01-1018P2_Specs_English.pdf

PDF 338 KB Posted

Attached to
Repair Secondary Water Lines Phase 2
Solicitation number
FA5575-13-R-0004
Issued by

About this file

English Technical Specifications

View the file

Other files

File Type Posted
Attachment_4_-_PPI_Questionnaire.doc DOC document
Attachment_3_-_PPI_reference_list.doc DOC document
FA5575-13-R-0004 _RPL_Secondary_Water_Lines_Phase2.doc DOC document
01-1018P2_Specs_Spanish.pdf PDF
01-1018P2_Schedule_of_Material_Submittals.xlsx XLSX spreadsheet
01-1008P2_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED FOR DEPARTMENT OF THE

AIR FORCE

BY

VINNELL, BROWN & ROOT

ENGINEERING DESIGN SECTION

MORÓN AIR BASE

TECHNICAL PROVISIONS & SPECIFICATIONS FOR:

PROJECT QUUG 01-1018P2

RPR SECONDARY WATER LINES

PHASE 2

Prepared by: ___________________________________________________________________ Name: José María Zumárraga, CENDM Date: 26 Apr 13

Approved by:___________________________________________________________________ Name: Sydney DeRizzio, CENM Date: 26 Apr 13

TP-2

LIST OF SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Scope of Work, Drawings and Special Conditions 12 01 11 01 General Conditions 15

DIVISION 02 - EXISTING CONDITIONS

02 41 00 Demolition 2

DIVISION 03 - CONCRETE

03 30 00 Cast-In-Place Concrete 8

DIVISION 09 - FINISHES

09 90 00 Paints and Coatings 7

DIVISION 22 -- PLUMBING

22 00 00 Water Pipes and Accessories 9

DIVISION 23 - HEATING VENTILATING AND AIR

CONDITIONING

23 00 00 General Mechanical Provisions 5

DIVISION 31 - EARTHWORK

31 00 00 Earthwork 9

PROJECT QUUG 01-1018 P2

01 11 00-1

SECTION 01 11 00

SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS

1. GENERAL DESCRIPTION: Work shall be carried out by zones and shall include the following items:

ZONES I & II

a. Demolish existing underground pipe and accessories, as indicated in the drawings.

b. Furnish and install underground pipe P1 and accessories. Install underground shutoff valves V26, V27, valve boxes and accessories. Those pipe sections that are no longer part of the potable water distribution system shall be capped.

Include connection Ts, connections to handholes, valves and accessories.

ZONE A

a. Replace air relief valve ARV1 and accessories as indicated in the drawings.

Include thrust blocks, connection T from the main pipe, vertical pipe, air relief valve and accessories.

ZONE B

a. Replace air relief valves ARV2 and ARV3 and accessories as indicated in the drawings. Include thrust blocks, connection Ts from the main pipe, vertical pipes, air relief valves and accessories.

ZONE C

a. Replace air relief valve ARV4 and accessories as indicated in the drawings.

b. Furnish and install underground shutoff valves V1, V2, valve boxes and accessories.

ZONE D

01 11 00-2

a. Replace air relief valves ARV5, ARV6 and ARV7 and accessories as indicated in the drawings. Include thrust blocks, connection Ts from the main pipe, vertical pipes, air relief valves and accessories.

b. Replace flush type fire hydrants H27, H28, H29 and accessories as indicated in the drawings. The supply pipe from the main pipe and the gate valve are to remain. Repair the asphalt. Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance). Paint hydrant covers and frames.

c. Replace flush type fire hydrants H30, H31, H32 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipe from the main pipe, underground gate valves, valve boxes and accessories. Repair the concrete. Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance). Paint hydrant covers and frames.

ZONE E

a. Replace flush type fire hydrants H24, H25, H26, H35, H36, H37, H38 and accessories as indicated in the drawings. The supply pipe from the main pipe and the gate valve are to remain. Repair the asphalt or concrete. Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance). Paint hydrant covers and frames.

b. Replace flush type fire hydrants H33, H34 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipe from the main pipe, underground gate valves, valve boxes and accessories. Repair the concrete.

Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance).

Paint hydrant covers and frames.

ZONE F

a. Replace air relief valves ARV8, ARV9 and accessories as indicated in the

b. Replace flush type fire hydrants H20, H21, H23 and accessories as indicated in the drawings. The supply pipe from the main pipe and the gate valve are to remain. Repair the asphalt. Perform flow test in each installed hydrant (said

01 11 00-3 tests will be performed by the Government, but the Contractor will be present during the test performance). Paint hydrant covers and frames.

c. Replace flush type fire hydrants H105, H106, H107, H108, H109 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipe from the main pipe, underground gate valves, valve boxes and accessories. Repair the asphalt. Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance). Paint hydrant covers and frames.

d. Replace the water supply pipe to aboveground fire hydrant H39 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrant is to remain.

