A-14_Exhibit_A B_20Aug13_Revision_-_Final_8Oct13.pdf
PDF 74 KB Posted
- Attached to
- Natural Gas at Yokota Air Base
- Solicitation number
- FA5209-13-R-0032
About this file
Exhibit A - Revised by Amend 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C-6_Signed_Page.pdf | ||
| C-6_Contract.pdf | ||
| A-14_Amend_3_Exhibit_A.pdf | ||
| A-14_Amend_3_FA520913R0032.pdf | ||
| A-14_Amend_3_Atch_1_-_SOW.pdf | ||
| A-16_Q A_11Oct13 _Atch1_Fuel_Use_L_Plant.xlsx | XLSX spreadsheet | |
| A-16_Q A_11Oct13 _Atch2_Fuel_Use_K_Plant.xlsx | XLSX spreadsheet | |
| A-16_Q A_11Oct13 _Atch3_Fuel_Use_H_Plant.xlsx | XLSX spreadsheet | |
| A-16_Q A_11Oct13 _Atch4_Fuel_Use_F_Plant.xlsx | XLSX spreadsheet | |
| A-16_Q A_11Oct13 _Fuel_oil_hourly_usage_data_Final.docx | DOCX document | |
| A-14_Amend_2 _FA5209-13-R-0032-0002.doc | DOC document | |
| A-14_FA5209-13-R-0032_RFP_Amendment_0001.pdf | ||
| A-14_Atch_1_-_SOW_Revised27Sep13.pdf | ||
| A-14_Atch_2_-_Est_Consump_Amend_Revised_27Sep13.pdf | ||
| A-16_Pre-proposal_Conf_Minutes.pdf | ||
| A-14_Atch_2_-_Estimated_Consumption.pdf | ||
| A-14_FA5209-13-R-0032_RFP.pdf | ||
| Government_Policy_Letter.pdf | ||
| A-14_Exhibit_A.pdf | ||
| A-14_Notice_to_Offeror.pdf | ||
| A-14_Atch_1_-_SOW.pdf | ||
| A-14_Atch_3_MAP_for_Gas_Line_Connection_Points_26Jun13.pdf | ||
| A-14_Exhibit_B.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment No. 0002 to Solicitation No. FA5209-13-R-0032 Exhibit A
Item No. Supply Point A001 Supply Point 1 (West)
A001AA Testing Period 19,000 ¥ /m3 (1) ¥ Minimum Order
Amount Minimum Order Maximum Order
2,900,000 ~ 4,000,000 ¥ /m3 ¥ ~ (2) ¥
A001AC
Penalty Charge for Yearly Load Factor (3) ¥
A002 Supply Point 2 (East)
A002AA Testing Period 35,400 ¥ /m3 (4) ¥ Minimum Order
Amount Minimum Order Maximum Order
4,500,000 ~ 6,100,000 ¥ /m3 ¥ ~ (5) ¥
A002AC
Penalty Charge for Yearly Load Factor (6) ¥
A003 Supply Point 3 (Main 1)
A003AA Testing Period 46,200 ¥ /m3 (7) ¥ Minimum Order
Amount Minimum Order Maximum Order
10,100,000 ~ 13,800,000 ¥ /m3 ¥ ~ (8) ¥
A003AC
Penalty Charge for Yearly Load Factor (9) ¥
A004 Supply Point 4 (Main 2) A004AA Testing Period ¥ N/A /m3 ¥ N/A
Minimum Order Amount Minimum Order Maximum Order
57,000 ~ 62,000 ¥ /m3 ¥ ~ (10) ¥
A004AC
Penalty Charge for Yearly Load Factor (11) ¥
**Normal Operation: Period: 5 years after Testing Period is completed.
***Unit price shall be the third decimal place.
**** 9-digit Provisional Value for Aug 13 released on 27 Sep 13 in the Trade Statistics of Japan published by the Ministry of Finance shall be used for Gas Resource Base.
Penalty Accessed If… Actual Yearly Load Factor < ________%
Estimate Consumption Amount (m3) Unit Price
Pricing Schedule
Estimate Amount
Maximum Order AmountA001AB Normal Operation
*Testing Period: Period: From after installation of gas lines for approx four (4) weeks for tests conducted during the winter season, nine (9) weeks in other than winter season
Maximum Order Amount
Penalty Accessed If… Actual Yearly Load Factor < ________%
N/A
(e) Total Maximum Estimate of CLIN A001 through to A004 = Sum of (a) through (d)
(f) Grand Total Maximum Estimate for Normal Operation for 5 Years = (e) x 5 (years)
A004AB Normal Operation
(a) Total Maximum Estimate of CLIN A001 = (1) +(2) + (3)
(b) Total Maximum Estimate of CLIN A002 = (4) +(5) + (6)
(c) Total Maximum Estimate of CLIN A003 = (7) +(8) + (9)
(d) Total Maximum Estimate of CLIN A004 = (10) +(11)
Maximum Order Amount
Penalty Accessed If… Actual Yearly Load Factor < ________%
Maximum Order Amount
Penalty Accessed If… Actual Yearly Load Factor < ________%
A002AB Normal Operation
A003AB Normal Operation
Exhibit A Pricing Schedule