FA8201-15-R-0007 Building 830 Demolition RFP
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question_2.docx | DOCX document | |
| Bldg._830_Q_and_A.docx | DOCX document | |
| Amendment_0004.pdf | ||
| 01_57_20_Environmental_Protection.docx | DOCX document | |
| 01_00_00_General_Requirements.docx | DOCX document | |
| 01_35_26_Government_Safety_Requirements.docx | DOCX document | |
| 01_32_00_Project_Schedule.docx | DOCX document | |
| Bldg._830_Q_and_A.docx | DOCX document | |
| SOW-Building_830_29_Apr_15.pdf | ||
| Site_Grading.pdf | ||
| FA820115R000700003.pdf | ||
| Site_Restoration.pdf | ||
| STATEMENT_OF_WORK-Building_830.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| SITE_WALK_ROSTER.pdf | ||
| Bldg_830_Solicitation.zip | ZIP file |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This project w ill be a Small Business Set-Aside under NAICS 238910. Request for Proposals (RFP) Point of Contact (POC) is Capt Adam Rearick / Contract Specialist (801) 775-5194, adam.rearick@us.af.mil or Chris Thomas / Contracting Officer (801) 777-4453, christopher.thomas.87@us.af.mil.
In accordance w ith FAR 36.204 project magnitude is betw een $1,000,000 and $5,000,000.
A site visit is scheduled for 20 April 2015, 10:00 AM MST. If you w ill be attending the site visit, e-mail your information (name of attendees and company, drivers license number and state) to Adam Rearick at the e-mail listed above NLT 15 April 2015, 10:00 AM MST.
Contractor questions w ill not be accepted after 24 April 2015 4:00 PM MST. Questions w il be answ ered by 30 April 2015 4:00 PM MST.
Notice to Offeror (s) / Supplier (s): Funds are not presently available for this effort. No aw ard w ill be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date for reciept of proposals. In the even the Government cancels this soliciation, the Government has no obligation to reimburse an offeror for any costs.
ADAM REARICK 801-586-9165
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
08-Apr-2015
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________08 May 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______160 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
OL:H/PZIO
PZIOA ADAM REARICK
6038 ASPEN AVE B1289NE
HILL AFB UT 84056-5805
FA8201
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 801-586-9165 TEL: FAX:
FA8201-15-R-0007 37
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA8201-15-R-0007
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot Bldg 830 Asbestos/Lead Paint Abatement
FFP
Perform asbestos and lead abatement removal and disposal, to include all PCB light ballasts and bulbs and air monitoring for all asbesots and lead abatement. This will all be done in accordance with the attached requirements in Section J List of Documents, Exhibits, and Other Attachments.
FOB: Destination
NET AMT
FSC CD: P400
0002 1 Lot Bldg 830 Demolition
FFP
Demolish and dispose of wood building 830 off base. Demolish and dispose of all concrete slab, foundations, footings, loading docks and ramps off base. Demolish and dispose of asphalt pavings off base. Cap and terminate all utilities (water, sewer, electric, gas, communication, storm drain and steam) at main. Removal of all and disposal of all all laterals. This will all be done in accordance with the attached requirements in Section J List of Documents, Exhibits, and Other Attachments.
0003 1 Lot Bldg 830 Site Restoration
FFP
Spread all backfill to grade and dispose remaining access fill off base. Restore site, reseed all disturbed areas of demolition. This will all be done in accordance with the attached requirements in Section J List of Documents, Exhibits, and Other Attachments
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination N/A Destination Government 0002 Destination N/A Destination Government 0003 Destination N/A Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 180 dys. ADC 1 75 CE
MARLONO LAUGHTER
5713 LAHM LANE BLDG 593 S
HILL AFB UT 84056-5410
801-777-1647
F2D0AC
0002 180 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0003 180 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
Section G - Contract Administration Data
CLAUSES INCORPORATED BY FULL TEXT
CONTRACT HOLIDAYS (APR 2003)
(a) The prices/costs in Section B of the contract include holiday observances; accordingly, the Government will not be billed for such holidays, except when services are required by the Government and are actually performed on a holiday. Holidays in addition to those reflected in this contract, which are designated by the Government, will be billable provided the assigned Contractor employee was available for performance and was precluded from such performance.