ZONE G

a. Replace air relief valves ARV10, ARV11 and accessories as indicated in the

b. Replace flush type fire hydrants H1, H2, H3, H9, H10 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipe from the main pipe, underground gate valves, valve boxes and accessories.

Perform flow test in each installed hydrant (said tests will be performed by the Government, but the Contractor will be present during the test performance).

Paint hydrant covers and frames.

c. Replace the water supply pipe to aboveground fire hydrant H7, H8, H11 and supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

ZONE H

a. Replace the water supply pipe to aboveground fire hydrant H47, H48 and

ZONE I

01 11 00-4

a. Replace the water supply pipe to aboveground fire hydrant H42, H43, H45, H46 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and

ZONE J

a. Replace the water supply pipe to aboveground fire hydrant H40 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrant is to remain.

b. Furnish and install underground shutoff valve V3, valve box and accessories.

ZONE K

a. Replace air relief valve ARV12 and accessories as indicated in the drawings.

b. Replace the water supply pipe to aboveground fire hydrant H112 and accessories. The hydrant is to remain.

ZONE L

a. Replace the water supply pipe to aboveground fire hydrant H119 and accessories. The hydrant is to remain.

ZONE M

a. Replace air relief valves ARV13, ARV14, ARV15 and accessories as indicated in the drawings. Include thrust blocks, connection Ts from the main pipe, vertical pipes, air relief valves and accessories.

b. Replace the water supply to aboveground fire hydrants H56, H57, H59, H60 and

01 11 00-5

ZONE N

a. Replace air relief valves ARV16, ARV17 and accessories as indicated in the

b. Replace the water supply pipe to aboveground fire hydrants H49, H50, H51, H54, H55, H58, H61, H62 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

ZONE O

a. Replace air relief valves ARV18, ARV19 and accessories as indicated in the

b. Replace the water supply pipe to aboveground fire hydrants H52, H53, H110 and accessories as indicated in the drawings. Include thrust blocks, connection

ZONE P

a. Replace air relief valves ARV20, ARV21 and accessories as indicated in the

b. Replace the water supply pipe to aboveground fire hydrants H111, H147, H1480

c. Furnish and install underground shutoff valve V4, valve box and accessories.

ZONE Q

a. Replace air relief valve ARV22 and accessories as indicated in the drawings.

01 11 00-6

b. Replace the water supply pipe to aboveground fire hydrants H81, H83, H84, H85 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

ZONE R

a. Replace air relief valve ARV23 and accessories as indicated in the drawings.

b. Replace the water supply pipe to aboveground fire hydrants H74, H75, H76, H77, H78, H79, H80 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

c. Furnish and install underground shutoff valves V5, V6, V7, V8, valve boxes and accessories.

ZONE S

a. Replace air relief valve ARV24 and accessories as indicated in the drawings.

b. Replace the water supply pipe to aboveground fire hydrants H65, H66, H67, H68, H69, H70, H71, H72, H73 and accessories as indicated in the drawings.

Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

c. Furnish and install underground shutoff valve V9, valve box and accessories.

d. Replace underground emergency shower supply pipe P2. Reinstall disconnector and accessories. Include connection T, valves and accessories.

ZONE T

a. Replace the water supply pipe to aboveground fire hydrants H82, H86, H87 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, 01 11 00-7

ZONE U

a. Replace the water supply pipe to aboveground fire hydrants H98, H99, H100

b. Furnish and install underground shutoff valve V10, valve box and accessories.

ZONE V

a. Replace air relief valve ARV25 and accessories as indicated in the drawings.

b. Replace the water supply pipe to aboveground fire hydrants H101, H102, H103, H104 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

ZONA W

a. Replace air relief valves ARV26, ARV27 and accessories as indicated in the

b. Replace the water supply pipe to aboveground fire hydrants H88, H89, H90, H91, H92, H93, H94, H95, H96, H97 and accessories as indicated in the drawings. Include thrust blocks, connection Ts, supply pipes from the main pipe, underground gate valves, valve boxes and accessories. The hydrants are to remain.

c. Furnish and install underground shutoff valves V11, V12, V13, V14, V15, V16, V17, V18, V19, V20, V21, V22, V23, V24, V25, valve boxes and accessories.

d. Replace underground pipe P3. Include connection T, connections to handhole and accessories.

ZONA X

01 11 00-8

a. Replace air relief valve ARV28 and accessories as indicated in the drawings.

ZONA Y

a. Replace air relief valve ARV29 and accessories as indicated in the drawings.

- GPS topographic study.

- Repair elements affected by project execution (pavement, topsoil, vegetation, sidewalks, etc.). The finish will be similar to the adjacent finish.

- General cleaning of the work site.

- Delivery of As-Built drawings.

All the above items do not limit or reduce the Contractor’s responsibility to perform all the work required by the project in order to provide a complete and operational installation.

2. PERFORMANCE PERIOD: The Contractor shall not initiate the work in a zone until all necessary materials corresponding to that zone have been received. The performance period proposed for the execution of this project, 360 calendar days, is for information purposes only and includes average inclement weather days.

