Questions-Responses_2.doc
DOC document 27 KB Posted
- Attached to
- Repair Aircraft Parking Apron Federal contract opportunity
- Solicitation number
- FA6633-16-B0002
About this file
Q A 2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Drawings_Sheets_7-11-12.pdf | ||
| Amendment_0001.docx | DOCX document | |
| Questions-Responses_APRIL_2016.doc | DOC document | |
| Site_Visit_Minutes_14Apr16.pdf | ||
| Questions-Responses_APRIL_2016.doc | DOC document | |
| SV_Attendance_Roster_14Apr16.pdf | ||
| Wage_Determination_MN96.doc | DOC document | |
| Financial_Responsibility_Sheet.doc | DOC document | |
| Drawings_24pgs.pdf | ||
| SF_24_Bid_Bond_Form.pdf | ||
| FA6633-16-B0002 _Solicitation.docx | DOCX document | |
| Technical_Specifications_132_pgs.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Responses #2 (20 April 2016)
FA6633-16-B0002 / QJKL 15-0025
Repair Aircraft Parking Apron
1. QUESTION: Is the intention with the 120 performance period to just be for Phase 1, and an additional 30 days to complete Phase 2?
1) RESPONSE: The 120 day performance period is the total number of days on the project, 90 days for the work to be done near bldg. 870, and 30 days for the work at bldg. 821.
2. QUESTION: Is the intention to begin Phase 2 as soon as the contractor finishes up with Phase 1? Or is there expected to be a delay between the two Phases?
2) RESPONSE: For bidding purposes, plan on being able to begin Phase 2 as soon as Phase 1 is completed without a delay.
20 April 2016