FA5575-19-R-A003
RPR MSA Igloos
Questions and Answers
1) According to the Solicitation document, Sub Factor – Past Experience, the offeror has to include with the proposal the following documents:
-3 to 5 example projects demonstrating design-build Project experience.
-3 to 5 example projects demonstrating the experience and capability of the A/E firm.
-3 to 5 example projects demonstrating the experience and capability of the Construction firm .
If a Project meets those three (3) requirements above, we would like to clarify if this project can be included to cover each of sections above (design-build, A/E firm experience, and Construction experience). I mean, the same Project would be included three (3) times once for each experience requirements.
Government response: The Contractor shall submit in total three to six example projects but, as a minimum, one of each type, as to say, one design-build, one A&E design and one construction project. These three projects shall belong to different contracts. Sections L and M of the solicitation have been amended to reflect this requirement.