(b) The following days are contract holidays:
New Years Day Martin Luther King Jr. Day Presidents’ Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
Section I - Contract Clauses
52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7 System for Award Management JUL 2013 52.204-8 Annual Representations and Certifications DEC 2014 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract
Awards
JUL 2013
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
AUG 2013
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
AUG 2013
52.211-10 Commencement, Prosecution, and Completion of Work APR 1984 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2004 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications
AUG 2011
52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.216-24 Limitation Of Government Liability APR 1984 52.216-25 Contract Definitization OCT 2010 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns OCT 2014 52.219-14 Limitations On Subcontracting NOV 2011 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities FEB 1999 52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction
FEB 1999
52.222-26 Equal Opportunity MAR 2007 52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity for Veterans JUL 2014 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans JUL 2014 52.222-38 Compliance With Veterans' Employment Reporting
Requirements
SEP 2010
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons FEB 2009 52.222-50 Combating Trafficking in Persons FEB 2009 52.223-1 Biobased Product Certification MAY 2012 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-4 Recovered Material Certification MAY 2008 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-9 Estimate of Percentage of Recovered Material Content for
EPA-Designated Items
MAY 2008
52.223-10 Waste Reduction Program MAY 2011 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-9 Buy American--Construction Materials MAY 2014 52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments APR 2012 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts MAY 2014 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014
52.233-2 Service Of Protest SEP 2006 52.233-3 Protest After Award AUG 1996 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.236-28 Preparation of Proposals--Construction OCT 1997 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items OCT 2014 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2010 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.252-2 Clauses Incorporated By Reference FEB 1998 52.252-6 Authorized Deviations In Clauses APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7000 Requirements Relating to Compensation of Former DoD Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7998 (Dev) Prohibition on Contracting with Entities that Require Certain
Internal Confidentiality Agreements—Representation.
(DEVIATION 2015-O0010)
FEB 2015
252.203-7999 (Dev) Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements. (DEVIATION 2015- O0010)
FEB 2015
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7006 Billing Instructions OCT 2005
252.204-7012 Safeguarding of Unclassified Controlled Technical Information
NOV 2013
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
DEC 2014
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities FEB 2013 252.225-7031 Secondary Arab Boycott Of Israel JUN 2005 252.227-7033 Rights in Shop Drawings APR 1966 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7001 Contract Drawings, and Specifications AUG 2000 252.236-7006 Cost Limitation JAN 1997 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.247-7023 Transportation of Supplies by Sea APR 2014
52.202-1 DEFINITIONS (NOV 2013)
When a solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulation (FAR), the word or term has the same meaning as the definition in FAR 2.101 in effect at the time the solicitation was issued, unless--
(a) The solicitation, or amended solicitation, provides a different definition;
(b) The contracting parties agree to a different definition;
(c) The part, subpart, or section of the FAR where the provision or clause is prescribed provides a different meaning;
or
(d) The word or term is defined in FAR Part 31, for use in the cost principles and procedures.
(End of clause)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the performance period indicated in the statement of work * The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $272.07 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $272.07 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
252.204-7012 SAFEGUARDING OF UNCLASSIFIED CONTROLLED TECHNICAL INFORMATION (NOV
2013)
(a) Definitions. As used in this clause--
Adequate security means protective measures that are commensurate with the consequences and probability of loss, misuse, or unauthorized access to, or modification of information.
Attribution information means information that identifies the Contractor, whether directly or indirectly, by the grouping of information that can be traced back to the Contractor (e.g., program description or facility locations).
