FA520510R0007_Attachment_4_Historical_Data.pdf
PDF 102 KB Posted
- Attached to
- Roads and Pavements IDIQ Contract Federal contract opportunity
- Solicitation number
- FA5205-10-R-0007
About this file
Attachment 4 Historical Data RFP No. FA5205-10-R-0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA5205-10-R-0007-0001.pdf | ||
| Q A_FA5205-10-R-0007.pdf | ||
| Pre-proposal_Conference_Minutes_10R0007.pdf | ||
| FA520510R0007_Attachment_2_Drawings.pdf | ||
| FA520510R0007_Attachment_3_Schedule_of_Contractors_Submittal.pdf | ||
| FA520510R0007_Attachment_1_Specifications.pdf | ||
| FA520510R0007__SF1442.pdf | ||
| (Identifiable Offeror s Name)_10R0007_Exhibit A-C.xls | XLS spreadsheet | |
| No_Bid_Form.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 4 RFP No. FA5205-10-R-0007
Historical Data of
Roads/Pavements IDIQ Contract
Summary of Roads/Pavements IDIQ Contract, FA5205-06-D-0003
Period: 27 Sep 06 thru 26 Apr 10
26 Apr 10
Period Number of TO Amount (Yen) Amount ($)
Basic Period 13 ¥374,103,040 $3,298,608.03
(27 Sep 06 thru 26 Oct 07)
13 Months
See page 2 for task order breakdown
Option Year One 4 ¥241,485,104 $2,103,930.14
(27 Oct 07 thru 26 Oct 08)
12 Months
See page 3 for task order breakdown
Option Year Two 12 ¥440,053,082 $3,878,662.10
(27 Oct 08 thru 26 Apr 10)
18 Months
See page 4 for task order breakdown
Total 29 ¥1,055,641,226 $9,281,200.27
Yearly Average Number of Task Order (TO): 9.67
Yearly Average of TO Amount: ¥351,880,409
Average Amount per Task Order ¥36,401,422
Construction Category Number of TO Amount (Yen) Amount ($)
Repair / Maintenance Work 23 ¥947,818,814 $8,305,687.42
(EEIC 521, 522 and 524)
Minor Construction Work 6 ¥107,822,412 $975,512.85
(EEIC 529)
HISTORICAL DATA
OF
ROADS/PAVEMENTS IDIQ
List of Task Orders, Roads/Pavements IDIQ Contract, FA5205-06-D-0003
Basic Period: 27 Sep 06 thru 26 Oct 07 (13 Months)
Performance TO# EEIC Description Award(Yen) Award ($) Award Date Period (CD)
5000 524 Rpr Falcon Drive, Main Base, Ph 5 ¥2,728,690 $23,727.74 28Sep06 232
5001 524 Rpr Golf Course Hole 10&11 Cart Path ¥21,570,234 $190,381.59 31Aug07 287
5002 524 Repair Freedom Drive, Flag Circle ¥39,628,020 $349,761.87 31Aug07 408
5003 524 Repair Falcon Drive, Phase 2 ¥35,123,000 $310,000.00 06Sep07 388
5004 524 Repair Falcon Drive, Phase 3 ¥21,980,200 $194,000.00 10Sep07 388
5005 529 Improve Main Gate Road Ph1 ¥40,935,290 $361,300.00 26Sep07 442
5006 524 Repair Falcon Drive, Phase 1 ¥36,482,600 $322,000.00 27Sep07 366
5007 529 Cnst Helicopter Pad (AF Funding) ¥5,665,000 $50,000.00 27Sep07 90
5008 529 Cnst Helicopter Pad (Army Funding) ¥4,418,330 $38,996.73 27Sep07 90
5009 524 Repair Freedom Drive, Flag Circle Ph2 ¥41,822,480 $369,130.45 28Sep07 381
5010 522 Improve Main Gate Road Ph2 ¥20,620,600 $182,000.00 28Sep07 442
5011 522/9 Improve Main Gate Road Ph3 ¥44,073,700 $389,000.00 30Sep07 442
5012 524 Improve Main Gate Road Ph4 ¥34,556,500 $305,000.00 30Sep07 442
Option Year One Period: 27 Oct 07 thru 26 Oct 08 (12 Months)
5013 524 Repair Reese Road, Phase 4 ¥70,228,180 $611,860.45 21Feb08 260
5014 524 Repair B/358 Base Chapel Parking Lot ¥36,728,050 $319,991.79 26Feb08 234
5015 524 Add/Alter R. I. Bong Training Ctr Pkg Lot ¥77,221,740 $672,791.59 27Mar08 240
5016 524 Rpr Shenandoah Drive B358 to B296 ¥57,310,990 $499,319.91 26Sep08 421
Option Year Two Period: 27 Oct 07 thru 26 Apr 10 (18 Months)
(As of 10 Feb 10)
5017 529 Pave Road/Parking, SMDC, B1751 ¥15,622,330 $136,677.47 16Mar09 130
5018 529 CNST Golf Cart Path Ph1 ¥16,149,210 $169,991.68 03Sep09 276
5019 524 Rpr Post Office Parking Lot ¥57,131,350 $499,833.77 08Sep09 352
5020 524 Repair Reese Road, Phase 7 ¥22,858,920 $199,989.33 08Sep09 273
5021 524 Rpr Housing Road, Various Loc, Ph1 ¥56,880,800 $497,641.75 11Sep09 304
5022 524 Rpr Housing Road, Various Loc, Ph2 ¥57,150,180 $499,998.51 11Sep09 371
5023 522 Add/Alter Walking Path, Rpr Perimeter Fence ¥60,572,880 $529,943.21 18Sep09 380
5024 522 Rpr AC Paved Running Path ¥25,124,600 $219,811.43 23Sep09 330
5025 522 Rpr Asphalt Pavements, Independence Dr ¥14,286,200 $124,987.86 16Sep09 273
5026 524 Rpr Falcon Drive North, Munitions ECP ¥52,571,570 $459,940.93 19Sep09 304
5030 522 Repair Falcon Drive, Phase 4 ¥27,431,230 $239,991.79 25Sep09 302
5031 529 Expand Parking Lot, MXG B1387 ¥10,513,900 $91,984.56 25Sep09 311
Single Task Order Amount
Highest Lowest Average
¥77,221,740 ¥2,728,690 ¥26,892,665
Task Orders performed simultaneously
Peak Average
Number of TOs 13 8.29 / 12 months
Amount of active TOs ¥545,466,424 ¥222,483,454
Period Mar 08 thru May 08 Sep 06 thru Feb 10 (42 months)
(As of 10 Feb 10)
Task Order
Construction Period
Performance Bonds Requirement
Average ¥222,483,454
Peak ¥545,466,424