SPECIFICATIONS

View the file

Other files for this federal contract opportunity

Other files attached to Gym Water Seepage, newest first.
File Type Posted
Amendment_2.pdf PDF
Requirement_Clarifications.pdf PDF
Amendment_1.pdf PDF
QUUG_13-1012_SCHEDULE_OF_MATERIAL_SUBMITTALS_SP-EN.xlsx XLSX spreadsheet
QUUG_13-1012_SPECIFICATIONS_100_(es).pdf PDF
QUUG_13-1012_DRAWINGS_100_.pdf PDF
FA5575-17-B-0004.pdf PDF
13-1012_Construction_Cost_Estimate_Breakdown_Ktor.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED FOR DEPARTMENT OF THE

AIR FORCE

BY

GISA, S.L.

(GABINETE DE INGENIERÍA Y SISTEMAS ANDALUZ, S.L.)

TECHNICAL PROVISIONS & SPECIFICATIONS FOR:

PROJECT QUUG 13-1012

RPR Gym Water Seepage Through Exterior

100% DESIGN SUBMITTAL

Repair Gymnasium Water Seepage Through Exterior.

Prepared by: ___________________________________________________________________ Name: Gonzalo Tejedor Panchón, Engineer (DOR) Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: José Manuel Rodríguez Márquez, Engineer (DOR) Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Juan José Tejedor Hernández, Architect (DOR) Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Sagrario Sánchez Martínez, Engineer (Chief Designer) Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Sandra Pérez Mateos, Technical Architect Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Belén Sanz Macias, Building Engineer Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Alvaro Racero Caputto, Specifications specialist Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Lorena Sanz Macias, Draftsman Date: 15 Feb 17

Prepared by: ___________________________________________________________________ Name: Javier Gomez Ortega, Draftsman Date: 15 Feb 17

PAGE INTENTIONALLY LEFT BLANK

PROJECT QUUG 13-1012

LIST OF SPECIFICATIONS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS

01 11 01 GENERAL CONDITIONS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

DIVISION 03 - CONCRETE

03 45 00 PRECAST ARCHITECTURAL CONCRETE

DIVISION 04 - MASONRY

04 20 00 MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 20 00 FINISH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 53 ELASTOMERIC SHEET WATERPROOFING

07 21 16 MINERAL FIBER INSULATION

07 42 13 METAL WALL PANELS

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 51 13 ALUMINUM WINDOWS

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 90 00 PAINTS AND COATINGS

DIVISION 21 – FIRE SUPRESSION

21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 53 00.00 40 EXIT SIGNS

26 56 00 EXTERIOR LIGHTING

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 74.00 20 INTERIOR FIRE DETECTION AND ALARM SYSTEM

DIVISION 31 - EARTHWORK

31 23 00 00 20 EXCAVATION AND FILLING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 16 13 CONCRETE SIDEWALKS AND CURBS

01 11 00 - 1

SECTION 01 11 00

SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS

1. SCOPE OF WORK: The project consists of:

1.1 Architectural Work:

1.1.1 Demolition and Disassembly Work:

a. Disassemble and move the gym machines to the determinated location.

b. Install protection on the floor of the gym made of one continuous polyethylene layer + MDF panels of 40mm of thickness.

moreover, protect the elements located in not affected walls (east and west) and located under the ceiling, in order to conserve their conditions and not to be damaged. Keep them during the construction.

c. Remove elements located in affected walls (north and south), with care of not to be damaged to be reused.

d. Demolish, when it corresponds, the indicated fixtures with care, avoiding any damage to building elements.

e. Carry out the work corresponding to building foundation.

f. Build new walls and installations

g. Carry out the works corresponding to the exterior and building finishes.

h. Install new elements and elements were removed to be reused.

i. Remove protections installed during the construction. gym floor protection, elements located in not affected walls (east and west) and located under the ceiling.

j. Clean the gym and accommodate the equipment in the initial location

k. Final cleaning of the total intervention area.

1.1.2 Foundation Work:

a. Provide material and construct foundation for new North and South walls.

1.1.3 Steel Work:

a. Clean surfaces of steel columns and all structural elements existing into North and South walls. Also shall be cleaned the bolted joints between steel columns and trusses.

b. Preparation works of metal surfaces. D Sa2½ level of preparation

01 11 00 - 2 by abrasive blasting before the passivation.

c. Once the sandblasting treatment has been applied to the steel elements, a loss of section test will be developed to determinate if the condition of the steel elements is acceptable. If it is required, the damage elements shall be replaced or reinforced.

d. Provide and install steel secondary structure to support the isolated metal panels and new windows.

e. Provide and apply primer and final enamel coating to the structure elements (structural elements affected by the project).

Color as indicated.

f. Provide and apply R90 fire protection coating.

g. The screws of the bolted joints between trusses and steel columns shall be fully and properly tightened.

h. Provide and install isolated metal panels.

1.1.4 Masonry Work:

a. Provide material and construct new North and South walls.

1.1.5 Phenolic paneling:

a. Provide and install phenolic panels.

1.1.6 Thermal and Moisture Protection:

a. Provide material and seal the roof construction joints.

b. Provide material and apply waterproof treatment coats.

c. Fix gutters, seal gutter joints.

g. Provide material and install plumbing pipe insulation.

1.1.7 Doors and windows:

a. Clean doors repair/restore hardware, frames and trims and reinstall.

b. Install new motorized windows in North and South walls.

1.1.8 Finishes:

a. Provide material and repair wall cracks from interior and exterior in East and West walls.

b. Provide material and apply paint to interior and exterior walls.

1.1.9 Civil:

a. Provide material and construct new sidewalks.

