08-5001_NAF-APF_Addendum_02_Rev0.pdf
PDF 19 KB Posted
- Attached to
- Amendment 2-FA7000-15-R-0009 Federal contract opportunity
- Solicitation number
- FA7000-15-R-0009
About this file
Addendum 02dated 29 Jun 15
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 2 NAF Project: XQPZ 08-5001 ‘Const New Golf Course Clubhouse’
APF Project: XQPZ 08-5001B ‘APF Infrastructure for NAF Major Construction’
08-5001 naf-apf addendum 02 rev0.docx
Revision 0: Original, 29 Jun 2015
Project Manager: Jeff Young, RA/LEED AP
10 CES/CENMP
8120 Edgerton Drive USAF Academy, CO 80840 Phone: Office: (719) 333-2241 / Mobile: (719) 896-6785
Construction Project Manager: Jeth Fogg, P.E.
10 CES/CECE
8120 Edgerton Drive USAF Academy, CO 80840 Phone: Office: (719) 333-8397
A. With regards to Appropriated Funds (APF) Project 2 XQPZ08-5001B APF
INFRASTRUCTURE SUPPORT FOR MAJOR NAF CONSTRUCTION:
a) Referring to SPECIFICATIONS 100% Submittal Golf Clubhouse APF Project, Construct Utilities to Site of New Clubhouse, USAFA Project Number XQPZ 08- 5001B:
REGARDING DIVISION 01
a. Remove specification section 00 01 15
b. Remove specification section text 01 11 00, 1.3 SUBMITTALS, SD-01:
“Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, “Government Furnished Property,” of this section.”
c. Remove specification section 01 11 00, PART 1 GENERAL, 1.4 WORK
COVERED BY CONTRACT DOCUMENTS.
d. Remove specification section 01 11 00, PART 1 GENERAL, 1.5 CONTRACT
DRAWINGS.
e. Remove specification section 01 11 00, PART 1 GENERAL, 1.6 WORK
RESCHEDULING.
f. Remove specification section 01 11 00, PART 1 GENERAL, 1.7 PROJECT
ENVIRONMENTAL GOALS.
g. Remove specification section 01 11 00, PART 1 GENERAL, 1.8
OCCUPANCY OF PREMISES.
h. Remove specification section 01 22 00.00 10, PART 1 GENERAL, 1.2.2 Removal of Hazardous Materials.
i. Remove specification section 01 22 00.00 10, PART 1 GENERAL, 1.3.1 Hazardous Materials Overages.
j. Remove specification section 01 30 00, PART 1 GENERAL, 1.1
SUBMITTALS, 1.2 VIEW LOCATION MAP, 1.3 PROGRESS AND
COMPLETION PICTURES, 1.5 CONTRACTOR SPECIAL REQUIREMENTS,
1.6 SUPERVISION, 1.7 SUPERVISION, 1.9 FACILITY TURNOVER
PLANNING MEETINGS (NAVFAC Red Zone – NRZ) and 1.10
PARTNERING.
k. Remove specification section 01 32 01.00 10, PART 1 GENERAL, 1.1
REFERENCES, 1.2 SUBMITTALS.
l. Remove multiple sub-sections within section 01 32 01.00 10, PART 3 GENERAL, 3.1.3 through 3.11.
Addendum No. 2 NAF Project: XQPZ 08-5001 ‘Const New Golf Course Clubhouse’
APF Project: XQPZ 08-5001B ‘APF Infrastructure for NAF Major Construction’
08-5001 naf-apf addendum 02 rev0.docx
m. Remove specification section 01 32 16.00 20, PART 1 GENERAL, CONSTRUCTION PROGRESS DOCUMENTATION, 1.1 SUBMITTALS and
1.3 SCHEDULE FLOAT and 1.16 PROGRESS SCHEDULE.
n. Remove specification section 01 33 00 SUBMITTAL PROCEDURES.
o. Remove specification section 01 35 40.00 20 ENVIRONMENTAL
MANAGEMENT.
p. Remove specification section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
q. Remove specification section 01 57 23 TEMPORARY STORM WATER
POLLUTION CONTROL.
r. Remove specification section 01 74 19 CONSTRUCTION WASTE
MANAGENMENT AND DISPOSAL.
REGARDING DIVISION 02
s. Remove DIVISION 02.
B. With regards to Non-Appropriated Funds (NAF) Project 1 XQPZ08-5001 USAFA
GOLF COURSE CLUBHOUSE:
a) Referring to Specification Section 23 09 00, PART 2 – PRODUCTS, 2.2 CONTROL SYSTEM add a paragraph D. which states the following:
“Provide two emergency shutoff switches (one (1) per floor) in the HVAC control system that can immediately shut down the air distribution and exhaust systems throughout the building and close all dampers leading to the outside. Each switch must be capable of shutting down all required systems and closing all required dampers, even if the local hand/off/auto switch is in the hand position, within 30 seconds of switch activation. Locate the Upper Level shutoff switch in Circulation 102 near door 102. Locate Lower Level switch in Circulation 001 near door 017-2 such that the travel distance to the nearest shutoff switch not be in excess of 200 feet. Ensure that the shutoff switches activate a light at the switch and is well labeled with a sign of a different color than fire alarm pull stations that states ”GOLF
STAFF ONLY – EMERGENGY AIR DISTRIBUTION SHUT-OFF SWITCH”.
END OF ADDENDUM 02