Questions-Responses_2.doc

DOC document 27 KB Posted

Attached to
Repair Aircraft Parking Apron Federal contract opportunity
Solicitation number
FA6633-16-B0002
Issued by
Department of the Air Force Reserve Command

About this file

Q A 2

View the file

Other files for this federal contract opportunity

Other files attached to Repair Aircraft Parking Apron, newest first.
File Type Posted
Revised_Drawings_Sheets_7-11-12.pdf PDF
Amendment_0001.docx DOCX document
Questions-Responses_APRIL_2016.doc DOC document
Site_Visit_Minutes_14Apr16.pdf PDF
Questions-Responses_APRIL_2016.doc DOC document
SV_Attendance_Roster_14Apr16.pdf PDF
Wage_Determination_MN96.doc DOC document
Financial_Responsibility_Sheet.doc DOC document
Drawings_24pgs.pdf PDF
SF_24_Bid_Bond_Form.pdf PDF
FA6633-16-B0002 _Solicitation.docx DOCX document
Technical_Specifications_132_pgs.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Responses #2 (20 April 2016)

FA6633-16-B0002 / QJKL 15-0025

Repair Aircraft Parking Apron

1. QUESTION: Is the intention with the 120 performance period to just be for Phase 1, and an additional 30 days to complete Phase 2?

1) RESPONSE: The 120 day performance period is the total number of days on the project, 90 days for the work to be done near bldg. 870, and 30 days for the work at bldg. 821.

2. QUESTION: Is the intention to begin Phase 2 as soon as the contractor finishes up with Phase 1? Or is there expected to be a delay between the two Phases?

2) RESPONSE: For bidding purposes, plan on being able to begin Phase 2 as soon as Phase 1 is completed without a delay.

20 April 2016