2.1 It shall be the sole responsibility of the Contractor to ensure all required submittals are submitted to the Contracting Office for approval in a timely manner which shall not incur any delay in completion of the project. Materials or equipment requiring long lead time for procurement and delivery shall be included in the period of performance. Delay in delivery/procurement will not justify an extension of the period of performance.

2.2 The contractor shall provide a Construction Schedule and Work Plan.

2.2.1 The Construction Schedule shall show each task name and reference number with its duration days period, the start and finish dates, the predecessor task number, the resource to be used for accomplishing and a graphic showing these dates and the flow chart.

2.2.2 The Work Plan shall present the sequence of preconstruction and construction activities which are planned to take place. The plan shall contain the following:

01 11 00-9

a. The summary of the proposed methodology for performing various phases of the work.

b. Description of equipment and personnel to be used.

The Work Plan shall be prepared in coordination with the Safety Plan and the Quality Control Plan.

3. DRAWINGS ACCOMPANYING SPECIFICATION:

No. of Drawing Sheet Date Title R-684-01 1 of 20 26 Apr 13 Cover Sheet, Drawing Schedule R-684-02 2 of 20 26 Apr 13 Scope of Work R-684-03 3 of 20 26 Apr 13 Phases of The Work at the Airfield Area R-684-04 4 of 20 26 Apr 13 Pipe Demolition R-684-05 5 of 20 26 Apr 13 New Pipe Installation R-684-06 6 of 20 26 Apr 13 Working Zones R-684-07 7 of 20 26 Apr 13 Water System Repairs (Zones A, B, C) R-684-08 8 of 20 26 Apr 13 Water System Repairs (Zone D) R-684-09 9 of 20 26 Apr 13 Water System Repairs (Zone E) R-684-10 10 of 20 26 Apr 13 Water System Repairs (Zone F) R-684-11 11 of 20 26 Apr 13 Water System Repairs (Zones G) R-684-12 12 of 20 26 Apr 13 Water System Repairs (Zones H, I, J, K, L) R-684-13 13 of 20 26 Apr 13 Water System Repairs (Zones M, N) R-684-14 14 of 20 26 Apr 13 Water System Repairs (Zones O, P, Q) R-684-15 15 of 20 26 Apr 13 Water System Repairs (Zones R, S, T) R-684-16 16 of 20 26 Apr 13 Water System Repairs (Zones U, V, X, Y) R-684-17 17 of 20 26 Apr 13 Water System Repairs (Zone W) R-684-18 18 of 20 26 Apr 13 Details I R-684-19 19 of 20 26 Apr 13 Details II R-684-20 20 of 20 26 Apr 13 Details III

4. GOVERNMENT-FURNISHED MATERIAL (GFM) Not applicable.

5. EQUIPMENT, CONTROLS, AND MATERIAL OF THE UNITED STATES OF

AMERICA

5.1 Equipment List: The following listed equipment, controls, and materials shall be manufactured in the United States of America or in another country where the supplier is under license of the United States of America manufacturer and the product meets the same applicable specifications and/or standards. No substitutions will be allowed.

a. Flush type fire hydrants.

01 11 00-10

b. Gate valves for fire hydrants.

5.2 Excess: The Contractor shall furnish to the Contracting Officer, just prior to completion of this contract, a consolidated inventory of all excess supplies, materials, and equipment imported duty free for use under this contract. The Contractor shall either pay required duties on the excesses or re-export the excesses.

6. CERTIFICATION OF CLASSIFICATION: Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by “Registro Oficial de Licitadores y Empresas Clasificadas del Estado”covering the following groups, subgroups, and categories.

Group Subgroup Category

E 1 c

7. SPECIAL REQUIREMENTS: The following special conditions apply:

7.1 Phasing Work on the Airfield: The Contractor shall perform the works that may affect the Airfield area in phases as indicated below. One phase shall not commence until the previous phase is complete. The Contractor shall review and adhere to the procedures as established in Construction Plan in Phases which forms part of this contract and Instruction USAFEI 32-1007, Attachment 16 “Construction Phasing Plan and Operational Safety on the Airfield During Construction”. The Contractor shall abandon the work site as directed by the Control Tower personnel:

a. Phase 1: Replace air relief valve ARV3.

b. Phase 2: Replace flush type fire hydrants H28 and H29.

c. Phase 3: Replace air relief valves ARV5 and ARV6 and flush type fire hydrants

H26 and H27.

d. Phase 4: Replace flush type fire hydrant H25.

e. Phase 5: Replace flush type fire hydrants H23 and H24.

f. Phase 6: Replace flush type fire hydrant H21.

g. Phase 7: Replace air relief valve ARV8 and flush type fire hydrant H20.

h. Phase 8: Replace flush type fire hydrants H1, H2 and H3.