1.1.10 Landscaping:

a. Provide material and construct new sidewalks.

01 11 00 - 3

b. Restore the topsoil and seeding the areas affected by the construction.

1.1.11 Gymnasium restoration:

a. Contractor shall remove gymnasium equipment installed in basketball court and reinstall it in determined location.

1.2 Mechanical Work:

1.2.1 Demolition Plumbing & Sewer Work:

a. Demolish exterior drainpipes and gutters (north and south walls).

b. Demolish plumbing installations affected by the project as indicated. A proper temporary cap will be installed in the disconnection points.

1.2.2 Disassembly HVAC Work:

a. Disassembly air ductwork which runs along the north wall and the south wall for subsequent reinstallation and the corresponding supports and accessories. The interior ductwork shall be cleaned to be reinstalled. Existing supports shall be cleaned and painted to be reused and reinstalled too.

1.2.3 Construction Plumbing & Sewer Work:

a. Provide and install new drainpipes and gutters.

b. Provide and install new plumbing system for north and south walls.

c. Provide and install temporary potable water supply for basketball court (shelter).

d. Perform potable water piping disinfection treatment (complete piping installation).

e. Perform water test for fecal coliforms, e-coli, pH and residual chlorine.

1.2.4 Construction HVAC Work:

a. Reinstall air ductwork which runs along the north wall and the south wall. Existing supports shall be cleaned and painted and reinstalled.

b. Start up, tests and adjustments of all the systems (existing and installed).

1.2.5 Construction Fire Suppression System Work:

a. Perform temporary modifications during the construction process to the Fire Department Connection point and fire suppression

01 11 00 - 4 sprinkler alarm as indicated. Once finished the construction process shall be restored the original conditions.

1.3 Electrical Work:

1.3.1 Electrical Demolition Work:

a. Partial demolition of interior electrical distribution system.

b. Demolition of complete exterior lighting system.

c. Partial demolition of fire alarm system. The removed appliances shall be temporary disconnected from the fire panel to avoid false alarms.

d. Partial demolition of communications system.

e. Partial demolition of CCTV & Access Control system.

1.3.2 Construction Electrical Work:

a. Provide material and perform modifications to the interior electrical distribution system.

b. Provide and install new exterior lighting.

c. Provide material and perform modifications to the fire alarm system.

d. Provide material and perform modifications to the CCTV &

Access Control system.

e. Provide and install LED EXIT signs and emergency lighting.

f. Provide and install electrical actuators and remote control stations for motorized windows.

g. Provide material and install new grounding system.

1.4 Final cleaning.

1.5 Delivery of As-Built drawings.

1.6 Delivery of Spatial data.

2. PERFORMANCE PERIOD: The performance period proposed for the execution of this project is 203 calendar days, and includes average inclement weather days.

2.1 It shall be the sole responsibility of the Contractor to ensure all required submittals are submitted to the Contracting Office for approval in a timely manner which shall not incur any delay in completion of the project. Materials or equipment requiring long lead time for procurement and delivery shall be included in the period of performance. Delay in delivery/procurement will not justify an extension of the period of performance.

2.2 Contractor shall submit a Construction Schedule and Work Plan.

2.2.1 The Construction Schedule shall include a Gantt chart showing each task, including its description, identification number, duration in calendar days, earliest

01 11 00 - 5 start and finish dates and the predecessor activity identification number, the critical path and the float that a task in the project network can be delayed without causing a delay to the subsequent task (free float) and to the project completion date (total float). The critical path shall be shown in red color and the float by means of black line after the predecessor task bar. The Construction Schedule shall show the whole week, from Monday through Sunday. The labor days shall be from Monday through Friday. Saturday and Sunday shall be non-labor days. The holidays shall not be considered on the Construction Schedule and, therefore, they shall be considered labor days for Construction Schedule development purpose only. The working hours for the labor days shall be 8 hours.

2.2.2 The Work Plan shall present the sequence of preconstruction and construction activities which are planned to take place. The Work Plan shall be prepared in coordination with the Safety Plan and the Quality Control Plan and shall contain the following:

a. The summary of the proposed methodology for the execution of each task required for the project completion.

b. The resources to be used for the execution of each task required for the project completion describing the equipment and personnel to be used.

c. Daily production for each task required for the project completion.

3. DRAWINGS:

No. of Drawing Sheet Date Title R-724-01 01 of 55 15 Feb 17 Cover Sheet R-724-02 02 of 55 15 Feb 17 Drawing Schedule R-724-03 03 of 55 15 Feb 17 Existing Condition I. Topographic Survey (I) R-724-04 04 of 55 15 Feb 17 Existing Condition II. Topographic Survey (II) R-724-05 05 of 55 15 Feb 17 Existing Condition III. Existing installations R-724-06 06 of 55 15 Feb 17 Site Work Plan R-724-07 07 of 55 15 Feb 17 Exterior Finishes Plan R-724-08 08 of 55 15 Feb 17 Foundation Plan R-724-09 09 of 55 15 Feb 17 Foundation details R-724-10 10 of 55 15 Feb 17 Work phases R-724-11 11 of 55 15 Feb 17 Plan. Existing Conditions and Demolitions R-724-12 12 of 55 15 Feb 17 Elevations. Existing Conditions and Demolitions R-724-13 13 of 55 15 Feb 17 Sections. Existing Conditions and Demolitions R-724-14 14 of 55 15 Feb 17 New Finishes Plan R-724-15 15 of 55 15 Feb 17 New Elevations R-724-16 16 of 55 15 Feb 17 New Sections R-724-17 17 of 55 15 Feb 17 Details I. Architecture I.

