ATTACHMENT 4 (23 March 2015) 1 OF 8
PROJECT PROJECT TITLE SOLICITATION/CONTRACT NO.
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
1 SUMMARY OF WORK
01 11 00-1.12 As-built drawings 4
7 days after final inspection
2 01 11 00-1.20 Notification before starting on-site work 4 21 days prior to start of work
3 01 11 00-1.29 DD Form 1354 4 5 days after final inspection
4 ENVIRONMENTAL PROTECTION
01 56 00-3.02A1 Environmental Protection Plan 4
14 days before work starts
5 01 56 00-3.02B Submittals required during site work 4 45
6 01 56 00-3.02C Submittals required after completion of work 4 after completion of site work
7 DEMOLITION
02 41 00-1.5 Existing conditions 4 7 days prior to start of work
8 02 41 00-1.5 Demolition plan 4 7 days prior to start of work
9 02 41 00-1.5 Receipts 4 after completion of submittals
REMOVAL/CONTROL AND DISPOSAL OF
PAINT WITH LEAD 02 82 33.13 20-1.4
Sampling results
4 7 days after test
11 02 82 33.13 20-1.4 Qualifications of CP 4 45
12 02 82 33.13 20-1.4 Lead waste management plan 4 45
AF FORM 66, SEP 86 COPY 1 - CONTRACT FILES
ATTACHMENT 4 (23 March 2015) 2 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
13 02 82 33.13 20-1.4 Completed and signed hazardous waste manifest 4 after completion of submittals
14 CAST-IN-PLACE CONCRETE
03 30 00-1.3a1 Materials for curing materials 4 45
15 03 30 00-1.3a2 Joint sealants 4 45
16 03 30 00-1.3b1 Joint filler 4 45
17 30 00-1.3c1 Concrete mix design 4 7 days after test
18 30 00-1.3c2 Aggregates 4 7 days after test
19 30 00-1.3c3 Compressive strength tests 4 7 days after test
20 30 00-1.3d1 Form removal schedule 4 45
21 30 00-1.3d2 Reinforcing steel 4 45
PAINTS AND COATINGS
09 90 00-1.2a1 Manufacturer's Technical Data Sheets
4 45
23 09 90 00-1.2b1 Color 4 45
24 09 90 00-1.2c1 Manufacturer's material safety data sheets 4 45
ATTACHMENT 4 (23 March 2015) 3 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
25 INTERIOR DISTRIBUTION SYSTEM
26 20 00-1.3 Door motor control panels 4 after completion of site work
26 26 20 00-1.3 Door driving system 4 after completion of site work
27 26 20 00-1.3 Revolving lamp (beacon) 4 after completion of site work
28 26 20 00-1.3 Alarm bell 4 after completion of site work
29 26 20 00-1.3 Wires and cables 4 45
30 26 20 00-1.3 Conduit and fittings 4 45
31 26 20 00-1.3 Circuit breakers 4 45
32 26 20 00-1.3 Enclosed circuit breakers 4 45
33 26 20 00-1.3 600-volt wiring test 4 7 days after test
34 EARTHWORK
31 00 00-1.4 Testing 4 7 days after test
35 31 00 00-1.4 Borrow site testing 4 7 days after test
36 SUBBASES FOR FLEXIBLE PAVING
32 11 16-1.2 Sampling and testing 4 7 days after test
ATTACHMENT 4 (23 March 2015) 4 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
37 32 11 16-1.2 Field density tests 4 7 days after test
AGGREGATE AND/OR GRADED-CRUSHED
AGGREGATE BASE COURSE 32 11 23-1.3
Sampling and testing
4 7 days after test
39 32 11 23-1.3 Field density tests 4 7 days after test
40 BITUMINOUS TACK AND PRIME COATS 32
12 10-1.2 Sampling and testing 4 7 days after test