7.2 Vehicle Operations on the Aerodrome: The contractor shall receive the applicable traffic rules and regulations regarding driving on the aerodrome. The contractor shall abide by what is instructed in regard to the aerodrome and very specifically the signaling and lights of said vehicles.

7.3 Parallel Taxiway Unserviceable Areas: It is possible that the illumination of the part of the parallel taxiway which is out of service or closed be without power during the time it is out

01 11 00-11 of service. In this case work shall be coordinated with the airfield maintenance personnel.

The Contractor shall install unserviceable area lights that identify unserviceable areas from in-service areas every three (3) m, maximum. The minimum number of unserviceable lights shall be 4, unless the area is triangular, in which case it shall be 3.

The unserviceable area lighting shall be an omnidirectional fixed red light. The light shall have enough intensity to ensure conspicuity considering the intensity of the adjacent lights and the general level of illumination against which it would normally be viewed. In no case shall the intensity be less than 10 cd of red light. The unserviceable area light shall be installed on cones.

Unserviceable area lights shall be frangible.

Cones shall be made of PVC with a neoprene base, at least 0.5 m high, minimum and a weight of 2.6 kg. They shall be red, orange, yellow or any one of these colors combined with white. The cones shall have a tensile strain of 100 kg/cm². The stability of the cones shall be such that separated from its vertical 30°, it will not turn over or suffer deformation. It shall keep its balance without being displaced when subjected to winds of over 70 km/h. The strain at failure shall be of 400 %, minimum.

The Contractor shall remove the cones and the unserviceable area lights once the repair has been finished and accepted by the Contracting Office and when air traffic is resumed.

7.4 Existing Lights to be Protected: The contractor shall protect and mark the existing parallel taxiway lights at the work site.

7.5 Water Outages: The Contractor will notify the Contracting Officer or authorized representative about planned water outages 5 working days in advance. Before conducting a water outage, the Contractor will uncover the pipe sections to be replaced or sealed off and those elements where the new-existing connection will be performed. If the new pipe does not run along the same area as the one to be replaced, the new pipe, accessories and devices will be installed first, and, once tested and disinfected, they will be connected to the existing water system, in order to minimize the duration of water supply outages. Additionally, the Contractor will have all necessary tools available as well as the sub-base and fill material, so that, once the water outage starts, replacement of the existing installation and assembly of the new one lasts a minimal amount of time. Water outages shall not be longer than 8 hours. At the end of each work day, the drinking water supply will be reestablished. Work will be planned in such a way that the new installation will be performed at the same time for those buildings covered by this contract which are affected by the same water outage.

7.6 Service Initiation: The pipe sections no longer part of the drinking water supply system shall be sealed off and special attention shall be given to all the components currently receiving drinking water so that they are not left without supply once the new installation has

01 11 00-12 been performed.

7.7 Stockpiling Area of Demolished/Removed Material: The Contractor shall transport the material to an authorized dump. Should any of the Morón Air Base shops need all or part of any of the materials from the demolition operations, Construction Management shall notify the Contracting Office, and shall coordinate with the Base Chief of Operations and Maintenance the exact location to stockpile said material.

7.8 Stockpiling Area for Contractor Material and Contractor Offices: construction Management shall coordinate with the base Chief of Operations and Maintenance the exact location for Contractor offices and stockpiling.

7.9 Trenches, Excavations and Related Equipment: The Contractor shall protect and adequately signal the excavations and trenches. In the case that there are open excavations during the night, these shall be adequately illuminated or be completely covered prior to the end of the work day. No equipment shall remain at the work site after working hours. Watering of the piles of excavated material or fill shall be accomplished in order to preclude wind dispersing said material.

X Area: Prior to starting working in this area, the Contractor shall coordinate with the Construction Inspector to obtain the pertinent authorizations since it is a controlled area.

*** END OF SECTION ***

01 11 01 - 1

SECTION 01 11 01

GENERAL CONDITIONS

1. GENERAL: The work consists of furnishing all labor, materials, plant, transportation, equipment, and services to complete the project described in Section 01000, Scope of Work, Drawings and Special Conditions, in accordance with the drawings and specifications, complete and ready for use by means of a firm fixed price construction contract.

Measurements given in the drawings and specifications are given for reference use only. It is the Contractor’s responsibility to verify any and all of said measurements.

2. GENERAL DESCRIPTION: The work consists in, but is not limited to, executing the line items indicated in the scope of work. All line items indicated in the scope of work do not limit or reduce the Contractor’s responsibility to perform all work as required by the project in order to provide a complete and operable facility.

3. LOCATION: The work is located in Morón Air Base, Spain, as shown on the contract drawings.

4. DRAWINGS ACCOMPANYING SPECIFICATION: The drawings accompanying this specification are a part thereof. Drawings are the property of the Government, and shall not be used for any purpose other than that contemplated by the specification. The drawings included in this specification are similar to A1.

5. WARRANTY: For this contract the Contractor shall provide a two year standard commercial warranty associated with all scope of work items including materials and workmanship.