R-724-18 18 of 55 15 Feb 17 Details II. Architecture II.

R-724-19 19 of 55 15 Feb 17 Details III. Architecture III.

R-724-20 20 of 55 15 Feb 17 Details IV. Phenolic Panels I.

R-724-21 21 of 55 15 Feb 17 Details V. Phenolic Panels II.

R-724-22 22 of 55 15 Feb 17 Details VI. Prefabricated concrete panels.

01 11 00 - 6

R-724-23 23 of 55 15 Feb 17 Details VII. Secondary structure.

R-724-24 24 of 55 15 Feb 17 Details VIII. Secondary structure. Joints I.

R-724-25 25 of 55 15 Feb 17 Details IX. Secondary structure. Joints II.

R-724-26 26 of 55 15 Feb 17 Details X. Secondary structure. Joints III.

R-724-27 27 of 55 15 Feb 17 Details XI. Windows I.

R-724-28 28 of 55 15 Feb 17 Details XII. Windows II.

R-724-29 29 of 55 15 Feb 17 Sewer installation. Existing condition and demolition.

R-724-30 30 of 55 15 Feb 17 Sewer installation. Existing condition and demolition. Elev.

R-724-31 31 of 55 15 Feb 17 New plan of sewer installation.

R-724-32 32 of 55 15 Feb 17 New sewer installation. Elevations.

R-724-33 33 of 55 15 Feb 17 Plumbing installation. Existing condition and demolition.

R-724-34 34 of 55 15 Feb 17 Plumbing installation. Existing condition and demolition. Elev.

R-724-35 35 of 55 15 Feb 17 New plan of plumbing installation.

R-724-36 36 of 55 15 Feb 17 New plumbing installation. Elevations.

R-724-37 37 of 55 15 Feb 17 Plumbing installation details.

R-724-38 38 of 55 15 Feb 17 Fire protection installation. Existing condition and demolition.

R-724-39 39 of 55 15 Feb 17 New plan of fire protection installation.

R-724-40 40 of 55 15 Feb 17 Fire protection installation details I.

R-724-41 41 of 55 15 Feb 17 Fire protection installation details II.

R-724-42 42 of 55 15 Feb 17 Existing air conditioning plan.

R-724-43 43 of 55 15 Feb 17 New air conditioning plan.

R-724-44 44 of 55 15 Feb 17 Electrical legend for existing condition.

R-724-45 45 of 55 15 Feb 17 Electrical Installation. Existing condition and demolition.

R-724-46 46 of 55 15 Feb 17 Elec. Inst. Existing condition and demolition.

Elevations.

R-724-47 47 of 55 15 Feb 17 Elec. Inst. Existing condition and demolition.

Sections.

R-724-48 48 of 55 15 Feb 17 Electrical legend for proposed new system.

R-724-49 49 of 55 15 Feb 17 New plan of electrical installation.

R-724-50 50 of 55 15 Feb 17 Grounding system.

R-724-51 51 of 55 15 Feb 17 New electrical Installation. Elevations.

R-724-52 52 of 55 15 Feb 17 New electrical Installation. Sections.

R-724-53 53 of 55 15 Feb 17 Electrical Installation. Details I.

R-724-54 54 of 55 15 Feb 17 Electrical Installation. Details II.

R-724-55 55 of 55 15 Feb 17 Electrical Installation. Details III.

4. GOVERNMENT-FURNISHED MATERIAL (GFM):

Not used.

5. EQUIPMENT, CONTROLS, AND MATERIAL OF THE UNITED STATES OF

AMERICA:

01 11 00 - 7

5.1 Equipment List: The following listed equipment, controls, and materials shall be manufactured in the United States of America or in another country where the supplier is under license of the United States of America manufacturer and the product meets the same applicable specifications and/or standards. No substitutions will be allowed.

a. Receptacles and plugs.

b. Fire alarm system appliances.

c. LED EXIT signs.

5.2 Excess: The Contractor shall furnish to the Contracting Officer, just prior to completion of this contract, a consolidated inventory of all excess supplies, materials, and equipment imported duty free for use under this contract. The Contractor shall either pay required duties on the excesses or re-export the excesses.

6. CERTIFICATION OF CLASSIFICATION: Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by the “Registro Oficial de Licitadores y Empresas Clasificadas del Estado”, covering the following groups, subgroups, and categories.

The certificate holder must execute the activities related to the certificate.

Group Subgroup Category C 1, 2, 3, 4, 6, 7 & 9 b J 2, 4 b K 9 b I 1, 6, 7 b

7. SPECIAL REQUIREMENTS: The following special conditions apply:

7.1 During demolition/construction phases, the rest of the areas of the building shall remain in operation continuing their normal activities, so the Contractor shall proceed in such a manner so as to interfere as least as possible with normal operations.

7.2 The demolition/construction of utility service lines, electric, water and sanitation common to the rest of the building shall be accomplished so as not to affect the other areas in operation or reduce to a minimum any interruption. In the case that any of the utility lines must be interrupted, this shall be authorized by the Contracting Officer.

7.3 Domestic cold/hot water, cooling/heating and electricity shut off schedule: The Contractor shall submit a detailed plan of the domestic cold/hot water and cooling/heating, electricity shut off schedule required for the execution of this project. Said schedule shall be submitted for approval 15 calendar days prior to the commencement of work in each phase.

Schedule shall include the number and duration of suspension of service/building use events taking into account that these shall be kept to a minimum.

