ADDENDUM 1 TO THE TECHNICAL SPECIFICATIONS

View the file

Other files

File Type Posted
FA5682-15-T-0011-0001.pdf PDF
ASHJ_15_1062_CNS_Cost_Est_blank.xls XLS spreadsheet
ASHJ_15_1062_SOW_REV1.pdf PDF
FA5682-15-T-0011.pdf PDF
ASHJ_15-1062_SUBMITTALS_R.pdf PDF
ADDITIONAL_REQUIREMENTS_(under_150K).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # ASHJ 15-1062 Technical Specifications R1

DATE: SEPT 2015 ADDENDUM#1

31CES/CENM

PROJECT ASHJ 15-1062

SUSTAIN HVAC SYSTEM BLDG 600

AREA E, AVIANO AIR BASE, ITALY

ADDENDUM#1______________________________________________________________________

Part 14. MECHANICAL WORKS.

Sub- item 14.b includes also:

- The secondary piping connection between existing fancoil steel pipe and new plastic pipes must have a stainless steel elastic pipe 40 cm long ( 2ea per fancoil, as used for solar panels) to absorb main plastic line movements .