The warranty should cover all defects noticed and reported to the Contractor within two years after acceptance of the project. The Contractor shall repair or replace defective materials at the Contractor's expense within a reasonable time, and as approved by the Contracting Officer

6. BASE ACCESS:

6.1 Permits or Authorizations: The Contractor shall obtain all permits or authorizations to access Morón Air Base. Once the works have finalized, the Contractor will return the permits or authorizations.

6.2 Delays and Interruptions: Contractors are advised that due to security reasons, during the access/egress process of personnel and materials from the Morón Air Base delays are liable to occur. Additionally, the Contractor shall immediately interrupt work when required to do so if security warning/alarm situations occur.

01 11 01 - 2

7. WORK CLEARANCE REQUEST: The Contractor shall request AF Form 103 “BCE Work Clearance Request” in order to obtain all the information pertaining to the current status of general utilities. Requests shall be processed through the Contracting Officer or authorized representative, minimum of 7 duty days beforehand. The Contractor shall not perform any excavation works under any circumstances without an approved Work Clearance Request at the work site (hard copy). Work Clearance Request will only be processed once all materials and documentation necessary to commence work have been submitted and approved.

The Contractor shall be held responsible for any damage caused to general utilities indicated on the AF Form 103 and related drawings and shall be repaired at no additional cost to the Government of the United States.

8. BASE UTILITIES:

8.1 Use of Base Utilities: Base utilities are available to the Contactor at no additional expense to the Contractor. The following utilities will be available from the existing Base utility systems. Any additional utilities requirement besides what is listed below shall be supplied by the contractor at no cost to the Government.

a. Electricity 120/208 volts, 60 Hz.

b. Non-potable water.

Connection requests shall indicate the type of utility service required, type of connection and disconnection, utility service use and maximum duration. All connection and disconnection works for Base utilities shall be programmed during normal Base personnel operating hours. It shall be the Contractor’s responsibility to effect the connections and disconnections and shall reimburse costs incurred in the connection, disconnection, conversion, transportation of Base utility services to the work site, including providing the mechanisms that avoid water from flowing back into the system (backflow preventers) and furnishing and installing the necessary transformers. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. The Contractor shall notify the Contracting Officer or authorized representative 5 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required. Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

8.2 Base Utility Outages: Utility outage requests shall indicate the type of outage to be performed, the scope of work and the maximum duration. All utility outages shall be programmed during normal Base personnel operating hours. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. The Contractor shall notify the Contracting Officer or authorized representative 5 duty days prior to any connection, 01 11 01 - 3 disconnection or manipulation of the control system of the utility services required. Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.

9. HOT WORK: The Contractor shall submit for approval a written request to the Contracting Officer or authorized representative 5 days prior to any welding, oxyacetylene or plasma cutting work. Said request shall indicate welding procedures and fire prevention measures. All welding work performed during the project shall be carried out by qualified welders only. The copies of the welding certificates, issued by an approved agency, shall be kept in the construction inspector’s files.

10. VEHICULAR TRAFFIC, MACHINERY AND EQUIPMENT:

10.1 Traffic Control: All works which require vehicular or pedestrian traffic disruptions on the Base shall require an approved transit control plan. Said plan shall be approved at least 7 days prior to carrying out said disruption. Said plan shall include the date, duration, proposed alternative routes, signs, barriers, cones and/or flagmen. The Contractor shall establish alternate procedures should unforeseen circumstances take place. The responsibility of furnishing, erecting, maintaining and removing all signs, barriers, cones and flags shall be solely the Contractor’s. Once the work is completed, the Contractor shall remove the signaling elements such as barriers, cones and/or flags.

10.2 Access Routes: The Contractor shall submit a plan for the access routes which shall be approved by the Contracting Officer or authorized representative.

10.3 Trucks: Trucks loaded with loose material (air borne dust, construction debris or other objects that could fall from them), shall be duly covered. Said covers, such as tarps, shall be fastened over the load prior to accessing the adjacent roads.

11. PROGRESS SCHEDULE: (See solicitation/Contract FAR clause 52.236-15, Schedules for Construction Contracts, Apr 1984). The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval four copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

01 11 01 - 4

12. MOBILITY PLAN: The Contractor shall submit a mobility plan to the Contracting Officer or authorized representative for approval. Said plan shall propose the location and surface of the work site, offices and material staging and storage areas. The Contractor shall submit the plan 5 duty days prior to commencing work. The Contractor shall include in the mobility plan the proposed system to supply the required utility services required at each site.

12.1 Construction Site Fencing: Construction sites, offices, latrines, material staging and storage areas shall be fenced in by means of a two meter high fence to include gates and locks, unless otherwise approved the Government of the United States. The type of fencing, height and color shall be specified in accordance with the Contracting Officer or authorized representative’s criteria. Fences shall be screened with green opaque screening material to prevent visibility inside the fenced area. Fencing shall be completely secured at top and bottom to prevent access.

Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. The Contractor shall include in the Mobilization Plan photos, catalogs or samples of the screening material. The Contractor shall not install the fencing or screening materials until approval, in writing, has been granted from the Contracting Officer or authorized representative. The responsibility of providing, erecting, maintaining and removing the fencing shall be solely the Contractor’s. The Contractor shall replace or repair, within the following 24 hours or as determined by the Contracting Officer or authorized representative, all fence or screening sections which have been damaged or deteriorated. Once the works have been finalized, the Contractor shall remove the fencing.

12.2 Offices: Temporary prefabricated buildings required for administrative reasons (office space, conference room and break room) shall be in good conditions. Temporary prefabricated buildings requiring paint, repairs or are in bad conditions shall not be allowed at the site. Said temporary prefabricated buildings shall include on the outside a plaque, 0.5 x 0.5 meters maximum dimensions, indicating the name of the company and telephone number (s) of the person (s) designated as POC for the Contractor 24 hours a day. Once the works are finalized, the Contractor shall remove the temporary prefabricated buildings.

12.3 Latrines: Prefabricated temporary buildings required as latrines for personnel shall be in good conditions. The prefabricated temporary buildings requiring paint, repairs or are in bad conditions shall not be allowed on the work site. These facilities shall be kept in perfect using conditions and sanitized, shall be treated for insects and shall be emptied once a week and cleaned with a detergent suitable for sanitary use. The frequency of emptying and cleaning shall be adjusted according to needs. The facilities shall be located no less than 50 meters from the existing buildings on Base if they cannot be located near a sewage manhole. Once the works have been completed, the Contractor shall remove the temporary facilities and shall leave the area clean and sanitized.

12.4 Parking: The Contractor, their employees and subcontractors shall park all vehicles, 01 11 01 - 5 including heavy machinery, equipment or vehicles, in areas where they do not pose an obstruction in the corresponding work site. All possible efforts must be made so that the vehicles are not parked in an area where they will be clearly visible from the outside.

12.5 Material Storage: Storage containers will be in good conditions. The storage of materials at the work site shall be at the Contractor’s own risk. The use of private security guards at the work site shall require Spanish Air Force Security Forces approval. The Contractor shall not use the work site to store material previously approved by the Contracting Officer or authorized representative. Once the works have finished, the Contractor shall remove the excess stored material.

12.6 NOT USED.

13. QUALITY CONTROL PLAN: The Contractor shall submit comprehensive Quality Control Plan 5 duty days prior to commencing work. The plan shall contain at minimum the following:

1. Names and Qualifications for any proposed Quality Control Manager or

Inspectors.

2. Develop an Organization Chart that identifies the Reporting Responsibility the

Quality Control Inspectors, Quality Control Manager and the Project Manager.

3. Inspection Procedures. This should include types and frequencies of inspections and procedures for failed or unsatisfactory inspections.

4. Inspection Reporting. Submit recommended forms for all types of planned inspections with the Quality Control Plan for approval.

5 Identify all necessary inspections and submit a schedule with the frequency of inspections.

6 Copies of all performed inspection reporting forms, including Specific (HVAC, Plumbing, framing, Electrical, HVAC etc.,) are to be submitted to the Contracting Officer within 24 hrs. after performing each inspection.

7. List of planned ‘Hold Inspection Points’ with the estimated dates from the construction schedule.

8. Request for Information (RFI) Submit the proposed RFI Form and RFI Log Form to be used. This will be used to submit and track any RFI’s during construction.

9. Material Testing: Submit the name and qualifications for any Testing Agency or Laboratory planned for testing. All testing reports shall be submitted in a timely manner for review and approval. Should any test report fail, follow-on work is not to proceed until after the failure has been corrected. It is the responsibility of the QC Manager to ensure that all reports have been reviewed and the necessary action taken to resolve any failed testing.

01 11 01 - 6

10 A daily report of all actions performed during the contract period is required to be documented on a daily basis

a. The following should be included in the report, but is not all-inclusive.

1) The date of the inspection.

2) Comment on the weather conditions.

3) Inspection of equipment and materials and when received at the job-site.

4) Names of visitors to the site during the day.

5) Inspection of any deficiencies discovered during the day and corrective action taken.

6) Inspection and acceptance of subcontractor materials and workmanship.

7) Work being performed during the day and notation of inspection and acceptance.

8) Any field changes made by Civil Engineer inspector or deviations from original plans or specifications.

These daily reports are to be kept on the job-site and available for review at all times.

13.1 Acceptance of the Construction Quality Control (QC) Plan: Acceptance of the QC Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work.

13.2 The contractor is expected to know and adhere to the contract specifications and drawings. The Government inspector will conduct regular inspections to confirm compliance with the drawings & specifications.

13.3 Tests to be performed by the contractor are to be in accordance with the specifications and will be evaluated by the government inspector.