Compromise means disclosure of information to unauthorized persons, or a violation of the security policy of a system, in which unauthorized intentional or unintentional disclosure, modification, destruction, or loss of an object, or the copying of information to unauthorized media may have occurred.
Contractor information system means an information system belonging to, or operated by or for, the Contractor.
Controlled technical information means technical information with military or space application that is subject to controls on the access, use, reproduction, modification, performance, display, release, disclosure, or dissemination.
Controlled technical information is to be marked with one of the distribution statements B-through-F, in accordance with DoD Instruction 5230.24, Distribution Statements on Technical Documents. The term does not include information that is lawfully publicly available without restrictions.
Cyber incident means actions taken through the use of computer networks that result in an actual or potentially adverse effect on an information system and/or the information residing therein.
Exfiltration means any unauthorized release of data from within an information system. This includes copying the data through covert network channels or the copying of data to unauthorized media.
Media means physical devices or writing surfaces including, but is not limited to, magnetic tapes, optical disks, magnetic disks, large-scale integration memory chips, and printouts onto which information is recorded, stored, or printed within an information system.
Technical information means technical data or computer software, as those terms are defined in the clause at DFARS 252.227-7013, Rights in Technical Data--Non Commercial Items, regardless of whether or not the clause is incorporated in this solicitation or contract. Examples of technical information include research and engineering data, engineering drawings, and associated lists, specifications, standards, process sheets, manuals, technical reports, technical orders, catalog-item identifications, data sets, studies and analyses and related information, and computer software executable code and source code.
(b) Safeguarding requirements and procedures for unclassified controlled technical information. The Contractor shall provide adequate security to safeguard unclassified controlled technical information from compromise. To provide adequate security, the Contractor shall—
(1) Implement information systems security in its project, enterprise, or company-wide unclassified information technology system(s) that may have unclassified controlled technical information resident on or transiting through them. The information systems security program shall implement, at a minimum—
(i) The specified National Institute of Standards and Technology (NIST) Special Publication (SP) 800-53 security controls identified in the following table; or
(ii) If a NIST control is not implemented, the Contractor shall submit to the Contracting Officer a written explanation of how—
(A) The required security control identified in the following table is not applicable; or
(B) An alternative control or protective measure is used to achieve equivalent protection.
(2) Apply other information systems security requirements when the Contractor reasonably determines that information systems security measures, in addition to those identified in paragraph (b)(1) of this clause, may be required to provide adequate security in a dynamic environment based on an assessed risk or vulnerability.
Table 1--Minimum Security Controls for Safeguarding
Minimum required security controls for unclassified controlled technical information requiring safeguarding in accordance with paragraph (d) of this clause. (A description of the security controls is in the NIST SP 800-53, ``Security and Privacy Controls for Federal Information Systems and Organizations'' (http://csrc.nist.gov/publications/PubsSPs.html).)
Access Control
AC-2
AC-3(4)
AC-4
AC-6
AC-7
Audit & Accountability
AU-2
AU-3
AU-6(1)
AU-7
Identification and Authentication
IA-2
IA-4
IA-5(1)
Media Protection
MP-4
MP-6
System & Comm Protection
SC-2
SC-4
SC-7
SC-8(1) Physical and http://csrc.nist.gov/publications/PubsSPs.html)
AC-11(1)
AC-17(2)
AC-18(1)
AC-19
AC-20(1)
AC-20(2)
AC-22
AU-8
AU-9
Environmental Protection
PE-2
PE-3
PE-5
SC-13
SC-15
SC-28
Incident Response
IR-2
IR-4
IR-5
IR-6
Configuration Management
CM-2
CM-6
CM-7
CM-8
Program Management
PM-10
System & Information Integrity
SI-2
SI-3
SI-4
Maintenance
MA-4(6)
MA-5
MA-6
Risk Assessment
RA-5
Awareness & Training
AT-2
Contingency Planning
CP-9
Legend:
AC: Access Control AT: Awareness and Training MP:
AU: Auditing and Accountability CM: Configuration Management CP: Contingency Planning IA: Identification and Authentication IR: Incident Response MA: Maintenance MP: Media Protection PE: Physical & Environmental Protection PM: Program Management RA: Risk Assessment SC: System & Communications Protection SI: System & Information Integrity
(c) Other requirements. This clause does not relieve the Contractor of the requirements specified by applicable statutes or other Federal and DoD safeguarding requirements for Controlled Unclassified Information as established by Executive Order 13556, as well as regulations and guidance established pursuant thereto.