41 HOT-MIX ASPHALT (HMA) FOR ROADS 32
12 16-1.2 Mix design 4 45
42 32 12 16-1.2 Aggregates 4 7 days after test
43 CONCRETE SIDEWALKS AND CURBS AND
GUTTERS 32 16 13-1.3 Concrete 4 45
44 32 16 13-1.3 Field quality control 4 7 days after test
45 PAVEMENT MARKINGS
32 17 23.00 20-1.2 Paints for airfields 4 45
46 32 17 23.00 20-1.2 Paints for roads and streets 4 45
47 32 17 23.00 20-1.2 Paints for airfields 4 7 days after test
48 32 17 23.00 20-1.2 Paints for roads and streets 4 7 days after test
ATTACHMENT 4 (23 March 2015) 5 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
49 32 17 23.00 20-1.2 Paints for airfields 4 45
50 32 17 23.00 20-1.2 Paints for roads and streets 4 45
51 SODDING
32 92 23-1.3 Fertilizer 4 45
52 32 92 23-1.3 Topsoil composition tests 4 7 days after test
53 32 92 23-1.3 Nursery or sod farm certification 4 45
54 STORM DRAINAGE UTILITIES
33 40 00-1.2 Placing pipe 4 45
55 33 40 00-1.2 Pipeline testing 4 45
56 33 40 00-1.2 Frame and cover for gratings 4 45
57 Drawing S-503 Cyclo gear box 4 45
58 Drawing S-503 Cyclo gear box 4 7 days after final inspection
59 Plummer block 4 45
60 Plummer block 4 7 days after final inspection
ATTACHMENT 4 (23 March 2015) 6 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
61 Driving shaft and parallel 4 45
62 Motor base 4 45
63 Drive sprocket 4 45
64 Explosion proof limit switch 4 45
65 Drawing S-504 Safety cover 4 45
66 Latch and hinge 4 45
67 Drawing S-505 Roller 4 45
68 Neoprene plate 4 45
69 Sub and main roller 4 45
70 Sub and main roller 4 7 daysafter final inspection
71 Drawing S-506 Guide Roller: Roller 4 45
72 Bearing assembly 4 45
ATTACHMENT 4 (23 March 2015) 7 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
73 Grease nipple 4 45
74 Guide roller 4 45
75 Guide roller 4 7 daysafter final inspection
76 Rack and Pin: Rack pin 4 45
77 Rack 4 45
78 Pulley: Sheave 4 45
79 Pulley: Sheave 4 7 daysafter final inspection
80 Pin 4 45
81 Wire 4 45
82 Pulley 4 45
83 Drawing S-507 Guide plate 4 45
84 Scraper 4 45
ATTACHMENT 4 (23 March 2015) 8 OF 8
SCHEDULE OF MATERIAL SUBMITTALS
LXEZ 13-1059 REPAIR 14 HAS DOORS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R
TI
FI
C
A
TI
O N
O F
C O
M P
LI
A
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
LE
S
C O
LO
R
S E
LE
C
TI
O
N
M A
N U
FA
C
TU
R
E R
'S R
E C
O M
M E
N D
A
TI
O N
C A
TA
LO
G D
A
TA
O P
E R
A
TI
N G
IN
S
TR
U
C
TI
O N
S
O P
E R
A
TI
O N
A L
A N
D M
A
IN
TE
N
A N
C E
D A
T
TE
S
T R
E P
O R
TS
O
TH
E R
S
REQUIRED
SUBMISSION
DATE
(CALENDAR DAYS
AFTER N.T.P.)
DATE
RECEIVED
IN
CONTRAC
T ING
DATE TO
CIVIL
ENGINEER
ING
RETURN
SUSPENSE
DATE
FOLLOW-UP DATE CONTRACTOR NOTIFIED
CONTRAC
TOR
RESUBMIT
TAL
FINAL APPROVAL REMARKS
APPROVED DISAPPROVED
85 Jack block 4 45
86 Support block 4 45
87 Hydraulic jack 4 45
88 Hydraulic jack 4 7 daysafter final inspection
89 Portable battery pump 4 45
90 Portable battery pump 4 7 daysafter final inspection
91 Jack Up instruction 4 after final inspection
92 Drawing S-508 Rubber stopper 4 45
File details come from the government source that posted it. Updated .