13.4 Maintenance of records required by the contract and specifications are the responsibility of the contractor.

13.5 Final inspection and acceptance will be conducted jointly with the inspector and a representative from the contracting office. All punch list items must be completed before final acceptance of the project.

14. WORK DAY:

01 11 01 - 7

14.1 Normal Work Hours: The Contractor shall perform all work during normal working hours unless a special authorization is issued by the Contracting Office representative to deviate from said work schedule. Normal working hours shall be from 0800 to 1700, from Monday to Friday, with the exception of holidays.

14.2 Work Outside Normal Hours: If the Contractor wishes to work outside the normal hours of operation, Saturdays, Sundays, or holidays, he shall submit an application to the Contracting Officer. The Contractor shall submit the request 5 duty days ahead of time as minimum.

15. CONSERVATION AND MAINTENANCE:

15.1 Conservation and Maintenance of the Existing Facilities: The contractor shall conserve and protect all existing facilities at the work site or adjacent to it which shall not to be removed or affected by the work required under this contract. The Contractor shall restore, at no additional cost to the Government of the United States of America, the facility affected during the execution of works to its original condition, before final acceptance of the project.

15.2 Conservation and Maintenance of the Existing Vegetation: The Contractor shall conserve and protect the existing vegetation (trees, shrubs, grass) on or adjacent to the work site, which shall not to be removed and which do not interfere with the work required under this contract. The contractor shall only remove trees or shrubs when specifically indicated in the drawings and specifications and shall avoid damaging the rest of vegetation. If any limbs or branches of trees are broken during contract performance due to the careless operation of equipment or the carelessness of the workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall cut the grass or vegetation in the work site so that it does not exceed 10 cm in height. The Contractor shall restore, at no additional cost to the Government of the United States of America to their original state all areas disturbed during construction to their original condition before final acceptance of works under this project.

16. CLEANING AND MAINTENANCE:

16.1 Housekeeping and Site Cleanup: The Contractor shall dispose of accumulated debris, waste materials and rubbish and shall keep the site in order. All rubbish and waste materials shall be removed daily and shall be placed in contractor furnished containers and shall be removed on a daily basis to an authorized dump off-Base as the project progresses.

Contractors shall ensure all light weight debris at the construction site is properly secured in waste receptacles so that it does not blow to another area or onto the airfield. Once the works are finished, the Contractor shall remove the containers.

16.2 Cleaning and Maintenance of Access Routes: The Contractor shall be solely

01 11 01 - 8 responsible for any material dumped/spilled by trucks, vehicles and machinery or equipment on the access routes. Said material shall be immediately removed by the Contractor. The Contractor shall be responsible for assuring that all access routes shall be kept clean and clear at all times.

No amount of debris whatsoever will be tolerated on the access routes

16.3 Waste and Construction Debris: The Contractor, once the project has been completed, shall submit a report to the Chief of Construction Management with the estimated amounts or waste and construction debris managed during the execution of the project.

17. HAZARDOUS MATERIAL: Before transporting any type of hazardous material, the Contractor shall contact the Chief of Construction Management to coordinate handling and storage. The Contractor shall be responsible for complying with all applicable environmental rules and regulations concerning handling, transportation and storage of materials and/or dangerous waste.

18. NOISE CONTROL: The Contractor shall comply with all applicable municipal and state regulations and all bylaws and norms pertaining to noise control, applicable on or off Base.

19. SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION: (See Solicitation/Contract FAR clause 52.236-21, Specifications and Drawings for Construction, Feb 1997).

19.1 Maintenance and Updating of As-Built Drawings and Specifications: The Contractor shall keep two sets of specifications and prints, regular size, on the site which shall show neatly and clearly marked in red all approved & not approved variations between the actual construction and the contract documents. The As-Built drawings shall be kept up-to-date at the work site at all times during the contract.

19.2 Availability and Review of As-Built Drawings: As-Builts shall be available for inspection by the Contracting Officer or his authorized representative. Upon completion of work, a complete set of As-Built drawings shall be submitted to the Contracting Officer for final review. A hard copy of the As-Built drawings will be submitted marked in red and signed by project inspection. The Contracting Officer shall provide comments and/or approval within the following two weeks from the submittal.

19.3 Submittal of As-Builts: After final review and once the As-Built drawings have been approved, the Contractor shall have two weeks to submit a complete set of As-Builts and a CD with Updated AutoCAD files, Version 2010, of said drawings. The name of the drawing files on the CD shall correspond to the drawing numbers of the hard copies. The CD shall be labeled as follows:

- Project Name and Number.

01 11 01 - 9

- Date.

- Contract Number.

- Contractor Name.

20. CONTRACTOR GENERAL GUIDELINES FOR AS-BUILT SPATIAL DATA

COLLECTION & SUBMITTAL:

20.1 The contractor is responsible for accurately collecting all spatial data* features as-built and as-installed. The required positional accuracy is +/- 2 cm.

20.2 The contractor is responsible for delivering the spatial data in a scalable vector format such as DXF, AutoCAD DWG, ESRI shapefile or ESRI Geodatabase.

