:

3.2.x.12, 3.2.x.13, 3.2.x.21, 3.2.x.22, 3.2.x.23, 3.2.x.24

Construct 2 MIDS:

2.2.2.3 – Launch System Risk Assessment

(3b-4) Launch System IV&V Tools
MA Cat 1/2/3 MIDS:

3.2.x.14, 3.2.x.15, 3.2.x.16, 3.2.x.17, 3.2.x.18, 3.2.x.19, 3.2.x.20

Construct 2 MIDS: N/A

All: 4.2.18

2.2.2.4 – Launch System IV&V Tools

(3b-5) Launch System Requirements IV&V
MA Cat 1/2/3 MIDS:

3.2.x.4, 3.2.x.6, 3.2.x.14, 3.2.x.15, 3.2.x.16, 3.2.x.17, 3.2.x.18, 3.2.x.19, 3.2.x.20

Construct 2 MIDS:

3.2.4.4, 3.2.4.6

2.2.2.5 – Launch System Requirements IV&V

(3b-6) Launch System Payload Integration Verification
MA Cat 1/2/3 MIDS: 3.2.x.7, 3.2.x.25

Construct 2 MIDS: N/A

2.2.2.6 – Launch System Payload Integration Verification

(3b-7) Launch System Range Integration Verification
MA Cat 1/2/3 MIDS: 3.2.x.7, 3.2.x.25

Construct 2 MIDS: N/A

2.2.2.7 – Launch System Range Integration Verification

(3b-8) Launch System Interface Verification
MA Cat 1/2/3 MIDS:

3.2.x.7

Construct 2 MIDS:

3.2.4.5

2.2.2.8 – Launch System Interface Verification

(3b-9) XBM Motor Utilization
MA Cat 1/2/3 MIDS: 3.2.1.20, 3.2.2.20, 3.2.3.20, 3.2.5, 3.2.6

Construct 2 MIDS: 3.2.5, 3.2.6

2.2.2.9 – XBM Motor Utilization

(3b-10) Sample Mission Proposals
Varies per MID and offeror’s mission-specific proposal
2.2.2.1 thru 2.2.2.10 (all)
(4a) Management Approach
-
-
(4a-1) Program Interface
4.1, 4.2, 4.6, 4.7, 4.8
2.3.1.1 - Program Interface
(4a-2) Lessons Learned Dissemination
3.2.1.26.2, 3.2.2.23.1, 3.2.4.8, 3.2.5.11, 3.2.6.8, 3.4.1.1
2.3.1.2 - Lessons Learned Dissemination
(4a-3) ASCON Interface
4.1, 4.2, 4.3, 4.5
2.3.1.3 - ASCON Interface
(4a-4) Fluctuation Management
4.1, 4.2, 4.5, 4.6, 4.7
2.3.1.6 - Fluctuation Management
(4b) Transition Plan
3.4.1
2.3.2.5 - Transition Plan Enhancements
(4b-1) 90 Day Attainment
3.1, 3.2.1, 3.2.2, 3.2.3, 3.2.4,

3.2.5, 3.2.6

2.3.2.1 - 90 Day Attainment

(4b-2) PWS Readiness
3.1, 3.2.1, 3.2.2, 3.2.3, 3.2.4,

3.2.5, 3.2.6, 3.3, 3.4

2.3.2.2 - PWS Readiness

(4b-3) Incumbent Interchange
PWS: N/A
2.3.2.3 - Incumbent Interchange
(4b-4) Follow-on Interchange
3.4.1
2.3.2.4 - Follow-on Interchange
(4c) Key Personnel
-
-
(4c-1) 5 Key Positions
PWS: N/A

Section H – “KEY POSITIONS AND MINIMUM QUALIFICATIONS” Clause

2.3.3.1 - 5 Key Positions

(4c-2) Key Personnel
PWS: N/A

2.3.3.2 - Key Personnel

(4c-3) Key Personnel Location
PWS: N/A

2.3.3.3 - Personnel Location

(4c-4) Transition Team
PWS: N/A

2.3.3.4 - Transition Team

(4d) Efficiency Plan
4.2.2, 4.9
2.3.4.1 - Price Target Oversight

2.3.4.2 - Target Price Reduction Enhancement

(5a) Correlation Matrix
N/A
N/A
(5b) CWBS w/ CWBS Dictionary
All
2.3.1.4 - Work Breakdown Structure (WBS)
(5c) Basis of Estimates
-
-
(5c-1) XBM Sustainment Engineering
3.1
2.2.1.1 – 2.2.1.8
(5c-2.x) New Launch System IV&V Sample Missions
3.2, 3.3, 3.4, 3.5
2.2.2.1-2.2.2.10
(5c-3.x) Existing Launch System IV&V Sample Missions
3.2, 3.3, 3.4, 3.5
2.2.2.1-2.2.2.10
(5d) Integrated Schedules
-
-
(5d-1) XBM Sustainment Engineering
N/A
2.2.1.1 – 2.2.1.8

2.3.2.1 - 90 Day Attainment

2.3.2.2 - PWS Readiness

2.3.2.4 - Follow-on Interchange

(5d-2.x) New Launch System IV&V Sample Missions
N/A
2.2.2.1-2.2.2.10
(5d-3.x) Existing Launch System IV&V Sample Missions
N/A
2.2.2.1-2.2.2.10
(5e) Sample IV&V Kickoff Presentation
3.2.2.23.1
2.2.2.1 – Launch System IV&V Analysis

2.2.2.2 – Launch System IV&V Reporting

(5f) Sample IV&V Midterm Presentation
3.2.2.23.2
2.2.2.1 – Launch System IV&V Analysis

2.2.2.3 – Launch System Risk Assessment

(5g) Sample IV&V Final Review
3.2.2.23.3
2.2.2.1 – Launch System IV&V Analysis

2.2.2.3 – Launch System Risk Assessment

(5h) [Not Used] Cross-Reference Matrix
N/A
N/A
(5i) AS9100 Certification (if applicable)
N/A
2.2.1.8 - XBM Enhancements 2.2.2.10 – IV&V Enhancements
(5j) Sample Aging Surveillance Analysis
3.1.14, 3.1.17, 3.1.18
2.2.1.5 - XBM AS Analysis 2.2.1.6 - XBM AS Reporting
(5k) Sample Refurbishment Work Package
3.1.11, 3.2.5.4
2.2.1.1 – XBM Refurbishment

2.2.1.7 - XBM Refurbishment Procedures

2.2.2.9 – XBM Motor Utilization

(5l) Copy of each document referred to in the CWBS dictionary
N/A
2.3.1.4 - Work Breakdown Structure
(5m) MAC-Tailored Reference Documents (refer to 7.3.4.3)
2.2
Any

* - Enhancements may be nominated relative to any effort in the cited section of the PWS effort, based upon the described approach.

File details come from the government source that posted it. Updated .