QUUG_15-1011_English_Specifications.pdf

PDF 990 KB Posted

Attached to
Install Generator & ATS, Bldg #1301 Federal contract opportunity
Solicitation number
FA5575-16-B-0007
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Contract Specifications (English)

View the file

Other files for this federal contract opportunity

Other files attached to Install Generator & ATS, Bldg #1301, newest first.
File Type Posted
FA5575-16-B-0007-0001_Amend.pdf PDF
FA5575-16-B-0007.pdf PDF
15-1011.pdf PDF
15-1011_AF_3052_Ktor_OH_BREAKDOWN.xlsx XLSX spreadsheet
QUUG_15-1011_Especificaciones_Espaol_(de_PROJECTS_tal_cual).pdf PDF
15-1011_Schedule_of_Material_Submittals.xlsx XLSX spreadsheet
Synopsis_16B0007.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED FOR DEPARTMENT OF THE

AIR FORCE

BY

VECTRUS SYSTEMS CORPORATION

ENGINEERING DESIGN SECTION

MORÓN AIR BASE

TECHNICAL PROVISIONS & SPECIFICATIONS FOR:

PROJECT QUUG 15-1011

INSTALL GENERATOR & ATS, BLDG #1301

Prepared by: _____________________________________________________________________ Name: Manuel Córdoba García, CENDE Date: 11 Jan 16

Reviewed by: ___________________________________________________________________ Name: Sydney Derizzio, CECC Date: 5 Jul 16

Approved by: ____________________________________________________________________ Name: John R. Floden, P.E., BCEE, DCE Date: 5 Jul 16

Validated by:_____________________________________________________________________ Name: David D. Schoenhardt, Capt, USAF Date: 5 Jul 16 Base Civil Engineer

TP-2

LIST OF SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Scope of Work, Drawings and Special Conditions 5 01 11 01 General Conditions 26

DIVISION 26 - ELECTRICAL

26 00 00.00 20 Basic Electrical Materials and Methods 7 26 20 00 Interior Distribution System 13

26 32 13.00 20 Single Operation Generator Sets 29 26 36 00.00 10 Automatic Transfer Switch and By-pass Isolation Switch 9

26 51 00 Interior Lighting 5

DIVISION 33 - UTILITIES

33 71 02.00 20 Underground Electrical Transmission and Distribution 5

01 11 00 - 1

SECTION 01 11 00

SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS

1. SCOPE OF WORK: The scope of work consists of the furnishing of all the labor, materials, plants, transportations, equipment and services to accomplish all the work in strict accordance with the drawings and specifications and complete and ready for use under a firm fixed price construction contract. The work includes, but is not limited to, the following items:

1.1 Demolition of existing generator installation.

1.1.1 Remove electrical connections of portable generator and assist/co-ordinate shop with removal.

1.1.2 Remove Automatic Transfer Switch and By-pass/Isolation Switch and deliver to

Government representatives as indicated in project drawings.

1.1.3 Demolish grounding system of generator.

1.1.4 Demolish other all equipment indicated in project drawings.

1.1.5 Demolish electrical and lighting installation at server rooms as indicated.

1.2 Installation of new equipment:

1.2.1 Furnish and install new EPA-compliant electrical generator rated and located as indicated in project drawings and specifications.

1.2.2 Furnish and install new automatic transfer switch for automatic change-over from the electrical network to generator operation.

1.2.3 Furnish and install new by-pass/isolation and manual transfer switch where required for by-pass maintenance capability.

1.2.4 Furnish and install new weatherproof metal raceway outdoors for connection of generator to building interior electrical installation.

1.2.5 Make all necessary connections.

01 11 00 - 2

1.2.6 Furnish and install new interior distribution system in server rooms as indicated in project drawings.

1.2.7 Furnish and install new interior lighting system in server rooms as indicated in project drawings.

1.2.8 Provide adequate grounding to new generator.

1.2.9 Commissioning and final testing on all new equipment.

1.3 Final cleaning.

1.4 Delivery of As-Built drawings.

1.5 Delivery of Spatial data.

2. PERFORMANCE PERIOD: The performance period estimated by the Government for the execution of this project, 210 calendar days, includes from the pre-construction activities through the final works, and includes average inclement weather days and equipment manufacture and delivery times.

2.1 It shall be the sole responsibility of the Contractor to ensure all required submittals are submitted to the Contracting Office for approval in a timely manner which shall not incur any delay in completion of the project. Materials or equipment requiring long lead time for procurement and delivery shall be included in the period of performance. Delay in delivery/procurement will not justify an extension of the period of performance.

2.2 The contractor's proposal has to include a Construction Schedule.

2.2.1 The Construction Schedule shall include a Gantt chart showing each task, including its description, identification number, duration in calendar days, earliest start and finish dates and the predecessor and successor activity identification number, the critical path and the float that a task in the project network can be delayed without causing a delay to the subsequent task/s (free float) and to the project completion date (total float). The critical path shall be shown in red color and the float by means of black line after the predecessor task bar.

2.2.2 The Construction Schedule shall show the whole week, from Monday through Sunday. The labor days shall be from Monday through Friday. Saturday and Sunday shall be non-labor days. The holidays shall not be considered on the Construction Schedule and, therefore, they shall be considered labor days for Construction Schedule development purpose only.

01 11 00 - 3

2.2.3 The Construction Schedule shall be developed assuming 8-working hours for each labor days.

2.2.4 The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies, as well as activities associated with both pre-construction and close-out submittals, commissioning, testing and pre-final/final inspections, correction of punch lists, final cleaning, etc.

2.3 Contractor shall submit a Work Plan:

2.3.1 The Work Plan shall present the sequence of preconstruction and construction activities planned to take place. The Work Plan shall be prepared in coordination with the Health and Safety Plan and the Quality Control Plan and shall contain the following:

a. The summary of the proposed methodology for the execution of each task required for the project completion.

b. The resources to be used for the execution of each task required for the project completion describing the equipment and personnel to be used.

c. Daily production for each task required for the project completion.

3. DRAWINGS:

No. of Drawing Sheet Date Title

R-708-01 01 of 07 23 Feb 16 Cover Sheet, Drawing Schedule R-708-02 02 of 07 23 Feb 16 Site Plan R-708-03 03 of 07 23 Feb 16 Existing Installation and Demolition R-708-04 04 of 07 23 Feb 16 Existing Condition Bldg 1301 R-708-05 05 of 07 23 Feb 16 New Electrical Installation R-708-06 06 of 07 23 Feb 16 Single-line Diagrams R-708-07 07 of 07 23 Feb 16 Electrical Details

4. GOVERNMENT-FURNISHED MATERIAL (GFM): NOT USED.

5. EQUIPMENT, CONTROLS, AND MATERIAL OF THE UNITED STATES OF

AMERICA:

5.1 Equipment List: The following listed equipment, controls, and materials shall be manufactured in the United States of America or in another country where the supplier is under

01 11 00 - 4 license of the United States of America manufacturer and the product meets the same applicable specifications and/or standards. No substitutions will be allowed.

a. Electrical conduits, boxes and accessories.

b. Generator sets.

c. Automatic Transfer Switches.

d. Receptacles and lighting switches.

e. Fluorescent lamps and ballasts.

5.2 Excess: The Contractor shall furnish to the Contracting Officer, just prior to completion of this contract, a consolidated inventory of all excess supplies, materials, and equipment imported duty free for use under this contract. The Contractor shall either pay required duties on the excesses or re-export the excesses.

6. CERTIFICATION OF CLASSIFICATION: Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by the “Registro Oficial de Licitadores y Empresas Clasificadas del Estado” of the "Ministerio de Hacienda y Administraciones Públicas", covering the following groups, subgroups, and categories. The certificate holder must execute the activities related to the certificate.

Group Subgroup Category I 1, 6 B

Certificate of Classification I1B corresponds to work activities related to lighting, illuminations and beaconing with an annual average of more than 60,000 euros but less than 120,000 euros, I6B to work activities related to low voltage distribution with an annual average of more than 60,000 euros but less than 120,000 euros.

7. SPECIAL REQUIREMENTS: For the purpose of minimizing the impact of the project execution with Base activities the Contractor shall consider in his price proposal that the power outages required for the project execution shall be coordinated with the user, the electrical shop and the ground power shop, so no building shall remain without electrical supply during execution for more than 15 minutes. Also, these power outages shall be scheduled outside normal working hours, to include weekends. The Contractor shall also consider that at least 4 hours are required by the shops to set up the switch and make the change to an alternate power supply, and the Contractor shall not be able to work in the installation during that time.

7.1 Work Restrictions: Work interruptions are expected to be caused by the security conditions of the site where work shall take place, considered a restricted area, where the Contractor shall be escorted at all times by members of the USMC. Also, entrance to building #1301 and to server rooms within shall be subject to additional security requirements that may slow down

01 11 00 - 5

Contractor’s work execution, who shall take said hindrances into account in his bid for consideration of his proposed period of performance.

*** END OF SECTION ***

01 11 01 - 1

SECTION 01 11 01

GENERAL CONDITIONS

1. GENERAL: The work consists of furnishing all labor, materials, plant, transportation, equipment, and services to complete the project described in Section 01 11 00, Scope of Work, Drawings and Special Conditions, in accordance with the drawings and specifications, complete and ready for use by means of a firm fixed price construction contract.

Measurements given in the drawings and specifications are given for reference use only. It is the Contractor’s responsibility to verify any and all of said measurements.

2. GENERAL DESCRIPTION: The work consists in, but is not limited to, executing the line items indicated in the scope of work. All line items indicated in the scope of work do not limit or reduce the Contractor’s responsibility to perform all work as required by the project in order to provide a complete and operable facility.

3. LOCATION: The work is located in Morón Air Base, Spain, as shown on the contract drawings.

4. DRAWINGS ACCOMPANYING SPECIFICATION: The drawings accompanying this specification are a part thereof. Drawings are the property of the Government, and shall not be used for any purpose other than that contemplated by the specification. The drawings included in this specification are similar to A1.

5. WARRANTY: For this contract the Contractor shall provide a two year standard commercial warranty associated with all scope of work items including materials and workmanship.

The warranty should cover all defects noticed and reported to the Contractor within two year after acceptance of the project. The Contractor shall repair or replace defective materials at the Contractor's expense within a reasonable time, and as approved by the Contracting Officer. The Contractor must comply with any additional warranty periods covered under Spanish codes and regulations. The Contractor shall submit the warranty prior to the Final Inspection and acceptance of the work by the Contracting Officer.

6. BASE ACCESS:

6.1 Permits or Authorizations: The Contractor shall obtain all permits or authorizations to access Morón Air Base. Once the works have finalized, the Contractor will return the permits or authorizations. Contractor is responsible to provide escorts as required to complete the project.

01 11 01 - 2

6.2 Delays and Interruptions: Contractors are advised that due to security reasons, during the access/egress process of personnel and materials from the Morón Air Base delays are liable to occur. Additionally, the Contractor shall immediately interrupt work when required to do so if security warning/alarm situations occur.

7. WORK CLEARANCE REQUEST: 5 calendar days after the notice to proceed (NTP) the Contractor shall request AF Form 103 “BCE Work Clearance Request” in order to obtain all the information pertaining to the current status of general utilities. Additional requests shall be processed through the Contracting Officer or authorized representative, minimum of 15 duty days beforehand. The Contractor shall not perform any excavation works under any circumstances without an approved Work Clearance Request at the work site (hard copy). Work Clearance Request will only be processed once all materials and documentation necessary to commence work have been submitted and approved. The Contractor shall be held responsible for any damage caused to general utilities indicated on the AF Form 103 and related drawings and shall be repaired at no additional cost to the Government of the United States.

8. BASE UTILITIES:

8.1 Use of Base Utilities: Water, Sewage and electric Base utilities are available to the Contactor for connections to the following facilities: Offices, latrines, break rooms, and laboratories.

The following Utilities will be available from the existing Base utility systems. Any additional utilities requirement besides what is listed below shall be supplied by the contractor at no cost to the Government.

a. Electricity 120/208 volts, 60 Hz.

b. Non-potable water.

15 calendar days after the notice to proceed (NTP) the Contractor shall request the connection and shall indicate the type of utility service required, type of connection and disconnection, utility service use and maximum duration. All connection and disconnection works for Base utilities shall be programmed between 08:30 and 16:00 hours, Monday through Friday, holidays excepted. It shall be the Contractor’s responsibility to effect the connections and disconnections and shall reimburse costs incurred in the connection, disconnection, conversion, transportation of Base utility services to the work site, including providing the mechanisms that avoid water from flowing back into the system (backflow preventers) and furnishing and installing the necessary transformers. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity.

Control devices will be Government operated. Additional requests shall be processed through the Contracting Officer or authorized representative with a minimum of 5 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required.

01 11 01 - 3

Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

8.2 Base Utility Outages: Whenever a utility outage is required, the Contractor shall request the utility outage and shall indicate the type of outage to be performed, the scope of work and the maximum duration. All utility outages shall be scheduled between 08:30 and 16:00 hours, Monday through Friday, holidays excepted. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity.

Control devices will be Government operated. The Contractor shall notify the Contracting Officer or authorized representative 10 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required. Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

9. HOT WORK: The Contractor shall submit for approval a written request to the Contracting Officer or authorized representative 10 calendar days prior to any welding, oxyacetylene or plasma cutting work. Said request shall indicate welding procedures and fire prevention measures. All welding work performed during the project shall be carried out by qualified welders only. The copies of the welding certificates, issued by an approved agency, shall be kept in the construction inspector’s files.

10. VEHICULAR TRAFFIC, MACHINERY AND EQUIPMENT:

10.1 Traffic Control: All works which require vehicular or pedestrian traffic disruptions on the Base shall require an approved transit control plan. Said plan shall be approved at least 7 calendar days prior to carrying out said disruption. Said plan shall include the date, duration, proposed alternative routes, signs, barriers, cones and/or flagmen. The Contractor shall establish alternate procedures should unforeseen circumstances take place. The responsibility of furnishing, erecting, maintaining and removing all signs, barriers, cones and flags shall be solely the Contractor’s. Once the work is completed, the Contractor shall remove the signaling elements such as barriers, cones and/or flags.

10.2 Access Routes: The Contractor shall submit a plan for the access routes which shall be approved by the Contracting Officer or authorized representative.

10.3 Trucks: Trucks loaded with loose material (air borne dust, construction debris or other objects that could fall from them), shall be duly covered. Said covers, such as tarps, shall be fastened over the load prior to accessing the adjacent roads.

11. PROGRESS SCHEDULE (AF Form 3064): (See solicitation/Contract FAR clause 52.236-15, Schedules for Construction Contracts, Apr 1984). The Contractor shall, 10 calendar days after the notice to proceed (NTP) or another period of time determined by the Contracting

01 11 01 - 4

Officer, prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

12. MOBILITY PLAN: The Contractor shall submit a mobility plan to the Contracting Officer or authorized representative for approval. Said plan shall propose the location and surface of the work site, offices and material staging and storage areas. The Contractor shall submit the plan 15 calendar days after the notice to proceed (NTP). The Contractor shall include in the mobility plan the proposed system to supply the required utility services required at each site.

12.1 Construction Site Fencing: Construction sites, offices, latrines, material staging and storage areas shall be fenced in by means of a two meter high fence to include gates and locks, unless otherwise approved the Government of the United States. The type of fencing, height and color shall be specified in accordance with the Contracting Officer or authorized representative’s criteria. Fences shall be screened with green opaque screening material to prevent visibility inside the fenced area. Fencing shall be completely secured at top and bottom to prevent access.

Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. The Contractor shall include in the Mobilization Plan photos, catalogs or samples of the screening material. The Contractor shall not install the fencing or screening materials until approval, in writing, has been granted from the Contracting Officer or authorized representative. The responsibility of providing, erecting, maintaining and removing the fencing shall be solely the Contractor’s. The Contractor shall replace or repair, within the following 24 hours or as determined by the Contracting Officer or authorized representative, all fence or screening sections which have been damaged or deteriorated. Once the works have been finalized, the Contractor shall remove the fencing.

12.2 Offices: Temporary prefabricated buildings required for administrative reasons (office space, conference room and break room) shall be in good conditions. Temporary prefabricated buildings requiring paint, repairs or are in bad conditions shall not be allowed at the site. Said temporary prefabricated buildings shall include on the outside a plaque, 0.5 x 0.5 meters maximum dimensions, indicating the name of the company and telephone number (s) of the person (s) designated as POC for the Contractor 24 hours a day. Once the works are finalized, the Contractor shall remove the temporary prefabricated buildings.

12.3 Latrines: Prefabricated temporary buildings required as latrines for personnel shall be in good conditions. The prefabricated temporary buildings requiring paint, repairs or are in

01 11 01 - 5 bad conditions shall not be allowed on the work site. These facilities shall be kept in perfect using conditions and sanitized, shall be treated for insects and shall be emptied once a week and cleaned with a detergent suitable for sanitary use. The frequency of emptying and cleaning shall be adjusted according to needs. The facilities shall be located no less than 50 meters from the existing buildings on Base if they cannot be located near a sewage manhole. Once the works have been completed, the Contractor shall remove the temporary facilities and shall leave the area clean and sanitized.

12.4 Parking: The Contractor, their employees and subcontractors shall park all vehicles, including heavy machinery, equipment or vehicles, in areas where they do not pose an obstruction in the corresponding work site. All possible efforts must be made so that the vehicles are not parked in an area where they will be clearly visible from the outside.

12.5 Material Storage: Storage containers will be in good conditions. The storage of materials at the work site shall be at the Contractor’s own risk. The use of private security guards at the work site shall require Spanish Air Force Security Forces approval. The Contractor shall not use the work site to store material previously approved by the Contracting Officer or authorized representative. Once the works have finished, the Contractor shall remove the excess stored material.

13 PROJECT SIGN 15 calendar days after the notice to proceed (NTP) the Contractor shall install an identifying project sign in accordance with Figure 1 no later than one day after the mobilization has been installed. The sign shall be mounted on two wooden posts 10 cm x 10 cm, fastened to the ground and adequately anchored. The location of said sign shall be determined by the Contracting Officer or his representative. During final cleanup of the work site, the sign, posts and anchoring elements shall be removed. Unless otherwise specified, the sign shall have a white background and the lettering shall be dark blue.

01 11 01 - 6

FIGURE 1 - : PROJECT SIGN

14. QUALITY CONTROL PLAN: 15 calendar days after the notice to proceed (NTP) the Contractor shall submit a comprehensive Quality Control Plan. The plan shall contain at minimum the following:

1. Names and Qualifications for the proposed Quality Control Manager and

Inspectors.

2. Organization Chart. Include teaming partners/key subcontractors for pertinent trades required for specific project. The subcontractors/partners indicated shall be those that will be effectively participating in the project and shall be the same than those submitted in the contract bid, if they were required. Lack of this information, or variation with previously submitted organizations shall be cause

01 11 01 - 7 for disapproval of the QC Plan, and the request to submit a new one before works can start/proceed.

3. Responsibility of the Quality Control Inspectors, Quality Control Manager and the Project Manager.

4. Inspection types to be performed. The Contractor shall fully develop a Program

Points Inspection (PPI) System covering all types of works involved in the project. Development of the PPI System shall be based in any and all of the following documentation:

a. Project drawings and specifications.

b. Applicable regulations, standards and industry codes.

c. Specific regulations to certain products, installations or facilities.

d. Manufacturer’s recommendations.

Number and type of Inspection Points (IP) shall be determined as many as required to provide an acceptable level of inspection for achieving the best quality results. Evaluation of whether or not the number and type of IPs are enough to achieve the expected level of quality shall be determined by the Contracting Officer.

5. Inspection Procedures and actions to be taken for failed or unsatisfactory inspections.

6. Inspection Reporting forms. Submit all reporting forms for any type of inspection to be performed under this project. As a minimum, a specific form shall be developed for each technical provision of the specifications, covering all necessary inspection points for such work. Minimum information required for each IP shall be: description of the IP, applicable documents, frequency/type of inspection, responsible of the inspection performed and result, date of inspection, reference to non-compliance document/register if not in compliance, information about pass/rejection criteria for the IP, etc.

7. List of planned ‘Hold Inspection Points’ with the estimated dates from the construction schedule.

8. Form “Schedule of Material Submittals” provided with this project with column titled “Required Submission Date” filled in by the Contractor with the dates provided by his Construction Schedule, in order to avoid delays in project completion because of pending non-approved submittals.

01 11 01 - 8

9. Request for Information (RFI): submit the Request for Information Form (RFI) and RFI Log Form. This will be used to submit and track any RFI’s during construction.

10. Material Testing: Submit the name and qualifications for any Testing Agency or

Laboratory planned for testing. All testing reports shall be submitted in a timely manner for review and approval. Related work may continue only after testing report has been approved. Should any test report fail, follow-on work is not to proceed until after the failure has been corrected. It is the responsibility of the QC Manager to ensure that all reports have been reviewed and the necessary action taken to resolve any failed testing.

11. A daily report of all actions performed during the contract period is required to be documented on a daily basis. The daily reports are to be kept on the job-site and available for review at all times. A copy of the daily reports shall be submitted weekly to the Contracting Officer. The following shall be included in the report, but is not all-inclusive.

a. The date of the inspection.

b. Comment on the weather conditions.

c. Inspection of equipment and materials and their delivery date at the job-site.

d. Names of visitors to the site during the day.

e. Inspection of any deficiencies discovered during the day and corrective action taken.

f. Inspection and acceptance of subcontractor materials and workmanship.

g. Work being performed during the day, including the used labor personnel and equipment.

h. Any field change or modifications approved by the Contracting Officer.

14.1 Acceptance of the Construction Quality Control (QC) Plan: Acceptance of the QC Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work.

14.2 Maintenance of records is the responsibility of the contractor.

15 PRE-FINAL AND FINAL INSPECTIONS: Final inspection and acceptance will be conducted jointly with the inspector and a representative from the contracting office. The contractor shall request a pre-final inspection once the works are completed in accordance with the inspector's judgement. After the solving of all the discrepancies found during the pre-final inspection, if any, the contractor shall request a final inspection. All punch list items must be

01 11 01 - 9 completed before final acceptance of the project.

16. WORK DAY:

16.1 Normal Work Hours: The Contractor shall perform all work during normal working hours unless a special authorization is issued by the Contracting Office representative to deviate from said work schedule. Normal working hours shall be from 0800 to 1700, from Monday to Friday, with the exception of holidays.

16.2 Work Outside Normal Hours: If the Contractor wishes to work outside the normal hours of operation, Saturdays, Sundays, or holidays, he shall submit an application to the Contracting Officer. The Contractor shall submit the request five (5) work days ahead of time as minimum.

16.3 Power Outages for Mission-Critical Buildings: Power outages for mission-critical buildings in this project may have to be performed outside normal hours to include weekends or holidays, to reduce impact on mission to a minimum

17. CONSERVATION AND MAINTENANCE OF THE EXISTING FACILITIES:

The contractor shall conserve and protect all existing facilities at the work site or adjacent to it which shall not to be removed or affected by the work required under this contract. The Contractor shall restore, at no additional cost to the Government of the United States of America, the facility affected during the execution of works to its original condition, before final acceptance of the project.

18. ENVIRONMENTAL PROTECTION PLAN: 15 calendar days after the notice to proceed (NTP) the Contractor shall submit the Environmental Protection Plan. The program shall include, but not be limited to, the following:

Classified Activitiess:

- Decreto 2414/1961, reglamento de actividades molestas, insalubres, nocivas y peligrosas (RAMINP). BOE de 07/12/1961

- Orden del Ministerio de Gobernación de 15/03/1963, se aprueba una instrucción por la que se dictan normas complementarias para la aplicación del reglamento de actividades molestas, insalubres, nocivas y peligrosas. BOE N°. 79 de 02/04/1963

- Decreto 297/1995, reglamento de calificación ambiental. BOJA No. 3 de

11/01/1996

Water:

01 11 01 - 10

- Real Decreto 60/2011, normas de calidad ambiental en el ámbito de la política de aguas. BOE No. 19 of 22/01/1201

- Real Decreto 849/1986, de 11 de abril, por el que se aprueba el Reglamento del

Dominio Público Hidráulico que desarrolla los títulos preliminar, I, IV, V, VI, VII y VIII del texto refundido de la Ley de Aguas, aprobado por el Real Decreto Legislativo 1/2001, de 20 de julio. BOE No. 103 de 30/04/1986

- Real Decreto Legislativo 1/2001, de 20 de julio, por el que se aprueba el texto refundido de la Ley de Aguas. BOE No. 176 de 24/07/2001

- Orden del Ministerio de Medio Ambiente, Rural y Marino (ARM)/1312/2009, de

20 de mayo, por la que se regulan los sistemas para realizar el control efectivo de los volúmenes de agua utilizados por los aprovechamientos de agua del dominio público hidráulico, de los retornos al citado dominio público hidráulico y de los vertidos al mismo. BOE No. 128 de 27/05/2009

Atmosphere:

- Reglamento (CE) n°. 1497/2007 de la Comisión, por el que se establecen, de conformidad con el Reglamento (CE) no 842/2006 del Parlamento Europeo y del Consejo, requisitos de control de fugas estándar para los sistemas fijos de protección contra incendios que contengan determinados gases fluorados de efecto invernadero. Diario Oficial de la Unión Europea (DOUE) Nº. 333 de 19/12/2007

- Reglamento (CE) n°. 304/2008 de la Comisión, por el que se establecen, de conformidad con el Reglamento (CE) nº 842/2006 del Parlamento Europeo y del Consejo, los requisitos mínimos y las condiciones del reconocimiento mutuo de la certificación de las empresas y el personal en lo relativo a los sistemas fijos de protección contra incendios y los extintores que contengan determinados gases fluorados de efecto invernadero. DOUE Nº. 92 de 03/04/2008

- Reglamento (UE) n°. 517/2014 del Parlamento Europeo y del Consejo, sobre los gases fluorados de efecto invernadero y por el que se deroga el reglamento (CE) n°. 842/06. DOUE Nº. 195 de 20/05/2014

- Real Decreto 833/1975, que desarrolla la Ley 38/1972 de protección del ambiente atmosférico. BOE No. 96 of 22/04/1975

- Decreto 3025/1974, limitación de la contaminación atmosférica producida por

01 11 01 - 11 vehículos automóviles. BOE No. 0 of 07/11/1974

- Decreto 74/1996, por el que se aprueba el reglamento de calidad del aire. BOJA

No. 30 of 07/03/1996

- Decreto 247/2001, de 13 de noviembre, por el que se aprueba el Reglamento de

Prevención y Lucha contra los Incendios Forestales. BOJA n°. 144 de 15/12/2001

Energy:

- Ley 25/1964, reguladora de la energía nuclear. BOE No. 107 of 04/05/1964

- Real Decreto 1427/1997, aprueba la instrucción técnica complementaria MI-IP 03

"instalaciones petrolíferas para uso propio". BOE No. 254 of 23/10/1997

- Real Decreto 1836/1999, reglamento sobre instalaciones nucleares y radiactivas.

BOE No. 313 of 31/12/1999

- Real Decreto 1523/1999, instalaciones petrolíferas. Modificación del reglamento aprobado por RD 2085/94 de 20 de octubre y las ITC MI - IP03 y MI-IP04. BOE of 22/10/1999

Ambient Impact Evaluation:

- Directiva 2010/75/UE del Parlamento Europeo y del Consejo, sobre las emisiones industriales (prevención y control integrados de la contaminación).DOUE de 17/12/2010

- Ley 7/2007, de gestión integrada de la calidad ambiental. BOE No. 190 of

09/08/2007

- Decreto 356/2010, se regula la autorización ambiental unificada, se establece el régimen de organización y funcionamiento del registro de autorizaciones de actuaciones sometidas a los instrumentos de prevención y control ambiental, de las actividades potencialmente contaminadoras de la atmósfera y de las instalaciones que emiten compuestos orgánicos volátiles, y se modifica el anexo I de la Ley 7/2007, de 9 de julio, de gestión integrada de la calidad ambiental.

BOJA No. 157 of 11/08/2010

General:

- Ley 21/1992, de Industria. BOE No. 176 of 23/07/1992

01 11 01 - 12

- Ley 26/2007, de responsabilidad ambiental. BOE No. 255 of 24/10/2007

- Real Decreto 2090/2008, por el que se aprueba el reglamento de desarrollo parcial de la Ley 26/2007, de 23 de octubre, de responsabilidad medioambiental. BOE No. 308 of 23/12/2008

- Ley 11/2014, por la que se modifica la ley 26/2007, de 23 de octubre, de responsabilidad medioambiental. BOE No. 162 of 04/07/2014

- Ley 32/2014, modificación de la ley 21/1992. BOE No. 309 of 23/12/2014

Installations (Technical-legal):

- Real Decreto 919/2006, se aprueba el reglamento técnico de distribución y utilización de combustibles gaseosos y sus instrucciones técnicas complementarias ICG 01 a 11. BOE No. 211 of 04/09/2006

- Real Decreto 1416/2006, aprueba la instrucción técnica complementaria MI-IP 06

"Procedimiento para dejar fuera de servicio los tanques de almacenamiento de productos petrolíferos líquidos". BOE No. 1416 of 25/12/2006

- Real Decreto 1027/2007, por el que se aprueba el reglamento de instalaciones térmicas en los edificios. BOE No. 207 of 29/08/2007

- Real Decreto 1826/2009, modifica RD 1027/2007 de instalaciones térmicas

(RITE). BOE No. 298 of 11/12/2009

- Real Decreto 1388/2011, se dictan las disposiciones de aplicación de la directiva

2010/35/UE del Parlamento Europeo y del Consejo de 16 de junio de 2010 sobre equipos a presión transportables y por la que se derogan las directivas 76/767/CEE, 84/526/CEE, 84/526/CEE, 84/527/CEE y 1999/36/CE. BOE No.

249 of 15/10/2011

Natural Environment and Landscape:

- Real Decreto 1311/2012, uso sostenible de los productos fitosanitarios. BOE No.

223 of 15/09/2012

Hazardous Goods:

01 11 01 - 13

- Instrumento de adhesión al acuerdo europeo sobre transporte internacional de mercancías peligrosas por carretera (ADR). BOE Nº 163 de 9/07/1973

Wastes:

- Directiva 2008/98/CE del Parlamento Europeo y del Consejo, sobre los residuos y por la que se derogan determinadas Directivas. DOUE Nº 312 de 22/11/2008

- Real Decreto 833/1988, reglamento para la ejecución de la ley 20/1986 básica de residuos tóxicos y peligrosos. BOE No. 182 of 30/07/1988

- Real Decreto 952/1997, modifica el reglamento para la ejecución de la ley

20/1986, básica de residuos tóxicos y peligrosos. BOE No. 160 of 05/07/1997

- Ley 11/1997, de envases y residuos de envases. BOE No. 99 of 25/04/1997

- Real Decreto 782/1998, reglamento para la ejecución de la ley 11/1997, de 24 de abril, de envases y residuos de envases. BOE No. 104 of 01/05/1998

- Real Decreto 1481/2001, eliminación de residuos mediante depósito en vertedero.

BOE No. 25 of 29/01/2002

- Orden del Ministerio de Medio Ambiente MAM/304/2002, operaciones de valorización y eliminación de residuos y lista europea de residuos. BOE No. 43 of 19/02/2002

- Real Decreto 105/2008, por el que se regula la producción y gestión de los residuos de construcción y demolición. BOE No. 38 of 13/02/2008

- Real Decreto 106/2008, sobre pilas y acumuladores y la gestión ambiental de sus residuos. BOE No. 37 of 12/02/2008

- Ley 22/2011, de residuos y suelos contaminados. BOE No. 181 of 29/07/2011

- Real Decreto 180/2015, se regula traslado de residuos en el interior del territorio del Estado. BOE No. 83 of 07/04/2015

- Real Decreto 1254/1999, se aprueban medidas de control de los riesgos inherentes a los accidentes graves en los que intervengan sustancias peligrosas. BOE No. 172 of 20/07/1999

- Orden 12/07/2002, por la que se regulan los documentos de control y seguimiento

01 11 01 - 14 a emplear en la recogida de residuos peligrosos en pequeñas cantidades. BOJA No. 97 of 20/08/2002

- Decreto 73/2012, se aprueba el reglamento de residuos de Andalucía. BOJA No.

81 of 26/04/2012

- Real Decreto 679/2006, por el que se regula la gestión de los aceites industriales usados. BOE No. 132 de 3/6/2006

Noise and Vibrations:

- Ley 37/2003, ley del ruido. BOE No. 276 of 18/11/2003

- Real Decreto 1367/2007, por el que se desarrolla la ley 37/2003, de 17 de noviembre, del ruido, en lo referente a zonificación acústica, objetivos de calidad y emisiones acústicas. BOE No. 254 of 23/10/2007

- Decreto 326/2003, reglamento de protección contra la contaminación acústica en

Andalucía. BOJA No. 243 of 18/12/2003

- Orden 26/07/2005, odelo tipo de ordenanza municipal de protección contra la contaminación acústica. BOJA No. 158 of 26/07/2005

- Decreto 6/2012, reglamento de protección contra la contaminación acústica en

Andalucia. BOJA No. 24 of 06/02/2012

- Real Decreto 212/2002, de 22 de febrero, por el que se regulan las emisiones sonoras en el entorno debidas a determinadas máquinas de uso al aire libre. BOE n°. 52 de 1/03/2002

Hazardous Substances:

- Real Decreto 379/2001, reglamento de almacenamiento de productos químicos y sus ITC MIE APQ 1, 2, 3, 4, 5, 6 y 7. BOE No. 112 of 10/05/2001

Soil and Subsoil:

- Decreto 2857/1978, reglamento general para el régimen de la minería. BOE No.

45 of 11/12/1978

- Real Decreto 9/2005, por el que se establece la relación de actividades potencialmente contaminantes del suelo y los criterios y estándares para la

01 11 01 - 15 declaración de suelos contaminados. BOE No. 15 of 18/01/2005

- Ley 22/1973, de minas. BOE No. 176 of 24/07/1973

Various:

- Real Decreto 957/2002, se regulan las inspecciones técnicas en carretera de los vehículos industriales que circulen en territorio español. BOE No. 227 of 21/09/2002

- Real Decreto 2042/1994, inspección técnica de vehículos. BOE No. 275 of

17/11/1994

18.1 Conservation and Maintenance of the Existing Vegetation: The Contractor shall conserve and protect the existing vegetation (trees, shrubs, grass) on or adjacent to the work site, which shall not to be removed and which do not interfere with the work required under this contract. The contractor shall only remove trees or shrubs when specifically indicated in the drawings and specifications and shall avoid damaging the rest of vegetation. If any limbs or branches of trees are broken during contract performance due to the careless operation of equipment or the carelessness of the workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall cut the grass or vegetation in the work site so that it does not exceed 10 cm in height. The Contractor shall restore, at no additional cost to the Government of the United States of America to their original state all areas disturbed during construction to their original condition before final acceptance of works under this project.

18.2 Housekeeping and Site Cleanup: The Contractor shall dispose of accumulated debris, waste materials and rubbish and shall keep the site in order. All rubbish and waste materials shall be removed daily and shall be placed in contractor furnished containers and shall be removed on a daily basis to an authorized dump off-Base as the project progresses.

Contractors shall ensure all light weight debris at the construction site is properly secured in waste receptacles so that it does not blow to another area or onto the airfield. Once the works are finished, the Contractor shall remove the containers.

18.3 Cleaning and Maintenance of Access Routes: The Contractor shall be solely responsible for any material dumped/spilled by trucks, vehicles and machinery or equipment on the access routes. Said material shall be immediately removed by the Contractor. The Contractor shall be responsible for assuring that all access routes shall be kept clean and clear at all times.

No amount of debris whatsoever will be tolerated on the access routes

18.4 Waste and Construction Debris: The Contractor, once the project work has been completed and prior to the Final Inspection, shall submit a certificate from the authorized dump

01 11 01 - 16 site to the Contracting Officer with the estimated amounts or waste and construction debris managed during the execution of the project. The delivery tickets must be previously submitted for verification to Construction Management during execution of the work.

18.5. Hazardous Material: Before transporting any type of hazardous material, the Contractor shall contact the Chief of Construction Management to coordinate handling and storage. The Contractor shall be responsible for complying with all applicable environmental rules and regulations concerning handling, transportation and storage of materials and/or dangerous waste.

18.6. Noise Control and Prevention: The Contractor shall comply with all applicable municipal and state regulations and all by laws and norms pertaining to noise control and prevention, applicable on or off Base. The Contractor shall take the required measures to prevent and control the noise in the vicinity of the construction area.

18.7. Dust Control and Prevention: The Contractor shall comply with all applicable municipal and state regulations and all by laws and norms pertaining to dust control and prevention, applicable on or off Base. The Contractor shall take the required measures to prevent and control the dust in the vicinity of the construction area.

18.8. Storm Water Pollution Prevention and Control: The Contractor shall comply with all applicable municipal and state regulations and all by laws and norms pertaining to prevention and control of the pollution of the storm water, applicable on or off Base. The Contractor shall take the required measures to prevent and control the pollution of the surface storm waters and ground waters of the base.

19. SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION: (See Solicitation/Contract FAR clause 52.236-21, Specifications and Drawings for Construction, Feb 1997).

19.1 Maintenance and Updating of As-Built Drawings and Specifications: The Contractor shall keep two sets of specifications and drawings, regular size, which shall show neatly and clearly marked in red all variations between the actual construction and the contract documents. The As-Built drawings shall be kept up-to-date at the work site at all times during the contract. Any revision must be marked and signed on the corresponding As-Built drawing block by the Contractor and Construction Management. All the revisions must be numbered and must be marked in red accompanied with the revision number. Moreover, the revision number must be indicated on the "Mark" column, the revision description on the "Description" column and the approval date on the "Date" column and must be signed by the representative of Construction Management on "Appr" column on the corresponding As-Built drawing block.

01 11 01 - 17

19.2 Availability and Review of As-Built Drawings: As-Builts shall be available for inspection by the Contracting Officer or his authorized representative. Upon completion of work, and prior to the Final Inspection, a complete set of As-Built drawings shall be submitted to the Contracting Officer for final review. A hard copy of the As-Built drawings will be submitted marked in red and signed by project inspection. The Contracting Officer shall provide comments and/or approval within the following two weeks from the submittal.

19.3 Submittal of As-Built drawings: After final review and once the As-Built drawings have been approved, the Contractor shall have two weeks to submit a complete set of As-Builts stamped with "AS-Built", with the numbered revisions, marked in red, described, dated and signed by project inspection and a CD with said “As-Built” drawings in AutoCAD format. The AutoCAD version shall be the same version used in the Base Design Section. Hard copies shall be A1 size. The name of the drawing files on the CD shall correspond to the drawing numbers of the hard copies. The CD, as well as the drawing block shall include the following information:

- Project Name and Number.

- Date.

- Contract Number.

- Contractor Name.

20. GUIDELINES FOR AS-BUILT SPATIAL DATA COLLECTION & SUBMITTAL:

The contractor shall submit the spatial data 15 calendar days after the acceptance of the works.

20.1 The contractor is responsible for accurately collecting all spatial data features as-built, as-constructed and as-installed. The required positional accuracy is +/- 2 cm.

20.2 The contractor is responsible for delivering the spatial data in ESRI shapefile or ESRI Geodatabase.

20.3 The contractor shall identify the classification, type, size, location, ID number, and any other necessary attributes, as specified by the Government, for all features.

20.4 The contractor is responsible for delivering the spatial data in a logical layering system according to the current version of Spatial Data Standard for Facilities Infrastructure and Environment (SDSFIE).

20.5 The contractor is responsible for delivering the spatial data in the Universal Transverse Mercator (UTM) coordinate system, World Geodetic System 1984 (WGS84) datum.

Morón AB is situated within UTM Zone 30 North.

20.6 The contractor will coordinate with the installation GeoBase Office to determine the current version being used for all software, data and data standards. The Government will

01 11 01 - 18 provide the contractor with data and information concerning all necessary and pertinent functions and principal features of the identified project including the installation's latest digital planimetric data.

20.7 All data deliverables shall be in a digital (electronic information) format and shall be delivered on CD-ROM or DVD-ROM. The media must have an external label listing the contractor's contact information, a short description of the contents, and a sequence number if there are multiple volumes.

20.7.1 A transmittal sheet in both hardcopy and digital format (*.dbf, *.xls, or ASCII comma-delimited format) must accompany the media containing the information included on the external labels, total number of volumes being delivered, and a list of file names and file descriptions on each volume. The transmittal sheet must also include instructions for reading, restoring, or transferring the files from the media, and certification that all delivery media is free of known computer viruses - including the name(s) of the virus scanning software and the date the virus scan was performed.

20.7.2 The following procedures must be performed before GIS data is placed on the delivery media:

1. Shapefile data shall include, as a minimum, the following files: the *.shp, the *.shx, the *.dbf, the *.prj and the *.xml or other metadata file.

2. Geodatabase data shall be returned in a Personal Geodatabase format compatible with the version of ArcGIS presently used by the GeoBase Office. All concomitant tables, domains, metadata, etc. shall be included in the Geodatabase.

3. Any ArcGIS Map Documents (i.e. *.mxd files) delivered shall be accompanied by all referenced data files, both spatial and tabular; and any associated images or other objects in the layout.

21 SITE INVESTIGATION AND CONDITIONS AFFECTING WORK: The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (See Solicitation/Contract FAR clause 52.236-3, Site Investigation and Conditions Affecting the Work, Apr 1984).

22. PERMITS AND RESPONSIBILITIES: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any National, regional, local and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons

01 11 01 - 19 or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .