QUESTIONS_AND_ANSWERS_FOR_ATFP_PROJECTS.pdf

PDF 11 KB Posted

Attached to
ATFP RPL Perimeter Fence Federal contract opportunity
Solicitation number
FA5575-18-R-0003
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

All contractor submitted questions and government provided answers

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS FOR ATFP PROJECTS

FA5575-18-R-0005 - ATFP Install Vehicle Denial Cable, MSA

FA5575-18-R-0004 - ATFP SUS Airfield Perimeter Ditch

FA5575-18-R-0003 - ATFP RPL Perimeter Fence

1) Can you confirm all three projects will be awarded under separate contracts (possibly to different firms)?

Answer: Yes, all ATFP projects will be awarded under separate contracts and possibly to different firms.

2) Shall contactors assume that all three projects will be awarded and executed concurrently?

Answer: Yes, the Notice to Proceed dates may differ, but that’s based on submittals, contractors getting access to the base, etc..

3) Can you specify what government review time shall be assumed for each of the submittals?

Answer: Materials submittals review time period is 3 – 5 business days, that’s our Civil Engineerings normal turn around. Any other submittals will have the same turn around time.