7.4 No heat/no cool season: The "no heat/no cool season" mentioned in section 01 11 00, paragraph 7.6 is defined as follows in accordance with USAFEI32-7040: No heat/no cool season: “Comfort cooling systems should not be in operation until the outside air temperatures exceed 75 degrees Fahrenheit (24 degrees Celsius) dry bulb or 68 degrees Fahrenheit (20

01 11 00 - 8 degrees Celsius) wet bulb for five consecutive days. In addition the heating season should not begin until the outside temp drops below 55 degrees Fahrenheit (13 degrees Celsius) for five consecutive days”. This period may vary but is usually established from 1 October to 15 November and from 1 Mar to 15 April. These dates are given as general guidance only.

7.5 Electrical power outages: If works under this contract require performing partial power outages in the facility, that shall be co-ordinated through Contracting Office as indicated in the General Conditions section of the specifications and herein.

*** END OF SECTION ***

01 11 01 - 1

SECTION 01 11 01

GENERAL CONDITIONS

1. GENERAL: The work consists of furnishing all labor, materials, plant, transportation, equipment, and services to complete the project described in Section 01 11 00, Scope of Work, Drawings and Special Conditions, in accordance with the drawings and specifications, complete and ready for use by means of a firm fixed price construction contract. Measurements given in the drawings and specifications are given for reference use only. It is the Contractor‟s responsibility to verify any and all of said measurements.

2. GENERAL DESCRIPTION: The work consists in, but is not limited to, executing the line items indicated in the scope of work. All line items indicated in the scope of work do not limit or reduce the Contractor‟s responsibility to perform all work as required by the project in order to provide a complete and operable facility.

3. LOCATION: The work is located in Morón Air Base, Spain, as shown on the contract drawings.

4. DRAWINGS ACCOMPANYING SPECIFICATION: The drawings accompanying this specification are a part thereof. Drawings are the property of the

Government, and shall not be used for any purpose other than that contemplated by the specification. The drawings included in this specification are similar to A1.

5. WARRANTY: For this contract the Contractor shall provide a two years standard commercial warranty associated with all scope of work items including materials and workmanship. The warranty should cover all defects noticed and reported to the Contractor within two years after acceptance of the project. The Contractor shall repair or replace defective materials at the Contractor's expense within a reasonable time, and as approved by the

Contracting Officer. The Contractor must comply with any additional warranty periods covered under Spanish codes and regulations. The Contractor shall submit the warranty prior to the Final

Inspection and acceptance of the work by the Contracting Officer.

6. BASE ACCESS:

6.1 Permits or Authorizations: The Contractor shall obtain all permits or authorizations to access Morón Air Base. Once the works have finalized, the Contractor will return the permits or authorizations. Contractor is responsible to provide escorts as required to complete the project.

6.2 Delays and Interruptions: Contractors are advised that due to security reasons, during the access/egress process of personnel and materials from the Morón Air Base delays are liable to occur. Additionally, the Contractor shall immediately interrupt work when required to do so if security warning/alarm situations occur.

7. WORK CLEARANCE REQUEST: 5 calendar days after the notice to proceed

(NTP) the Contractor shall request AF Form 103 “BCE Work Clearance Request” in order to

01 11 01 - 2 obtain all the information pertaining to the current status of general utilities. Additional requests shall be processed through the Contracting Officer or authorized representative, minimum of 15 duty days beforehand. The Contractor shall not perform any excavation works under any circumstances without an approved Work Clearance Request at the work site (hard copy). Work Clearance Request will only be processed once all materials and documentation necessary to commence work have been submitted and approved. The

Contractor shall be held responsible for any damage caused to general utilities indicated on the AF Form 103 and related drawings and shall be repaired at no additional cost to the

Government of the United States.

8. BASE UTILITIES:

8.1 Use of Base Utilities: Water, Sewage and electric Base utilities are available to the Contactor for connections to the following facilities: Offices, latrines, break rooms, and laboratories.

The following Utilities will be available from the existing Base utility systems. Any additional utilities requirement besides what is listed below shall be supplied by the contractor at no cost to the Government.

a. Electricity 120/208 volts, 60 Hz.

b. Non-potable water.

15 calendar days after the notice to proceed (NTP) the Contractor shall request the connection and shall indicate the type of utility service required, type of connection and disconnection, utility service use and maximum duration. All connection and disconnection works for Base utilities shall be programmed between 08:30 and 16:00 hours, Monday through Friday, holidays excepted. It shall be the Contractor‟s responsibility to effect the connections and disconnections and shall reimburse costs incurred in the connection, disconnection, conversion, transportation of Base utility services to the work site, including providing the mechanisms that avoid water from flowing back into the system (backflow preventers) and furnishing and installing the necessary transformers. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. Additional requests shall be processed through the Contracting Officer or authorized representative with a minimum of 5 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required. Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

8.2 Base Utility Outages: Whenever a utility outage is required, the Contractor shall request the utility outage and shall indicate the type of outage to be performed, the scope of work and the maximum duration. All utility outages shall be scheduled between 08:30 and

16:00 hours, Monday through Friday, holidays excepted. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. The Contractor shall notify the

Contracting Officer or authorized representative 10 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required.

Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

01 11 01 - 3

9. HOT WORK: The Contractor shall submit for approval a written request to the

Contracting Officer or authorized representative 10 calendar days prior to any welding, oxyacetylene or plasma cutting work. Said request shall indicate welding procedures and fire prevention measures. All welding work performed during the project shall be carried out by qualified welders only. The copies of the welding certificates, issued by an approved agency, shall be kept in the construction inspector‟s files.

10. VEHICULAR TRAFFIC, MACHINERY AND EQUIPMENT:

10.1 Traffic Control: All works which require vehicular or pedestrian traffic disruptions on the Base shall require an approved transit control plan. Said plan shall be approved at least 7 calendar days prior to carrying out said disruption. Said plan shall include the date, duration, proposed alternative routes, signs, barriers, cones and/or flagmen. The

Contractor shall establish alternate procedures should unforeseen circumstances take place.