(d) Cyber incident and compromise reporting.
(1) Reporting requirement. The Contractor shall report as much of the following information as can be obtained to the Department of Defense via (http://dibnet.dod.mil/) within 72 hours of discovery of any cyber incident, as described in paragraph (d)(2) of this clause, that affects unclassified controlled technical information resident on or transiting through the Contractor's unclassified information systems:
(i) Data Universal Numbering System (DUNS).
(ii) Contract numbers affected unless all contracts by the company are affected.
(iii) Facility CAGE code if the location of the event is different than the prime Contractor location.
http://dibnet.dod.mil/
(iv) Point of contact if different than the POC recorded in the System for Award Management (address, position, telephone, email).
(v) Contracting Officer point of contact (address, position, telephone, email).
(vi) Contract clearance level.
(vii) Name of subcontractor and CAGE code if this was an incident on a subcontractor network.
(viii) DoD programs, platforms or systems involved.
(ix) Location(s) of compromise.
(x) Date incident discovered.
(xi) Type of compromise (e.g., unauthorized access, inadvertent release, other).
(xii) Description of technical information compromised.
(xiii) Any additional information relevant to the information compromise.
(2) Reportable cyber incidents. Reportable cyber incidents include the following:
(i) A cyber incident involving possible exfiltration, manipulation, or other loss or compromise of any unclassified controlled technical information resident on or transiting through Contractor's, or its subcontractors', unclassified information systems.
(ii) Any other activities not included in paragraph (d)(2)(i) of this clause that allow unauthorized access to the Contractor's unclassified information system on which unclassified controlled technical information is resident on or transiting.
(3) Other reporting requirements. This reporting in no way abrogates the Contractor's responsibility for additional safeguarding and cyber incident reporting requirements pertaining to its unclassified information systems under other clauses that may apply to its contract, or as a result of other U.S. Government legislative and regulatory requirements that may apply (e.g., as cited in paragraph (c) of this clause).
(4) Contractor actions to support DoD damage assessment. In response to the reported cyber incident, the Contractor shall—
(i) Conduct further review of its unclassified network for evidence of compromise resulting from a cyber incident to include, but is not limited to, identifying compromised computers, servers, specific data and users accounts. This includes analyzing information systems that were part of the compromise, as well as other information systems on the network that were accessed as a result of the compromise;
(ii) Review the data accessed during the cyber incident to identify specific unclassified controlled technical information associated with DoD programs, systems or contracts, including military programs, systems and technology; and
(iii) Preserve and protect images of known affected information systems and all relevant monitoring/packet capture data for at least 90 days from the cyber incident to allow DoD to request information or decline interest.
(5) DoD damage assessment activities. If DoD elects to conduct a damage assessment, the Contracting Officer will request that the Contractor point of contact identified in the incident report at (d)(1) of this clause provide all of the damage assessment information gathered in accordance with paragraph (d)(4) of this clause. The Contractor shall comply with damage assessment information requests. The requirement to share files and images exists unless there are legal restrictions that limit a company's ability to share digital media. The Contractor shall inform the Contracting Officer of the source, nature, and prescription of such limitations and the authority responsible.
