23_Atch_15_Performance_Incentive_Plan_(29_Apr_09).doc

DOC document 255 KB Posted

Attached to
GPS Advanced Control Segment (OCX) Blocks 1 & 2 Federal contract opportunity
Solicitation number
FA8807-09-R-0003
Issued by
Department of the Air Force Space Command Space and Missile Systems Center

About this file

23_Atch_15_Performance_Incentive_Plan_(29_Apr_09)

View the file

Other files for this federal contract opportunity

Other files attached to GPS Advanced Control Segment (OCX) Blocks 1 & 2, newest first.
File Type Posted
03 Section L_A0003_20090607.doc DOC document
02_A-K_A0003_20090608.doc DOC document
00_OCX RFP A0003_20090608.pdf PDF
09 Atch 02_Compliance_Reference Document_A0003_20090607.doc DOC document
01_A-K_A0003_20090608.pdf PDF
15_Atch_07_GFP_A0002_20090528.doc DOC document
03 Section L_A0002_20090601.doc DOC document
07 Exhibit A CDRL List_A0002_20090529.doc DOC document
A0002_20090602.pdf PDF
09 Atch 02_Compliance_Reference Document_A0002_20090528.doc DOC document
06 Exhibit A CDRL List_A0002_20090529.pdf PDF
08_Atch_01_GSOW_A0002_20090528.doc DOC document
A-K Conformed_A0001_20090519.doc DOC document
21_Atch_13_System_Modifications_(29_Apr_09).doc DOC document
16_Atch_08_Data_Rights_A0001_20090519.doc DOC document
16_Atch_08_Data_Rights_A0001_20090519.doc DOC document
OCX RFP A0001 —
21_Atch_13_System_Modifications_(29_Apr_09).doc DOC document
03_Section_L_A0001_20090519.doc DOC document
08_Atch_01_GSOW_A0001_20090519.doc DOC document
A-K_A0001_20090519.pdf PDF
01 Section A-K —
17_Atch_09_Small_Business_(29_Apr_09).doc DOC document
10_Atch_03_CWBS_Dictionary_(29_Apr_09).docx DOCX document
06 Exhibit A CDRL List —
14_Atch_06_DD254_(29_Apr_09).doc DOC document
19_Atch_11_Special_Studies_(29_Apr_09).doc DOC document
11_Atch_04_IMP_(29_Apr_09).doc DOC document
22_Atch_14_Capability_Insertion_Program_(29_Apr_09).doc DOC document
13 Atch 06_DD 254 —
08_Atch_01_GSOW_(29_Apr_09).docx DOCX document
12_Atch_05_Award_Fee_Plan_(29_Apr_09).doc DOC document
18_Atch_10_OCI_(29_Apr_09).doc DOC document
15_Atch_07_GFP_(29_Apr_09).doc DOC document
03_Section_L_(29_Apr_09).doc DOC document
04_Section_L_Annex_(29_Apr_09).doc DOC document
16_Atch_08_Data_Rights_(29_Apr_09).docx DOCX document
09_Atch_02_Compliance_Reference_Document_(29_Apr_09).doc DOC document
07_Exhibit_A_CDRL_List_(29_Apr_09).docx DOCX document
05_Section_M_(29_Apr_09).doc DOC document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 15: PERFORMANCE AND SCHEDULE INCENTIVE PLAN

GPS Advanced Control Segment (OCX)

Attachment 15: Performance and Schedule Incentive Plan for

FA8807-09-R-0003

29 April 2009

[This page intentionally blank]

PERFORMANCE AND SCHEDULE INCENTIVE PLAN

For

GPS Advanced Control Segment (OCX)

Contractor Name TBD

Contract Number TBD

COORDINATED:

JANET W. GRONDIN, Lt Col, USAF

DATE

Commander, GPAS

APPROVED:

DAVID M. MADDEN, Col, USAF

Commander, GPSW

JOY M. WHITE, SES, DAF

Director of Contracting, SMC

[This page intentionally blank]

1. Introduction

a. This incentive plan is one part of a three part incentive program for this GPS Advanced Control System (OCX) contract. The incentive covered by this plan is a performance and schedule incentive and represents approximately one-third of the OCX fee pool. The other incentives include award fee and the incentive fee associated with the Cost-Plus Incentive Fee (CPIF) contract type. Each incentive stands alone and has its own governing provisions. Award fee will be paid according to the terms in contract Attachment 5, “Award Fee Plan”. The CPIF incentive fee will be paid according to FAR 52.216-10, “Incentive Fee”. Award Fee and the CPIF incentive fee are not discussed in or governed by this plan.

b. The Performance and Schedule Incentive is the basis for the Global Positioning Systems Wing’s (GPSW) evaluation of the Contractor’s performance against annually established objective milestones and of the timely delivery of OCX Block 2.0. There are two principal goals of this plan. The first is to motivate optimum Contractor performance and to emphasize mission success. The second is to motivate on-time delivery of OCX Block 2.0 to the operational community to ensure support to GPS IIIA.

c. Performance incentives shall only be earned under the conditions defined in this plan and shall only be retained in their entirety based upon the Government’s acceptance (DD250) of CLIN 0200, “OCX Block 2.0 Development” no later than 60 calendar days after the delivery date for CLIN 0200 in Section F of the contract.