20.3 The contractor shall identify the classification, type, size, location, ID number, and any other necessary attributes, as specified by the Government, for all features.

20.4 The contractor is responsible for delivering the spatial data in a logical layering system according to the current version of Spatial Data Standard for Facilities Infrastructure and Environment (SDSFIE). The layers and associated definitions are listed in Appendix A.

SDSFIE Feature Summary Listing.

20.5 The contractor is responsible for delivering the spatial data in the Universal Transverse Mercator (UTM) coordinate system Zone 30 North, World Geodetic System 1984 (WGS84) datum.

20.6 The contractor will coordinate with the installation GeoBase Office to determine the current version being used for all software, data and data standards. The Government will provide the contractor with data and information concerning all necessary and pertinent functions and principal features of the identified project including the installation's latest digital planimetric data.

20.7 Deliverables include, but are not limited to:

• Site plans.

• Topographic surveys or studies.

• Boundary or Cadastral surveys.

• Utility (water, sewer, power, storm, etc.) designs, plans, surveys and studies.

• Pavement, Grading, or Excavation plans.

• Soil/Geology studies or surveys.

• Environmental assessments, surveys, studies, or plans.

• Historical or Archaeological surveys, studies, or plans.

01 11 01 - 10

All data deliverables shall include a schedule and shall be in a digital (electronic information) format and shall be delivered on CD-ROM or DVD-ROM. The media must have an external label listing the contractor's contact information, a short description of the contents, and a sequence number if there are multiple volumes.

20.7.1 A transmittal sheet in both hardcopy and digital format (a *.dbf, *.xls, or ASCII comma-delimited format) must accompany the media containing the information included on the external labels, total number of volumes being delivered, and a list of file names and file descriptions on each volume. The transmittal sheet must also include instructions for reading, restoring, or transferring the files from the media, and certification that all delivery media is free of known computer viruses - including the name(s) of the virus scanning software and the date the virus scan was performed.

20.7.2 The following procedures must be performed before CADD data is placed on the delivery media:

1. Include all files, both graphic and non-graphic, required for the project.

Ensure all files are in the same directory, and that references to those files do not include device or directory specifications.

2. Ensure all reference (external reference) files are attached and without device or directory (path) specifications.

3. Remove all extraneous graphics and text outside the project border area, and set the active parameters to a standard setting (or the setting contained in the seed or prototype file).

4. Include any standards sheets (abbreviations, symbols libraries, font libraries, color tables, pen tables, plot configuration files, user command files, etc.) necessary for a complete project.

20.7.3 The following procedures must be performed before GIS data is placed on the delivery media:

1. Shapefile data shall include, as a minimum, the following files: the *.shp, the *.shx, the *.dbf, the *.prj and the *.xml or other metadata file.

2. Geodatabase data shall be returned in a Personal Geodatabase format compatible with the version of ArcGIS presently used by the GeoBase Office. All concomitant tables, domains, metadata, etc. shall be included in the Geodatabase.

01 11 01 - 11

3. Any ArcGIS Map Documents (i.e. *.mxd files) delivered shall be accompanied by all referenced data files, both spatial and tabular; and any associated images or other objects in the layout.

*Spatial data, also known as geospatial data or geographic information, means any data with a direct or indirect reference to a specific location or geographical area.

21 SITE INVESTIGATION AND CONDITIONS AFFECTING WORK: The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to… see Solicitation/Contract FAR clause 52.236-3, Site Investigation and Conditions Affecting the Work, Apr 1984.

22. PERMITS AND RESPONSIBILITIES: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occurs as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract. (See Solicitation/Contract FAR clause 52.236-7, Permits and responsibilities, Nov 1991)

23. CONTRACTOR AND SUBCONTRACTOR PERSONNEL:

23.1 Superintendent: The Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. The superintendent must be able to effectively answer technical questions related to the project and effectively manage the work.

23.2 English Speaking Representative:

23.2.1 At all times during the execution of any work, the Contractor shall have a representative present on site capable of explaining the work operations and receiving instructions in English. The Contracting Officer or authorized representative shall have the right to determine, without appeal of such decision, whether the proposed representative has the linguistic capability or not, in which case, said representative shall be replaced immediately by another previously approved by the Contracting Officer or his authorized representative.

23.3 Personnel Listing: The Contractor shall submit a list of key personnel and subcontractor personnel to include position, personal addresses and phone number for emergency

01 11 01 - 12 contact purposes. As changes occur and additional information becomes available, the Contractor shall correct the information contained in the previously submitted lists.

23.4 Personnel Transit On-Base: Personnel working on the Base shall keep to the work site and shall transit using the approved access routes. The personnel shall keep off restricted areas unless the pertinent authorization is issued.

24. PUBLIC RELEASE OF INFORMATION: The public release of information o photographs concerning any aspect of the materials or services related to this bid, purchase order or other documents resulting thereof without prior written…