Appendix_1_DF-16_Library_Motorized_Solar_Shades.pdf

PDF 530 KB Posted

Attached to
Motorized Solar Shades Federal contract opportunity
Solicitation number
FA7000-16-T-0067
Issued by
Department of the Air Force Headquarters Air Force Academy

About this file

Atch 2 Appendix 1 Library Motorized Shades

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HQ U.S. Air Force Academy

I n t e g r i t y - S e r v i c e - E x c e l l e n c e

McDermott Library

Motorized Solar

Shades Building 2354

1 April 2016

Robin Witek, Base Interior Designer

10 CES/CECE

Banks of windows with existing drapery

North and south elevation of 6 banks of windows that are treated with drapery.

All existing drapery will be required to be removed and disposed.

Each bay (12 total; 6 per elevation) will be required to include 2 shades that are each 13 ft x 300 inch shades

69 inches between mullions

82 inches between mullions

82 inches between mullions

69 inches between mullions

Outer mount shades—2--13 ft wide x

300 inches long per bank ( 1 end bay =

69 + middle bay = 82 + half of mullion width of 2 inches)

Existing switches for drapery

Existing switches operate the existing drapery horizontally. The electrical infrastructure can be used for the operation of the solar shades; however, the new shades are required to include programable pre-determined stops to open shades vertically.

Existing Solar Shades on East Elevation

Existing shades on east side of building; a fascia is included at top

Left: Existing switches on 3rd floor which are located on a window mullion to control the shades

File details come from the government source that posted it. Updated .