(e) Protection of reported information. Except to the extent that such information is lawfully publicly available without restrictions, the Government will protect information reported or otherwise provided to DoD under this clause in accordance with applicable statutes, regulations, and policies. The Contractor shall identify and mark attribution information reported or otherwise provided to the DoD. The Government may use information, including attribution information and disclose it only to authorized persons for purposes and activities consistent with this clause.
(f) Nothing in this clause limits the Government's ability to conduct law enforcement or counterintelligence activities, or other lawful activities in the interest of homeland security and national security. The results of the activities described in this clause may be used to support an investigation and prosecution of any person or entity, including those attempting to infiltrate or compromise information on a contractor information system in violation of any statute.
(g) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (g), in all subcontracts, including subcontracts for commercial items.
252.225-7048 EXPORT-CONTROLLED ITEMS (JUNE 2013)
(a) Definition. ``Export-controlled items,'' as used in this clause, means items subject to the Export Administration Regulations (EAR) (15 CFR Parts 730-774) or the International Traffic in Arms Regulations (ITAR) (22 CFR Parts 120-130). The term includes--
(1) ``Defense items,'' defined in the Arms Export Control Act, 22 U.S.C. 2778(j)(4)(A), as defense articles, defense services, and related technical data, and further defined in the ITAR, 22 CFR Part 120; and
(2) ``Items,'' defined in the EAR as ``commodities'', ``software'', and ``technology,'' terms that are also defined in the
EAR, 15 CFR 772.1.
(b) The Contractor shall comply with all applicable laws and regulations regarding export-controlled items, including, but not limited to, the requirement for contractors to register with the Department of State in accordance with the ITAR. The Contractor shall consult with the Department of State regarding any questions relating to compliance with the ITAR and shall consult with the Department of Commerce regarding any questions relating to compliance with the EAR.
(c) The Contractor's responsibility to comply with all applicable laws and regulations regarding export-controlled items exists independent of, and is not established or limited by, the information provided by this clause.
(d) Nothing in the terms of this contract adds, changes, supersedes, or waives any of the requirements of applicable Federal laws, Executive orders, and regulations, including but not limited to—
(1) The Export Administration Act of 1979, as amended (50 U.S.C. App. 2401, et seq.);
(2) The Arms Export Control Act (22 U.S.C. 2751, et seq.);
(3) The International Emergency Economic Powers Act (50 U.S.C. 1701, et seq.);
(4) The Export Administration Regulations (15 CFR Parts 730-774);
(5) The International Traffic in Arms Regulations (22 CFR Parts 120-130); and
(6) Executive Order 13222, as extended.
(e) The Contractor shall include the substance of this clause, including this paragraph (e), in all subcontracts.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow
(WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Construction
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
Government
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC FA8201 Admin DoDAAC FA8201 Inspect By DoDAAC F2D0AA Ship To Code F2D0AA Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) F2D0AA Service Acceptor (DoDAAC) F2D0AA Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
Christopher.thomas.87@us.af.mil or adam.rearick@us.af.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
N/A
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
5352.201-9101 OMBUDSMAN (APR 2014)
mailto:Christopher.thomas.87@us.af.mil mailto:adam.rearick@us.af.mil
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, [Mr Kevin Flinders AFMC OL_H/PZC 801-777-6549, kevin.flinders@us.af.mil. Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/HQ AFICA/AFISRA/SMC ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330- 1060, phone number (571) 256-2395, facsimile number (571) 256-2431. (INTERIM CHANGE: See Policy Memo 14-C-05)
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.
5352.223-9000 ELIMINATION OF USE OF CLASS I OZONE DEPLETING SUBSTANCES (ODSs) (NOV 2012)
(a) Contractors shall not:
(1) Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or
(2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.
[Note: This prohibition does not apply to manufacturing.]
(b) For the purposes of Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32-7086) are Class I ODSs:
(1) Halons: 1011, 1202, 1211, 1301, and 2402;
(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and
(3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.
[NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Air Force defi-nition of a Class I ODS.]
