ASHJ_15_1062_CNS_Cost_Est_blank.xls

XLS spreadsheet 101 KB Posted

Attached to
ASHJ SUSTAIN HVAC SYSTEM BLDG 600 AREA E AVIANO AB
Solicitation number
FA5682-15-T-0011
Issued by

About this file

ASHJ 15-1062 CONSTRUCTION COST ESTIMATE BREAKDOWN

View the file

Other files

File Type Posted
FA5682-15-T-0011-0001.pdf PDF
ASHJ_15_1062_SOW_ADD_1_r.pdf PDF
ASHJ_15_1062_SOW_REV1.pdf PDF
FA5682-15-T-0011.pdf PDF
ASHJ_15-1062_SUBMITTALS_R.pdf PDF
ADDITIONAL_REQUIREMENTS_(under_150K).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASHJ 15-1062

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
SUSTAIN HVAC SYSTEM BLDG 600
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
ASHJ 15-1062AREA E, AVIANO AB, ITALY
MATERIAL PLUS LABOR COSTSLABOR COSTS
LINE ITEM NO.ITEM (1)UNIT OF MEASURE (2)QUANTITY (3)UNIT (4)TOTAL (5)MANHOUR MANDAYS (6)AVERAGE RATE (7)TOTAL (8)OTHER DIRECT COSTS (9)LINE TOTAL (10)
1DESIGN FEESitems2 to 12L.S.
CIVIL WORKS
2SUSPENDED CEILING REMOVALitem13aSQ.MT
3VACUUM CLEANING ABOVE SUSPENDE CEILINGitem13bL.S.
4NEW SUSPENDED CEILINGitem13cSQ.MT
5GENERAL CLEANINGitem13dL.S.0.00
MECHANICAL WORKS
6REMOVAL PIPELINESitem14aL.S.
7NEW PLASTIC PIPELINEitem14bL.S.
8NEW FLANGED BALL VALVESitem14cEA
ELECTRICAL WORKS
9REMOVAL EXISTING LIGHT FIXTUREitem15aL.S.
10REMOVE/RE-INSTALL FIRE ALARM COMPONENTSitem15bL.S.
11MODIFY WIRINGitem15cL.S.
12NEW FLUORESCENT LIGHT FIXTURESitem15dL.S.

TOTAL € - 0