The responsibility of furnishing, erecting, maintaining and removing all signs, barriers, cones and flags shall be solely the Contractor‟s. Once the work is completed, the Contractor shall remove the signaling elements such as barriers, cones and/or flags.

10.2 Access Routes: The Contractor shall submit a plan for the access routes which shall be approved by the Contracting Officer or authorized representative.

10.3 Trucks: Trucks loaded with loose material (air borne dust, construction debris or other objects that could fall from them), shall be duly covered. Said covers, such as tarps, shall be fastened over the load prior to accessing the adjacent roads.

11. PROGRESS SCHEDULE (AF Form 3064): (See solicitation/Contract FAR clause 52.236-15, Schedules for Construction Contracts, Apr 1984). The Contractor shall, 10 calendar days after the notice to proceed (NTP) or another period of time determined by the

Contracting Officer, prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the

Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

12. MOBILITY PLAN: The Contractor shall submit a mobility plan to the

Contracting Officer or authorized representative for approval. Said plan shall propose the location and surface of the work site, offices and material staging and storage areas. The

Contractor shall submit the plan 15 calendar days after the notice to proceed (NTP). The

Contractor shall include in the mobility plan the proposed system to supply the required utility services required at each site.

12.1 Construction Site Fencing: Construction sites, offices, latrines, material staging and storage areas shall be fenced in by means of a two meter high fence to include gates and locks, unless otherwise approved the Government of the United States. The type of fencing, height and color shall be specified in accordance with the Contracting Officer or authorized representative‟s criteria. Fences shall be screened with green opaque screening material to

01 11 01 - 4 prevent visibility inside the fenced area. Fencing shall be completely secured at top and bottom to prevent access. Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. The Contractor shall include in the

Mobilization Plan photos, catalogs or samples of the screening material. The Contractor shall not install the fencing or screening materials until approval, in writing, has been granted from the Contracting Officer or authorized representative. The responsibility of providing, erecting, maintaining and removing the fencing shall be solely the Contractor‟s. The

Contractor shall replace or repair, within the following 24 hours or as determined by the

Contracting Officer or authorized representative, all fence or screening sections which have been damaged or deteriorated. Once the works have been finalized, the Contractor shall remove the fencing.

12.2 Offices: Temporary prefabricated buildings required for administrative reasons

(office space, conference room and break room) shall be in good conditions. Temporary prefabricated buildings requiring paint, repairs or are in bad conditions shall not be allowed at the site. Said temporary prefabricated buildings shall include on the outside a plaque, 0.5 x

0.5 meters maximum dimensions, indicating the name of the company and telephone number

(s) of the person (s) designated as POC for the Contractor 24 hours a day. Once the works are finalized, the Contractor shall remove the temporary prefabricated buildings.

12.3 Latrines: Prefabricated temporary buildings required as latrines for personnel shall be in good conditions. The prefabricated temporary buildings requiring paint, repairs or are in bad conditions shall not be allowed on the work site. These facilities shall be kept in perfect using conditions and sanitized, shall be treated for insects and shall be emptied once a week and cleaned with a detergent suitable for sanitary use. The frequency of emptying and cleaning shall be adjusted according to needs. The facilities shall be located no less than 50 meters from the existing buildings on Base if they cannot be located near a sewage manhole.

Once the works have been completed, the Contractor shall remove the temporary facilities and shall leave the area clean and sanitized.

12.4 Parking: The Contractor, their employees and subcontractors shall park all vehicles, including heavy machinery, equipment or vehicles, in areas where they do not pose an obstruction in the corresponding work site. All possible efforts must be made so that the vehicles are not parked in an area where they will be clearly visible from the outside.

12.5 Material Storage: Storage containers will be in good conditions. The storage of materials at the work site shall be at the Contractor‟s own risk. The use of private security guards at the work site shall require Spanish Air Force Security Forces approval. The

Contractor shall not use the work site to store material previously approved by the

Contracting Officer or authorized representative. Once the works have finished, the

Contractor shall remove the excess stored material.

13 PROJECT SIGN: 15 calendar days after the notice to proceed (NTP) the

Contractor shall install an identifying project sign in accordance with Figure 1 no later than one day after the mobilization has been installed. The sign shall be mounted on two wooden posts 10 cm x 10 cm, fastened to the ground and adequately anchored. The location of said sign shall be determined by the Contracting Officer or his representative. During final cleanup of the work site, the sign, posts and anchoring elements shall be removed. Unless otherwise specified, the sign shall have a white background and the lettering shall be dark blue.

01 11 01 - 5

FIGURE 1 - : PROJECT SIGN

14. QUALITY CONTROL PLAN: 15 calendar days after the notice to proceed

(NTP) the Contractor shall submit a comprehensive Quality Control Plan. The plan shall contain at minimum the following:

1. Names and Qualifications for the proposed Quality Control Manager and

Inspectors.

2. Organization Chart. Include teaming partners/key subcontractors for pertinent trades required for specific project. The subcontractors/partners indicated shall be those that will be effectively participating in the project and shall be the same than those submitted in the contract bid, if they were required. Lack of this information, or variation with previously submitted organizations shall be cause for disapproval of the QC Plan, and the request to submit a new one before works can start/proceed.

3. Responsibility of the Quality Control Inspectors, Quality Control Manager and the Project Manager.

4. Inspection types to be performed. The Contractor shall fully develop a

Program Points Inspection (PPI) System covering all types of works involved in the project. Development of the PPI System shall be based in any and all of the following documentation:

a. Project drawings and specifications.

b. Applicable regulations, standards and industry codes.

c. Specific regulations to certain products, installations or facilities.

d. Manufacturer‟s recommendations.