2. Evaluation Areas and Criteria

a. Performance Incentive Periods and Pool. The performance incentive emphasizes Contractor effort on R&D development CLINs 0100, 0200, 0300, 0350, 0600, and 0710. The periods and associated available incentive pool are shown in Table 1, “Performance Incentive Periods and Amounts”. The amount earned for each period will be added by the Government at the end of each period.

Table 1 Performance Incentive Periods and Amounts

Period
Dates of Period
Available Performance Incentive Pool
Earned Performance Incentive
1
Contract award –

15 Aug 10

*
**
2
16 Aug 10 – 15 Aug 11
*
**
3
16 Aug 11 – 15 Aug 12
*
**
4
16 Aug 12 – 30 Sep 13
*
**

Total

*
**

* To be inserted by the Government after receipt of proposals.

** To be inserted by the Government after final determination of milestone completion.

b. Performance Milestones. Prior the beginning of each performance incentive period, the Government will unilaterally select approximately four performance incentive milestones and the amount of the performance incentive fee pool allocated to each milestone based on importance to mission success, program progress, technical difficulty, or effort required. These milestones and the amounts of the annual performance incentive pool allocated to each will be listed in Annex 1, Table 1-1, “Performance Incentive Milestones by Period”. The amount earned for each milestone will be added to the table by the Government at the end of each period. The amounts earned will also be listed in Table 1. Notional completion dates are for reference only and are not part of the success criteria.

c. Milestone Completion. To earn the performance incentive for each milestone, the Contractor must successfully accomplish the milestone event during the evaluation period (See Table 1) in accordance with the established detailed exit criteria defined in Annex 1, Table 1-2 “Milestone Exit Criteria” for each milestone. Partial success will result in no performance incentive earned for a milestone. Failure to successfully complete a milestone event during the period will result in loss of the associated performance incentive amount. There shall be no rollover of lost incentive amounts. Table 1-2 will be updated prior to the beginning of each performance incentive period in accordance with the procedure in Section 2.e below.

d. Government Evaluation and Payment. The Contractor shall notify the PCO by letter upon completion of each milestone event. The OCX Program Manager will evaluate the completion of each milestone using the criteria in Table 1-2. If the OCX Program Manager determines that the milestone has been accomplished, he/she will recommend approval of the milestone to the GPSW Commander. If the GPSW Commander makes the final determination that the Contractor successfully completed the milestone, he/she will direct the PCO to notify the Contractor and to issue a contract modification, within 30 days of the determination, adjusting the value of the contract and obligating 100% of the amount of performance incentive earned for that milestone in accordance with Table 1-1.

e. Updates to This Plan. During the last quarter of a performance incentive period, the PCO shall request the Contractor provide recommendations to the OCX Program Manager for the next period’s milestones, weighting, and detailed evaluation criteria. The Program Manager shall consider the Contractor’s input but shall not be bound by it. The Program Manager shall recommend the milestone events, weightings, and associated exit criteria to the GPSW Commander who will make the final decision and direct the PCO to issue a unilateral modification updating this plan to incorporate the decision. The Commander may also direct other changes to this plan which the PCO may incorporate unilaterally prior to the beginning of the performance incentive period.

3. Schedule Incentive

a. Background. The second main objective of this Performance and Schedule Incentive Plan is to emphasize the need to deploy OCX Block 2.0 as quickly as possible to support warfighter and civil needs for new signals. This part of the incentive plan focuses on that objective.

b. Amounts at Risk. The total of all Performance Incentives earned under this plan is shown in the “Total” cell for “Earned Performance Incentive” of Table 1. This total amount is at risk under the schedule incentive portion of this plan.

c. Requirement. The parties agree that the amount shown in the “Total” cell for “Earned Performance Incentive” of Table 1 represents the estimated value to the Government of having OCX Block 2.0 delivered no later than 60 calendar days after the delivery date for CLIN 0200 in Section F of the contract. As stated in Section 3.b above, this amount is at risk of having to be repaid to the Government if the final acceptance of Block 2.0 occurs more than 60 calendar days after the delivery date in Section F. The delivery date for CLIN 0200 is specified in Section F of the contract. If the Government has signed the DD250 for CLIN 0200 any time on or before 60 calendar days after the delivery date in Section F, the Contractor shall retain all performance incentives earned on this contract. However, if the Government signs the DD250 for CLIN 0200 more than 60 days after the Section F delivery date, the Contractor shall remit to the Government 10% of all earned incentive each 30-day period that the DD250 remains unsigned until either Block 2.0 is delivered or the Contractor has remitted to the Government all performance incentives earned under this Attachment, whichever occurs first. The requirement to return 10% of the earned incentive is effective on the first day of the 30-day period regardless of how many days into that period CLIN 0200 is ultimately delivered. See Annex 2 for sample calculations.

Annex 1 Performance Incentive Evaluation Criteria 1-1 Performance Incentive Milestones

In accordance with Section 2.e of this plan, the GPSW Commander will identify performance incentive milestones and their weightings for each performance incentive period prior to the beginning of that period. The PCO will incorporate this information into Table 1-1 prior to the beginning of each performance incentive period. The sum of the weightings for each period must add up to 100%.

Table 1-1 Performance Incentive Milestones by Period

Period
No.
Title of Milestone or Product
Notional Completion

Date Period

Milestone

Weighting

Incentive Amount Allocated
Incentive Amount Earned
1
1
Block 1.0 & 2.0 IBR Complete
Apr 2010
30%
$*
$**
1
2
Block 1.0 & 2.0 SSR Complete
Jan 2010
30%
$*
$**
1
2
Block 1.0 & 2.0 PDR Complete
Jun 2010
40%
$*
$**

Period 1 Total

100%
$*
$**

* To be inserted by the Government after receipt of proposals.

** To be inserted by the Government after final determination of milestone completion.

1-2 Milestone Exit Criteria

Table 1-2 below defines the exit criteria for each performance incentive milestone identified in Table 1-1 above. Table 1-2 will be updated prior to the beginning of each performance incentive period in accordance with the procedure in Section 2.e of this plan.

Table 1-2 Milestone Exit Criteria by Period

Exit Criteria
Period 1, Milestone 1

Title: Staffing Ramp-Up Complete

Purpose: *

Exit Criteria: *

Exit Criteria
Period 1, Milestone 2

Title: Block 1.0 & 2.0 Preliminary Design Review Complete

Exit Criteria: *

Exit Criteria
Period 1, Milestone 3

Title: Block 1.0 Critical Design Review Complete

Exit Criteria: *

Exit Criteria
Period 1, Milestone 4

Title: To be completed by Offeror

Exit Criteria: *

* To be completed by the Offeror Annex 2 Sample Calculations

2-1 Sample Performance Incentive Calculations

In this sample calculation, assume the Contractor completes Block 1.0 and 2.0 IBR on April 5, 2010 and Block 1.0 and 2.0 SSR on May 10, 2010 but does not complete Block 1.0 and 2.0 PDR until 12 September 2010.

Period
Dates of Period
Available Performance Incentive Pool
Earned Performance Incentive
1
Contract award –

15 Aug 10

$4,000,000
$2,400,000
Period
No.
Title of Milestone or Product
Notional Completion

Date Period

Milestone

Weighting

Incentive Amount Allocated
Incentive Amount Earned
1
1
Block 1.0 & 2.0 IBR Complete
Apr 2010
30%
$1,200,000
$1,200,000
1
2
Block 1.0 & 2.0 SSR Complete
Jan 2010
30%
$1,200,000
$1,200,000
1
2
Block 1.0 & 2.0 PDR Complete
Jun 2010
40%
$1,600,000
$0

Period 1 Total

100%
$4,000,000
$2,400,000

2-2 Sample Schedule Incentive Calculations

In this sample calculation, assume the delivery date for CLIN 0200 in Section F is 31 July 2013. The Contractor has earned performance incentive as follows:

Period
Dates of Period
Available Performance Incentive Pool
Earned Performance Incentive
1
Contract award –

15 Aug 10

$6,250,000
$6,250,000
2
16 Aug 10 – 15 Aug 11
$6,250,000
$5,000,000
3
16 Aug 11 – 15 Aug 12
$6,250,000
$4,000,000
4
16 Aug 12 – 30 Sep 13
$6,250,000
$2,000,000

Total

$25,000,000
$17,250,000

The Schedule Incentive will be calculated as follows:

Date CLIN 0200 Delivered
Percent of Performance Incentive Returned
Final Performance and Schedule Incentive
Prior to 29 Sep 2013
0%
$17,250,000
30 Sep 2013 – 29 Oct 2013
10%
$15,525,000
30 Oct 2013 – 28 Nov 2013
20%
$13,800,000
29 Nov 2013 – 28 Dec 2013
30%
$12,075,000
29 Dec 2013 – 27 Jan 2014
40%
$10,350,000
28 Jan 2014 – 26 Feb 2014
50%
$8,625,000
27 Feb 2014 – 28 Mar 2014
60%
$6,900,000
29 Mar 2014 – 27 Apr 2014
70%
$5,175,000
28 Apr 2014 – 27 May 2014
80%
$3,450,000
28 May 2014 – 26 Jun 2014
90%
$1,725,000
27 Jun 2014 – 25 Aug 2014
100%
$0

· If the Contractor delivers Block 2.0 on 27 September 2013, it will retain all of its earned performance incentive ($17,250,000).

· If the Contractor delivers Block 2.0 on 31 December 2013, it will lose 40% of its previously earned performance incentive ($6,900,000) and will retain $10,350,000.