Questions and Answers Amendment 01.pdf

PDF 80 KB Posted

Attached to
Fiber Cable Duct Survey Federal contract opportunity
Solicitation number
FA557020Q0010
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

This document provides questions and answers regarding solicitation number FA557020Q0010 for fiber cable duct survey services at RAF Molesworth, UK. The contractor will be required to update the Cyberspace Infrastructure Planning System with outside plant telecommunications infrastructure information through GPS surveys of manholes, handholes, pedestals and building entries to tag cables and enter enclosure attributes and cable data. The contractor must demonstrate the accuracy and completeness of updated information in the system through progress reports and drawings. The response deadline was extended to March 28, 2020. The government will not provide equipment, cable tags or funding for defense base act insurance. No page limits apply to the technical or price submissions, which may be combined provided pricing is separate. Past performance will not be evaluated.

View the file

Other files for this federal contract opportunity

Other files attached to Fiber Cable Duct Survey, newest first.
File Type Posted
Combo - FA557020Q0010.pdf PDF
Questions and Answers Amendment 02.pdf PDF
DRAFT Combo - FA557020Q0010.pdf PDF
Attachment 1 PWS for CVC Survey.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contracting responses in blue

Questions regarding solicitation FA557020Q0010, Fiber Cable Duct Survey

Q&A Round 1

1. Question: Are there page limits to either Technical or Price? There are no page limits to either volume.

2. Question: Are Technical and Price to be submitted as separate files? The files may be combined as long as pricing is not intermingled with technical information.

3. Question: Will relevant past performance be considered in any way? Past performance is not an evaluation factor.

4. Question: Will the government be providing the cable tags or will the contractor be responsible for providing those? (I believe the answer is they will not be providing this equipment per 3.1

Government‐Furnished Property (GFP) The Government will not be providing cable tags.

5. Question: Will the government be providing the required equipment such as(Trucks, pumps, safety equipment, underground locators, etc.) or will be contractor be responsible for providing this equipment? (I believe the answer is they will not be providing this equipment per 3.1

Government‐Furnished Property (GFP) The Government will not be providing equipment.

6. Question: Will contractor DBA Insurance be funded as an ODC? The Government does not believe the Defense Base Act (DBA) is applicable to this requirement because it does not meet the definition of a public‐work contract, as defined in FAR 28.305 (a). No construction, alteration, removal, or repair is incidental to this requirement, nor is this requirement in connection with national defense, or war activities.

7. Question: Would the Government consider extending the due date since answers to these questions will determine how accurate our quote will be? Yes, the response deadline has been extended to 28 March 2020 at 1400 GMT