Number and type of Inspection Points (IP) shall be determined as many as required to provide an acceptable level of inspection for achieving the best

01 11 01 - 6 quality results. Evaluation of whether or not the number and type of IPs are enough to achieve the expected level of quality shall be determined by the

Contracting Officer.

5. Inspection Procedures and actions to be taken for failed or unsatisfactory inspections.

6. Inspection Reporting forms. Submit all reporting forms for any type of inspection to be performed under this project. As a minimum, a specific form shall be developed for each technical provision of the specifications, covering all necessary inspection points for such work. Minimum information required for each IP shall be: description of the IP, applicable documents, frequency/type of inspection, responsible of the inspection performed and result, date of inspection, reference to non-compliance document/register if not in compliance, information about pass/rejection criteria for the IP, etc.

7. List of planned „Hold Inspection Points‟ with the estimated dates from the construction schedule.

8. Form “Schedule of Material Submittals” provided with this project with column titled “Required Submission Date” filled in by the Contractor with the dates provided by his Construction Schedule, in order to avoid delays in project completion because of pending non-approved submittals.

9. Request for Information (RFI): submit the Request for Information Form

(RFI) and RFI Log Form. This will be used to submit and track any RFI‟s during construction.

10. Material Testing: Submit the name and qualifications for any Testing

Agency or Laboratory planned for testing. All testing reports shall be submitted in a timely manner for review and approval. Related work may continue only after testing report has been approved. Should any test report fail, follow-on work is not to proceed until after the failure has been corrected. It is the responsibility of the QC Manager to ensure that all reports have been reviewed and the necessary action taken to resolve any failed testing.

11. A daily report of all actions performed during the contract period is required to be documented on a daily basis. The daily reports are to be kept on the job-site and available for review at all times. A copy of the daily reports shall be submitted weekly to the Contracting Officer. The following shall be included in the report, but is not all-inclusive.

a. The date of the inspection.

b. Comment on the weather conditions.

c. Inspection of equipment and materials and their delivery date at the job-site.

d. Names of visitors to the site during the day.

e. Inspection of any deficiencies discovered during the day and

1261440306A Comment on Text What is this?

01 11 01 - 7 corrective action taken.

f. Inspection and acceptance of subcontractor materials and workmanship.

g. Work being performed during the day, including the used labor personnel and equipment.

h. Any field change or modifications approved by the Contracting

Officer.

14.1 Acceptance of the Construction Quality Control (QC) Plan: Acceptance of the

QC Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work.

14.2 Maintenance of records is the responsibility of the contractor.

15 PRE-FINAL AND FINAL INSPECTIONS: Final inspection and acceptance will be conducted jointly with the inspector and a representative from the contracting office. The contractor shall request a pre-final inspection once the works are completed in accordance with the inspector's judgement. After the solving of all the discrepancies found during the pre-final inspection, if any, the contractor shall request a final inspection. All punch list items must be completed before final acceptance of the project.

16. WORK DAY:

16.1 Normal Work Hours: The Contractor shall perform all work during normal working hours unless a special authorization is issued by the Contracting Office representative to deviate from said work schedule. Normal working hours shall be from 0800 to 1700, from Monday to Friday, with the exception of holidays.

16.2 Work Outside Normal Hours: If the Contractor wishes to work outside the normal hours of operation, Saturdays, Sundays, or holidays, he shall submit an application to the Contracting Officer. The Contractor shall submit the request five (5) work days ahead of time as minimum.

17. CONSERVATION AND MAINTENANCE OF THE EXISTING FACILITIES:

The contractor shall conserve and protect all existing facilities at the work site or adjacent to it which shall not to be removed or affected by the work required under this contract. The

Contractor shall restore, at no additional cost to the Government of the United States of

America, the facility affected during the execution of works to its original condition, before final acceptance of the project.

18. ENVIRONMENTAL PROTECTION PLAN: 15 calendar days after the notice to proceed (NTP) the Contractor shall submit the Environmental Protection Plan. The program shall include, but not be limited to, the following:

Classified Activitiess:

- Decreto 2414/1961, reglamento de actividades molestas, insalubres, nocivas y peligrosas (RAMINP). BOE de 07/12/1961

01 11 01 - 8

- Orden del Ministerio de Gobernación de 15/03/1963, se aprueba una instrucción por la que se dictan normas complementarias para la aplicación del reglamento de actividades molestas, insalubres, nocivas y peligrosas. BOE N°.

79 de 02/04/1963

- Decreto 297/1995, reglamento de calificación ambiental. BOJA No. 3 de

11/01/1996

Water:

- Real Decreto 60/2011, normas de calidad ambiental en el ámbito de la política de aguas. BOE No. 19 of 22/01/1201

- Real Decreto 849/1986, de 11 de abril, por el que se aprueba el Reglamento del Dominio Público Hidráulico que desarrolla los títulos preliminar, I, IV, V, VI, VII y VIII del texto refundido de la Ley de Aguas, aprobado por el Real

Decreto Legislativo 1/2001, de 20 de julio. BOE No. 103 de 30/04/1986

- Real Decreto Legislativo 1/2001, de 20 de julio, por el que se aprueba el texto refundido de la Ley de Aguas. BOE No. 176 de 24/07/2001

- Orden del Ministerio de Medio Ambiente, Rural y Marino (ARM)/1312/2009, de 20 de mayo, por la que se regulan los sistemas para realizar el control efectivo de los volúmenes de agua utilizados por los aprovechamientos de agua del dominio público hidráulico, de los retornos al citado dominio público hidráulico y de los vertidos al mismo. BOE No. 128 de 27/05/2009

