Questions and Responses 1.docx

DOCX document 13 KB Posted

Attached to
F16 Tail Paint Stands Federal contract opportunity
Solicitation number
FA822421R0007
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This document contains a questions and responses file and a federal contract opportunity solicitation for the fabrication of F-16 Tail Paint Stands. The Air Force is seeking proposals to fabricate twelve F-16 Tail Paint Stands in accordance with provided Drawing X202023571 to be used at Hill Air Force Base. A prototype stand must be delivered within five months of award, with five additional stands due twelve months after prototype acceptance and the final six stands due twenty-four months from prototype acceptance. Delivery will be FOB Destination to Hill Air Force Base, Utah. The solicitation is being issued by the Department of the Air Force Materiel Command Air Force Sustainment Center.

View the file

Other files for this federal contract opportunity

Other files attached to F16 Tail Paint Stands, newest first.
File Type Posted
Questions and Responses 4.docx DOCX document
Questions and Responses 3.docx DOCX document
Questions and Responses 2.docx DOCX document
SOW F16 Paint Stand 29 Jan.docx DOCX document
Solicitation - FA822421R0007.pdf PDF
Addendums 52.212-1 and 52.212-2.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-16 PAINT TAIL STAND

QUESTIONS AND RESPONSES 1

Question:

From the drawing file provided and also mentioned in the SOW is this a ‘build to print’ request OR can the supplier offer some design changes?

Response:

The design is fixed and should be bid on as is.

It seems this is a variable height platform – what are the heights it goes from? Lowest to highest?

The height travel is approximately equal to the travel of the Jackscrews, item 305, sheet 3, which is 24.0 inches. The lowest platform height is on sheet 1, zone C8, 9’-3.9”. These platforms also rotate into position.

Will you be using ProjNet for this solicitation?

No