Construction Cost Estimate Breakdown

View the file

Other files for this federal contract opportunity

Other files attached to Install Generator & ATS, Bldg #1301, newest first.
File Type Posted
FA5575-16-B-0007-0001_Amend.pdf PDF
FA5575-16-B-0007.pdf PDF
15-1011.pdf PDF
QUUG_15-1011_English_Specifications.pdf PDF
QUUG_15-1011_Especificaciones_Espaol_(de_PROJECTS_tal_cual).pdf PDF
15-1011_Schedule_of_Material_Submittals.xlsx XLSX spreadsheet
Synopsis_16B0007.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ktor

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
MORÓN AIR BASE, SPAIN
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
INSTALL GENERATOR & ATS, BLDG #1301
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 15-1011MORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
Interior Distribution System Modifications
Modificaciones del Sistema de Distribución Interior
1Demoler instalación existente de fuerza e iluminación
Demolish existing lighting and power installationJOB
2Receptacles NEMA 5-20R, boxes and accessories
Enchufes NEMA 5-20R, cajas y acc.Ea
3Surface Metal Raceway 50x150mm
Canaleta metálica de superficie 50x150mmLm
43/4" EMT including couplings & accessories
Conducto acero galv. 3/4", incluso manguitos y accesoriosLm
51 1/2" RMC including couplings & accessories
Conducto acero galv. 1 1/2", incluso manguitos y accesoriosLm
61" RMC including couplings & accessories
Conducto acero galv. 1", incluso manguitos y accesoriosLm
7Copper cable 1x2.5 mm2 H07V-K 450/750V
Cable de cobre 1x2.5 mm2 H07V-K 450/750VLm
8Copper cable 1x4 mm2 H07V-K 450/750V
Cable de cobre 1x4 mm2 H07V-K 450/750VLm
9Copper cable 1x6 mm2 RZ1-K (AS) 0.6/1 kV
Cable de cobre 1x6 mm2 RZ1-K (AS) 0.6/1 kVLm
10Lighting fixtures (Type A) 2xTL5 35W HFP
Luminaria estanca 2xTL5 35 W HFP (Tipo A)Ea
11Emergency lighting fixtures (Type A) 2xTL5 35W HFP
Luminaria estanca de emergencia 2xTL5 35 W HFP (Tipo A)Ea
12Nuevo panel eléctrico LDP
New LDP Electric PanelboardEa
13Puesta a tierra
Grounding SystemEa
Interior Distribution System Modifications Total
Total Interior Distribution System Modifications
Generator and Automatic Transfer Switch
Grupo electrógeno y Conmutador Automático
14Demoler generador, accesorios y transporte a vertedero
Demolish and dispose of generator and accessoriesJOB
15Grupo electrógeno 125 kW, cableado, conductos y acc.
Generator 125 kW, wiring, conduits & acc.Ea
16Conmutador automático, 4 polos, 600 A, cableado y acc.
4-Pole, 600 A,Automatic Transfer Switch, wiring and acc.Ea
17Seccionador de by-pass, cableado y acc.
By-pass/Isolation Switch, wiring and acc.Ea
18Copper cable 1x35 mm2 RZ1-K (AS) 0.6/1 kV
Cable de cobre 1x35 mm2 RZ1-K (AS) 0.6/1 kVLm
19Copper cable 1x95 mm2 RZ1-K (AS) 0.6/1 kV
Cable de cobre 1x95 mm2 RZ1-K (AS) 0.6/1 kVLm
20Weatherproof metal raceway 100x300mm, incl. coplings & acc.
Canal metal estanca 100x300mm, incluso acc. y conexionesLm
21Puesta a tierra
Grounding SystemEa
Generator and Automatic Transfer Switch Total
Total Grupo electrógeno y Conmutador Automático
WORK SUMMARY
RESUMEN TRABAJOS
Interior Distribution System Modifications
Modificaciones del Sistema de Distribución Interior
Generator and Automatic Transfer Switch
Grupo electrógeno y Conmutador Automático
GRAND TOTAL
GRAN TOTAL
`
OVERHEAD BREAKDOWNTOTAL MATERIAL COSTS

Project Superintendent TOTAL LABOR COSTS

QC Manager TOTAL OTHER DIRECT COSTS

Safety Manager TOTAL DIRECT COSTS

English Speaking Representative OVERHEAD (see breakdown)

Other Overhead Costs SUBTOTAL

TOTAL OVERHEAD BREAKDOWN EUROS PROFIT

TOTAL PROJECT EUROS

DATE: FIRM NAME:

TITLE: BY:

Page &P of &N