Atmosphere:

- Reglamento (CE) n°. 1497/2007 de la Comisión, por el que se establecen, de conformidad con el Reglamento (CE) no 842/2006 del Parlamento Europeo y del Consejo, requisitos de control de fugas estándar para los sistemas fijos de protección contra incendios que contengan determinados gases fluorados de efecto invernadero. Diario Oficial de la Unión Europea (DOUE) Nº. 333 de

19/12/2007

- Reglamento (CE) n°. 304/2008 de la Comisión, por el que se establecen, de conformidad con el Reglamento (CE) nº 842/2006 del Parlamento Europeo y del Consejo, los requisitos mínimos y las condiciones del reconocimiento mutuo de la certificación de las empresas y el personal en lo relativo a los sistemas fijos de protección contra incendios y los extintores que contengan determinados gases fluorados de efecto invernadero. DOUE Nº. 92 de

03/04/2008

- Reglamento (UE) n°. 517/2014 del Parlamento Europeo y del Consejo, sobre los gases fluorados de efecto invernadero y por el que se deroga el reglamento

(CE) n°. 842/06. DOUE Nº. 195 de 20/05/2014

- Real Decreto 833/1975, que desarrolla la Ley 38/1972 de protección del ambiente atmosférico. BOE No. 96 of 22/04/1975

01 11 01 - 9

- Decreto 3025/1974, limitación de la contaminación atmosférica producida por vehículos automóviles. BOE No. 0 of 07/11/1974

- Decreto 74/1996, por el que se aprueba el reglamento de calidad del aire.

BOJA No. 30 of 07/03/1996

- Decreto 247/2001, de 13 de noviembre, por el que se aprueba el Reglamento de Prevención y Lucha contra los Incendios Forestales. BOJA n°. 144 de

15/12/2001

Energy:

- Ley 25/1964, reguladora de la energía nuclear. BOE No. 107 of 04/05/1964

- Real Decreto 1427/1997, aprueba la instrucción técnica complementaria MI-IP

03 "instalaciones petrolíferas para uso propio". BOE No. 254 of 23/10/1997

- Real Decreto 1836/1999, reglamento sobre instalaciones nucleares y radiactivas. BOE No. 313 of 31/12/1999

- Real Decreto 1523/1999, instalaciones petrolíferas. Modificación del reglamento aprobado por RD 2085/94 de 20 de octubre y las ITC MI - IP03 y

MI-IP04. BOE of 22/10/1999

Ambient Impact Evaluation:

- Directiva 2010/75/UE del Parlamento Europeo y del Consejo, sobre las emisiones industriales (prevención y control integrados de la contaminación).DOUE de 17/12/2010

- Ley 7/2007, de gestión integrada de la calidad ambiental. BOE No. 190 of

09/08/2007

- Decreto 356/2010, se regula la autorización ambiental unificada, se establece el régimen de organización y funcionamiento del registro de autorizaciones de actuaciones sometidas a los instrumentos de prevención y control ambiental, de las actividades potencialmente contaminadoras de la atmósfera y de las instalaciones que emiten compuestos orgánicos volátiles, y se modifica el anexo I de la Ley 7/2007, de 9 de julio, de gestión integrada de la calidad ambiental. BOJA No. 157 of 11/08/2010

General:

- Ley 21/1992, de Industria. BOE No. 176 of 23/07/1992

- Ley 26/2007, de responsabilidad ambiental. BOE No. 255 of 24/10/2007

- Real Decreto 2090/2008, por el que se aprueba el reglamento de desarrollo parcial de la Ley 26/2007, de 23 de octubre, de responsabilidad

01 11 01 - 10 medioambiental. BOE No. 308 of 23/12/2008

- Ley 11/2014, por la que se modifica la ley 26/2007, de 23 de octubre, de responsabilidad medioambiental. BOE No. 162 of 04/07/2014

- Ley 32/2014, modificación de la ley 21/1992. BOE No. 309 of 23/12/2014

Installations (Technical-legal):

- Real Decreto 919/2006, se aprueba el reglamento técnico de distribución y utilización de combustibles gaseosos y sus instrucciones técnicas complementarias ICG 01 a 11. BOE No. 211 of 04/09/2006

- Real Decreto 1416/2006, aprueba la instrucción técnica complementaria MI-IP

06 "Procedimiento para dejar fuera de servicio los tanques de almacenamiento de productos petrolíferos líquidos". BOE No. 1416 of 25/12/2006

- Real Decreto 1027/2007, por el que se aprueba el reglamento de instalaciones térmicas en los edificios. BOE No. 207 of 29/08/2007

- Real Decreto 1826/2009, modifica RD 1027/2007 de instalaciones térmicas

(RITE). BOE No. 298 of 11/12/2009

- Real Decreto 1388/2011, se dictan las disposiciones de aplicación de la directiva 2010/35/UE del Parlamento Europeo y del Consejo de 16 de junio de

2010 sobre equipos a presión transportables y por la que se derogan las directivas 76/767/CEE, 84/526/CEE, 84/526/CEE, 84/527/CEE y 1999/36/CE.

BOE No. 249 of 15/10/2011

Natural Environment and Landscape:

- Real Decreto 1311/2012, uso sostenible de los productos fitosanitarios. BOE

No. 223 of 15/09/2012

Hazardous Goods:

- Instrumento de adhesión al acuerdo europeo sobre transporte internacional de mercancías peligrosas por carretera (ADR). BOE Nº 163 de 9/07/1973

Wastes:

- Directiva 2008/98/CE del Parlamento Europeo y del Consejo, sobre los residuos y por la que se derogan determinadas Directivas. DOUE Nº 312 de

22/11/2008

- Real Decreto 833/1988, reglamento para la ejecución de la ley 20/1986 básica de residuos tóxicos y peligrosos. BOE No. 182 of 30/07/1988

- Real Decreto 952/1997, modifica el reglamento para la ejecución de la ley

20/1986, básica de residuos tóxicos y peligrosos. BOE No. 160 of 05/07/1997

01 11 01 - 11

- Ley 11/1997, de envases y residuos de envases. BOE No. 99 of 25/04/1997

- Real Decreto 782/1998, reglamento para la ejecución de la ley 11/1997, de 24 de abril, de envases y residuos de envases. BOE No. 104 of 01/05/1998

- Real Decreto 1481/2001, eliminación de residuos mediante depósito en vertedero. BOE No. 25 of 29/01/2002

- Orden del Ministerio de Medio Ambiente MAM/304/2002, operaciones de valorización y eliminación de residuos y lista europea de residuos. BOE No.

43 of 19/02/2002

- Real Decreto 105/2008, por el que se regula la producción y gestión de los residuos de construcción y demolición. BOE No. 38 of 13/02/2008

- Real Decreto 106/2008, sobre pilas y acumuladores y la gestión ambiental de sus residuos. BOE No. 37 of 12/02/2008

- Ley 22/2011, de residuos y suelos contaminados. BOE No. 181 of 29/07/2011

- Real Decreto 180/2015, se regula traslado de residuos en el interior del territorio del Estado. BOE No. 83 of 07/04/2015

- Real Decreto 1254/1999, se aprueban medidas de control de los riesgos inherentes a los accidentes graves en los que intervengan sustancias peligrosas. BOE No. 172 of 20/07/1999

- Orden 12/07/2002, por la que se regulan los documentos de control y seguimiento a emplear en la recogida de residuos peligrosos en pequeñas cantidades. BOJA No. 97 of 20/08/2002

- Decreto 73/2012, se aprueba el reglamento de residuos de Andalucía. BOJA

No. 81 of 26/04/2012

- Real Decreto 679/2006, por el que se regula la gestión de los aceites industriales usados. BOE No. 132 de 3/6/2006

Noise and Vibrations:

- Ley 37/2003, ley del ruido. BOE No. 276 of 18/11/2003

- Real Decreto 1367/2007, por el que se desarrolla la ley 37/2003, de 17 de noviembre, del ruido, en lo referente a zonificación acústica, objetivos de calidad y emisiones acústicas. BOE No. 254 of 23/10/2007

- Decreto 326/2003, reglamento de protección contra la contaminación acústica en Andalucía. BOJA No. 243 of 18/12/2003

- Orden 26/07/2005, odelo tipo de ordenanza municipal de protección contra la

01 11 01 - 12 contaminación acústica. BOJA No. 158 of 26/07/2005

- Decreto 6/2012, reglamento de protección contra la contaminación acústica en

Andalucia. BOJA No. 24 of 06/02/2012

- Real Decreto 212/2002, de 22 de febrero, por el que se regulan las emisiones sonoras en el entorno debidas a determinadas máquinas de uso al aire libre.

BOE n°. 52 de 1/03/2002

Hazardous Substances:

- Real Decreto 379/2001, reglamento de almacenamiento de productos químicos y sus ITC MIE APQ 1, 2, 3, 4, 5, 6 y 7. BOE No. 112 of 10/05/2001

Soil and Subsoil:

- Decreto 2857/1978, reglamento general para el régimen de la minería. BOE

No. 45 of 11/12/1978

- Real Decreto 9/2005, por el que se establece la relación de actividades potencialmente contaminantes del suelo y los criterios y estándares para la declaración de suelos contaminados. BOE No. 15 of 18/01/2005

- Ley 22/1973, de minas. BOE No. 176 of 24/07/1973

Various:

- Real Decreto 957/2002, se regulan las inspecciones técnicas en carretera de los vehículos industriales que circulen en territorio español. BOE No. 227 of

21/09/2002

- Real Decreto 2042/1994, inspección técnica de vehículos. BOE No. 275 of

17/11/1994

18.1 Conservation and Maintenance of the Existing Vegetation: The Contractor shall conserve and protect the existing vegetation (trees, shrubs, grass) on or adjacent to the work site, which shall not to be removed and which do not interfere with the work required under this contract. The contractor shall only remove trees or shrubs when specifically indicated in the drawings and specifications and shall avoid damaging the rest of vegetation. If any limbs or branches of trees are broken during contract performance due to the careless operation of equipment or the carelessness of the workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall cut the grass or vegetation in the work site so that it does not exceed 10 cm in height.

The Contractor shall restore, at no additional cost to the Government of the United States of

America to their original state all areas disturbed during construction to their original condition before final acceptance of works under this project.

18.2 Housekeeping and Site Cleanup: The Contractor shall dispose of accumulated debris, waste materials and rubbish and shall keep the site in order. All rubbish and waste materials shall be removed daily and shall be placed in contractor furnished containers and

01 11 01 - 13 shall be removed on a daily basis to an authorized dump off-Base as the project progresses.

Contractors shall ensure all light weight debris at the construction site is properly secured in waste receptacles so that it does not blow to another area or onto the airfield. Once the works are finished, the Contractor shall remove the containers.

18.3 Cleaning and Maintenance of Access Routes: The Contractor shall be solely responsible for any material dumped/spilled by trucks, vehicles and machinery or equipment on the access routes.