RFI__Responses_1-6.docx

DOCX document 14 KB Posted

Attached to
BASEWIDE ROOFING WRIGHT PATTERSON AFB Federal contract opportunity
Solicitation number
FA8601-18-B-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

RFI Responses 1-6

View the file

Other files for this federal contract opportunity

Other files attached to BASEWIDE ROOFING WRIGHT PATTERSON AFB, newest first.
File Type Posted
171102_Specification_Revision_3.pdf PDF
Site_visit_rules_and_attendance_sheet.pdf PDF
FA8601-18-B-0001_Amendment_4.pdf PDF
FA8601-18-B-0001_Amendment_3.pdf PDF
Addendum_01.pdf PDF
FA860118B0001_Amendment_02.pdf PDF
FA8601-18-B-0001_Amendment_1.pdf PDF
Bid_schedule_attachment.xlsx XLSX spreadsheet
Specifications.pdf PDF
General_Decision_Number_0H180114__OH180102.pdf PDF
Fa8601-18-B-0001.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Responses (Gov Answers bolded)

RFI #1

Please see the following section that has always been part of the base wide IDIQ. Was this missed in the documents?

These requirements are included in the contract via Specification Section 01 01 00 Summary (WPAFB) as revised by Amendments 01 & 02.

RFI #2

Will the AFICA contract limit award amounts for the IDIQ contract?

Yes, the AFICA Mandatory use policy is fully inforce, and there is no longer an exception for the WPAFB IDIQ contract no longer exists.

RFI #3

We need clarification on all line items. Is this copper material? What size on all Arrestors? Are they in main Electrical Panels or Sub Panels?

Refer to the following specification sections. With incorporation of Amendments 01 & 02, this detail is provided.

· 01 35 13 Statement of work for pricelist 1.0 THRU 17.0 (Amdt 01&02)

· 267 41 00 Lightning Protection System (original) RFI #4 0011AU and 0011AV- Replace existing 3” to 6” CI storm system with new PVC pipe and fittings. Is this only for aboveground storm or could it be for underground and within buildings?

Refer to Specification Section 01 35 13 STATEMENT OF WORK FOR PRICELIST 1.0 THRU 17.0. With incorporation of Amendments 01 & 02, this detail is provided.

RFI #5 0011AK and 0011AL- new 3” to 6” roof drain liner. Please provide more information. Is this a retrofit drain, or is this epoxy lining of bowl and pipe. If so, how many lineal feet?

Refer to Specification Section 01 35 13 STATEMENT OF WORK FOR PRICELIST 1.0 THRU 17.0. With incorporation of Amendments 01 & 02, this detail is provided.

RFI #6 0005CH and 0011AX- insulate interior roof drain bowl and pipe. Item is duplicated, what is the approximate lineal feet of piping to estimate?

Refer to Specification Section 01 35 13 STATEMENT OF WORK FOR PRICELIST 1.0 THRU 17.0. With incorporation of Amendments 01 & 02, this detail is provided.