5352.242-9000 CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (Nov 2012)
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with AFI 31-101, Integrated Defense, and AFI 31-501, Personnel Security Program Management] citing the appropriate paragraphs as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
5352.242-9000 CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (Nov 2012)
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with AFI 31-101, Integrated Defense, and AFI 31-501, Personnel Security Program Management] citing the appropriate paragraphs as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
PROGRESS SCHEDULES AND REPORTS
The reports contemplated in the clause FAR 52.236-15, Schedules for Construction Contracts, shall be accomplished and in accordance with the instructions for locally generated Contract Progress Schedule, and Contract Progress Report forms
Section J - List of Documents, Exhibits and Other Attachments
LIST OF ATTACHMENTS
LIST OF ATTACHMENTS
NAME
01 00 00 GENERAL REQUIREMENTS 21
01 32 00 PROJECT SCHEDULE 05
01 35 26 GOVERNMENT SAFETY REQUIREMENTS 23
01 57 20 ENVIRONMENTAL PROTECTION 19
02 41 00 DEMOLITION AND DECONSTRUCTION 16
Spec BASE FACILITY DESIGN STANDARD 80 Spec C&D Diversion Report Form 01
3.0 HAFB CONSTRUCTION SITE STORMWATER 05
MGT SOPs FINAL
SOW STATEMENT OF WORK-830 24
----- Schedule of Drawings 13 PDF MEMO Restoration of Grasses 02 ---- Asbestos Sample Reports 02 Excel Sheets ---- Wage Determination UT104 05 ---- Total Evaluated Price Worksheet
Section K - Representations, Certifications and Other Statements of Offerors
52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2015)
Substitute the following paragraphs (d) and (e) for paragraph (d) of the provision at FAR 52.204-8:
(d)(1) The following representations or certifications in the System for Award Management (SAM) database are applicable to this solicitation as indicated:
(i) 252.209-7003, Reserve Officer Training Corps and Military Recruiting on Campus--Representation. Applies to all solicitations with institutions of higher education.
(ii) 252.216-7008, Economic Price Adjustment--Wage Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government controls wage rates or material prices and may during contract performance impose a mandatory change in wages or prices of materials.
(iii) 252.222-7007, Representation Regarding Combating Trafficking in Persons, as prescribed in 222.1771. Applies to solicitations with a value expected to exceed the simplified acquisition threshold.
(iv) 252.225-7042, Authorization to Perform. Applies to all solicitations when performance will be wholly or in part in a foreign country.
(v) 252.225-7049, Prohibition on Acquisition of Commercial Satellite Services from Certain Foreign Entities-- Representations. Applies to solicitations for the acquisition of commercial satellite services.
(vi) 252.225-7050, Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism. Applies to all solicitations expected to result in contracts of $150,000 or more.
(vii) 252.229-7012, Tax Exemptions (Italy)--Representation. Applies to solicitations when contract performance will be in Italy.
(viii) 252.229-7013, Tax Exemptions (Spain)--Representation. Applies to solicitations when contract performance will be in Spain.
(ix) 252.247-7022, Representation of Extent of Transportation by Sea. Applies to all solicitations except those for direct purchase of ocean transportation services or those with an anticipated value at or below the simplified acquisition threshold.
(2) The following representations or certifications in SAM are applicable to this solicitation as indicated by the Contracting Officer: [Contracting Officer check as appropriate.]
____ (i) 252.209-7002, Disclosure of Ownership or Control by a Foreign Government.
____ (ii) 252.225-7000, Buy American--Balance of Payments Program Certificate.
____ (iii) 252.225-7020, Trade Agreements Certificate.
____ Use with Alternate I.
____ (iv) 252.225-7031, Secondary Arab Boycott of Israel.
____ (v) 252.225-7035, Buy American--Free Trade Agreements--Balance of Payments Program Certificate.
____ Use with Alternate I.
____ Use with Alternate II.
____ Use with Alternate…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .