FA5575-16-B-0007-0001_Amend.pdf
PDF 51 KB Posted
- Attached to
- Install Generator & ATS, Bldg #1301 Federal contract opportunity
- Solicitation number
- FA5575-16-B-0007
About this file
Amendment to extend due date correct performance period and clarify warranty.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA5575-16-B-0007.pdf | ||
| QUUG_15-1011_Especificaciones_Espaol_(de_PROJECTS_tal_cual).pdf | ||
| 15-1011_Schedule_of_Material_Submittals.xlsx | XLSX spreadsheet | |
| 15-1011.pdf | ||
| QUUG_15-1011_English_Specifications.pdf | ||
| 15-1011_AF_3052_Ktor_OH_BREAKDOWN.xlsx | XLSX spreadsheet | |
| Synopsis_16B0007.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F3N7A06188A001 QUUG 15-1011
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to amend the bid due date to 22 August 2016 at 1030 and correct the performance period reference w ithin CLIN 0001 to read as 210 days after NTP. Final change to Warranty of Construction clause to amend standard 1 year w arranty to 2 years. This is also referenced in the CLIN.
All other items remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA5575-16-B-0007
X 9B. DATED (SEE ITEM 11)
20-Jul-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Aug-2016
CODE
496 ABS/LGC (FA5575)
APARTADO 221
41530 MORON
SEVILLA
FA5575 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA5575-16-B-0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 20-Aug-2016 10:30 AM to 22-Aug-2016 10:30 AM.
The required performance has changed from Project QUUG 10-1011, Install Generator & ATS, BLDG.
1301, Moron Air Base, SpainThe magnitude of this project is between $100,000 and $250,000 U.S. Dollars. This is furnished for the convenience of prospective contractors. The actual extent of work requirements will be governed by the specifications and drawings. Bids will be evaluated according to the criteria in Section M, Evaluation factors for award. A pre-proposal Conference / Site Visit will be held 10 August 2016, 11:45 hours local time, at the site location, bldg 1301. Refer to instruction 52.236-27 Alt.I for base access information. Bids must be received by the
Contracting Officer no later than 10:30 hours local time on 20 August 2016. Bids submitted by facsimile will NOT be accepted. IN ACCORDANCE WITH THE OFFICE OF DEFENSE COOPERATION POLICY DIRECTIVE
400-5 "(4) SPANISH MATERIAL, LABOR AND EQUIPMENT MUST BE USED IF PERMITTED BY THE
REQUIREMENTS OF THE CONTRACT SPECIFICATIONS."Notice to Offerors: The Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of bids. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs. to Project QUUG
10-1011, Install Generator & ATS, BLDG. 1301, Moron Air Base, SpainThe magnitude of this project is between
$100,000 and $250,000 U.S. Dollars. This is furnished for the convenience of prospective contractors. The actual extent of work requirements will be governed by the specifications and drawings. Bids will be evaluated according to the criteria in Section M, Evaluation factors for award. A pre-proposal Conference / Site Visit will be held 10
August 2016, 11:45 hours local time, at the site location, bldg 1301. Refer to instruction 52.236-27 Alt.I for base access information. Bids must be received by the Contracting Officer no later than 10:30 hours local time on 22
August 2016. Bids submitted by facsimile will NOT be accepted. IN ACCORDANCE WITH THE OFFICE OF
DEFENSE COOPERATION POLICY DIRECTIVE 400-5 "(4) SPANISH MATERIAL, LABOR AND
EQUIPMENT MUST BE USED IF PERMITTED BY THE REQUIREMENTS OF THE CONTRACT
SPECIFICATIONS."Notice to Offerors: The Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of bids. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs..
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from:
Install Generator & ATS bldg. 1301 Provide labor, management, supervision, material and equipment necessary to
Install Generator and ATS in accordance with project Quug 10-1011 Technical Provisions and Specifications.
Budget rate: $0.9049 Contract performance period 62 calendar days after receipt of Notice to Proceed.
To:
Install Generator & ATS bldg. 1301 Provide labor, management, supervision, material and equipment necessary to
Install Generator and ATS in accordance with project Quug 10-1011 Technical Provisions and Specifications.
Budget rate: $0.9049. 2-year warranty included. Contract performance period 210 calendar days after receipt of
Notice to Proceed..
SECTION I - CONTRACT CLAUSES
The following have been modified:
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 2 years from the date of final acceptance of the work. If the
Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 2 years from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the
Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The
Contractor's warranty with respect to work repaired or replaced will run for 2 years from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the
Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the
Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the
Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
(End of clause)
(End of Summary of Changes)