Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MFR_for_FBO.pdf | ||
| Perm_Party_Dorm_Q&As.pdf | ||
| Solicitation_Amendment_-_FA500419BA0080004.pdf | ||
| Solicitation_Amendment_FA500419BA0080004_SF_30.pdf | ||
| Solicitation_Amendment_FA500419BA0080003_SF30.pdf | ||
| JA-6_Wage_Determination(14_June_2019).pdf | ||
| Solicitation_Amendment_FA500419BA0080002_SF30.pdf | ||
| FA500419BA0080001_SF_30.pdf | ||
| FA500419BA0080001.pdf | ||
| JA-4_Submittal_Register.pdf | ||
| JA-6_Wage_Determination_19_Apr_19.pdf | ||
| JA-2_Drawings_pt1.pdf | ||
| JA-7_Bid_Schedule.pdf | ||
| JA-3_Drawings_pt2.pdf | ||
| Solicitation_-_FA500419BA008.pdf | ||
| JA-1_Synopsis_of_Work.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RENOVATE PERMANENT PARTY DORM
BLDG. 2262
FTQW 08-1036
SPECIFICATIONS
Final (100%) Design
November 2018
Prepared for:
Department of the Air Force: Pacific Air Forces
354th Contracting Squadron 2310 Central Avenue, Suite 3 (B2258)
Eielson AFB, AK 99702-1887
Prepared by:
1028 Aurora Drive
Fairbanks, Alaska 99709 T: 907.452.1414
AECC605
17175FB
This page intentionally left blank.
FA5004-17-C-C004 Renovate Permanent Party Dorm FTQW081036 Eielson AFB, Alaska
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00.10 EXPLANATIONS: DRAWINGS AND SPECIFICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 60 00 MATERIAL AND EQUIPMENT
01 73 29 CUTTING AND PATCHING
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
02 83 13.00 20 LEAD IN CONSTRUCTION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
PROJECT TABLE OF CONTENTS Page 1 Final (100%) Design FOR CONSTRUCTION
08 11 16 ALUMINUM DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 39 53 BLAST RESISTANT DOORS (OVAL ARCH MAGAZINES)
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 72 00 WALLCOVERINGS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 11 - EQUIPMENT
11 31 13 ELECTRIC KITCHEN EQUIPMENT
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 24 13 ROLLER WINDOW SHADES
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 21 23 HYDRONIC PUMPS
23 57 10.00 10 FORCED HOT WATER HEATING SYSTEMS USING WATER AND STEAM
HEAT EXCHANGERS
DIVISION 25 - INTEGRATED AUTOMATION
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END
AND INTEGRATION
PROJECT TABLE OF CONTENTS Page 2
DIVISION 26 - ELECTRICAL
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 51 00 LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
FA5004-17-C-C004 Renovat e Per manent Par t y Dor m FTQW081036 Ei el son Ai r For ce Base
SECTI ON 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1. 1 WORK COVERED BY CONTRACT DOCUMENTS
1. 1. 1 Pr oj ect Descr i pt i on
The wor k i ncl udes r enovat i on and r epai r of Bui l di ng 2262 and i nci dent al r el at ed wor k.
1. 1. 2 Location
The wor k i s l ocat ed at Bui l di ng 2262, Ei el son AFB, appr oxi mat el y as i ndi cat ed. The exact l ocat i on wi l l be shown by t he Cont r act i ng Of f i cer .
1. 2 NOTI FI CATI ON OF COMMENCEMENT OF WORK
Pr i or t o excavat i on on- si t e, t he cont r act or shal l coor di nat e wi t h al l of t he or gani zat i ons l i s t ed on AF For m 103, Base Ci v i l Engi neer i ng Wor k Cl ear ance Request . The compl et ed f or m shal l be submi t t ed t o t he Cont r act i ng Of f i cer and a copy shal l be kept at t he wor k s i t e at al l t i mes.
The Cont r act or shal l not i f y t he Cont r act i ng Of f i cer t hat wor k wi l l begi n a mi ni mum of seven ( 7) days pr i or t o commenci ng wor k.
1. 3 GOVERNMENT OCCUPANCY
The Gover nment wi l l occupy pr emi ses dur i ng ent i r e per i od of const r uct i on f or t he conduct of i t s nor mal oper at i ons.
The Cont r act or shal l per f or m t he wor k under t hi s cont r act i n such a manner t hat adj acent Ai r For ce act i v i t i es may pr oceed unhi nder ed. Pr i or t o begi nni ng on- si t e wor k t he Cont r act or shal l meet wi t h t he Cont r act i ng Of f i cer and t echni cal r epr esent at i ves f r om Base Ci v i l Engi neer i ng t o schedul e t he wor k of t hi s cont r act .
Cooper at e wi t h Gover nment t o mi ni mi ze conf l i c t and t o f aci l i t at e i t s oper at i ons. I n case of conf l i c t accept Cont r act i ng Of f i cer ' s di r ect i on as f i nal and adj ust use of pr emi ses accor di ngl y.
Mai nt ai n I BC compl yi ng access t o and t hr ough cor r i dor s, st ai r ways, and bui l di ng exi t s at al l t i mes.
Coor di nat e Wor k i n and use of pr emi ses wi t h t he Gover nment .
1. 4 EXI STI NG WORK
I n addi t i on t o FAR 52. 236- 9 Pr ot ect i on of Exi st i ng Veget at i on, St r uct ur es, Equi pment , Ut i l i t i es, and I mpr ovement s:
a. Remove or al t er exi st i ng wor k i n such a manner as t o pr event i nj ur y or damage t o any por t i ons of t he exi st i ng wor k whi ch r emai n.
b. Repai r or r epl ace por t i ons of exi st i ng wor k whi ch have been al t er ed
SECTI ON 01 11 00 Page 1
Ei el son Ai r For ce Base dur i ng const r uct i on oper at i ons t o mat ch exi st i ng or adj oi ni ng wor k, as appr oved by t he Cont r act i ng Of f i cer . At t he compl et i on of oper at i ons, exi st i ng wor k must be i n a condi t i on equal t o or bet t er t han t hat whi ch exi st ed bef or e new wor k st ar t ed.
1. 5 LOCATI ON OF UNDERGROUND UTI LI TI ES
Obt ai n di ggi ng per mi t s pr i or t o st ar t of excavat i on, and compl y wi t h I nst al l at i on r equi r ement s f or l ocat i ng and mar ki ng under gr ound ut i l i t i es. [ Cont act l ocal ut i l i t y l ocat i ng ser vi ce a mi ni mum of 48 hour s pr i or t o excavat i ng, t o mar k ut i l i t i es, and wi t hi n suf f i c i ent t i me r equi r ed i f wor k occur s on a Monday or af t er a Hol i day. Ver i f y exi st i ng ut i l i t y l ocat i ons i ndi cat ed on cont r act dr awi ngs, wi t hi n ar ea of wor k. Ref er ence Sect i on 01 57 19 TEMPORARY ENVI RONMENTAL CONTROLS f or di ggi ng per mi t r equi r ement s.
I dent i f y and mar k al l ot her ut i l i t i es not managed and l ocat ed by t he l ocal ut i l i t y compani es. Scan t he const r uct i on s i t e wi t h Gr ound Penet r at i ng Radar ( GPR) , el ect r omagnet i c, or soni c equi pment , and mar k t he sur f ace of t he gr ound, or paved sur f ace wher e exi st i ng under gr ound ut i l i t i es ar e di scover ed. Ver i f y t he el evat i ons of exi st i ng pi pi ng, ut i l i t i es, and any t ype of under gr ound or encased obst r uct i on not i ndi cat ed, or speci f i ed t o be r emoved, t hat i s i ndi cat ed or di scover ed dur i ng scanni ng, i n l ocat i ons t o be t r aver sed by pi pi ng, duct s, and ot her wor k t o be conduct ed or i nst al l ed. Ver i f y el evat i ons bef or e i nst al l i ng new wor k c l oser t han near est manhol e or ot her st r uct ur e at whi ch an adj ust ment i n gr ade can be made.
[] PART 2 PRODUCTS
Not used.
PART 3 EXECUTI ON
Not used.
- - End of Sect i on - -
SECTI ON 01 11 00 Page 2
Ei el son AFB, Al aska
SECTI ON 01 14 00
WORK RESTRI CTI ONS
PART 1 GENERAL
1. 1 SUBMITTALS
Submi t t he f ol l owi ng i n accor dance wi t h Sect i on 01 33 00 SUBMI TTAL
PROCEDURES:
1. 2 SPECI AL SCHEDULI NG REQUI REMENTS
a. Per mi ssi on t o i nt er r upt any Act i v i t y r oads, r ai l r oads, or ut i l i t y ser vi ce must be r equest ed i n wr i t i ng a mi ni mum of 15 cal endar days pr i or t o t he desi r ed dat e of i nt er r upt i on.
1. 3 CONTRACTOR ACCESS AND USE OF PREMI SES
1. 3. 1 Act i v i t y Regul at i ons
Ensur e t hat Cont r act or per sonnel empl oyed on t he Act i v i t y become f ami l i ar wi t h and obey Act i v i t y r egul at i ons i ncl udi ng saf et y, f i r e, t r af f i c and secur i t y r egul at i ons. Keep wi t hi n t he l i mi t s of t he wor k and avenues of i ngr ess and egr ess. Wear har d hat s i n desi gnat ed ar eas. Do not ent er any r est r i c t ed ar eas unl ess r equi r ed t o do so and unt i l c l ear ed f or such ent r y. Mar k Cont r act or equi pment f or i dent i f i cat i on.
1. 3. 1. 1 No Smoki ng Pol i cy
Smoki ng i s pr ohi bi t ed wi t hi n and out s i de of al l bui l di ngs on i nst al l at i on, except i n desi gnat ed smoki ng ar eas. Thi s appl i es t o exi st i ng bui l di ngs, bui l di ngs under const r uct i on and bui l di ngs under r enovat i on. Di scar di ng t obacco mat er i al s ot her t han i nt o desi gnat ed t obacco r ecept acl es i s consi der ed l i t t er i ng and i s subj ect t o f i nes. The Cont r act i ng Of f i cer wi l l i dent i f y desi gnat ed smoki ng ar eas.
1. 3. 2 Wor ki ng Hour s
Regul ar wor ki ng hour s must consi st of an 8 1/ 2 hour per i od est abl i shed by t he Cont r act i ng Of f i cer , bet ween 7 a. m. and 4: 30 p. m. , Monday t hr ough Fr i day, excl udi ng Gover nment hol i days.
1. 3. 3 Wor k Out si de Regul ar Hour s
Wor k out s i de r egul ar wor ki ng hour s r equi r es Cont r act i ng Of f i cer appr oval .
Make appl i cat i on 15 cal endar days pr i or t o such wor k t o al l ow ar r angement s t o be made by t he Gover nment f or i nspect i ng t he wor k i n pr ogr ess, gi v i ng t he speci f i c dat es, hour s, l ocat i on, t ype of wor k t o be per f or med, cont r act number and pr oj ect t i t l e. Based on t he j ust i f i cat i on pr ovi ded, t he Cont r act i ng Of f i cer may appr ove wor k out s i de r egul ar hour s. Dur i ng per i ods of dar kness, t he di f f er ent par t s of t he wor k must be l i ght ed i n a manner appr oved by t he Cont r act i ng Of f i cer .
SECTI ON 01 14 00 Page 1
1. 3. 4 Ut i l i t y Cut over s and I nt er r upt i ons
a. Make ut i l i t y cut over s and i nt er r upt i ons af t er nor mal wor ki ng hour s or on Sat ur days, Sundays, and Gover nment hol i days. Conf or m t o pr ocedur es r equi r ed par agr aph WORK OUTSI DE REGULAR HOURS.
b. Ensur e t hat new ut i l i t y l i nes ar e compl et e, except f or t he connect i on, bef or e i nt er r upt i ng exi st i ng ser v i ce.
c. I nt er r upt i on t o wat er , sani t ar y sewer , st or m sewer , t el ephone ser vi ce, el ect r i c ser vi ce, ai r condi t i oni ng, heat i ng, f i r e al ar m, and compr essed ai r ar e consi der ed ut i l i t y cut over s pur suant t o t he par agr aph WORK
OUTSI DE REGULAR HOURS.
d. Oper at i on of St at i on Ut i l i t i es: The Cont r act or must not oper at e nor di st ur b t he set t i ng of cont r ol devi ces i n t he st at i on ut i l i t i es syst em, i ncl udi ng wat er , sewer , el ect r i cal , and st eam ser v i ces. The Gover nment wi l l oper at e t he cont r ol devi ces as r equi r ed f or nor mal conduct of t he wor k. The Cont r act or must not i f y t he Cont r act i ng Of f i cer gi v i ng r easonabl e advance not i ce when such oper at i on i s r equi r ed.
1. 4 ACCESS TO CONTROLLED AREAS
The Cont r act or shal l compl y wi t h al l Ei el son AFB secur i t y and access t o cont r ol l ed ar ea pr ocedur es and r equi r ement s when and i f necessar y access i s absol ut el y necessar y. I ni t i al pr ocedur es and r equi r ement s wi l l be pr ovi ded t o t he Cont r act or at t he Pr e- Const r uct i on Conf er ence.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTI ON
Not Used
- - End of Sect i on - -
SECTI ON 01 14 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
04/18
PART 1 GENERAL
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
SD-04 Samples
Color Boards; G
1.2 COLOR BOARDS FOR AIR FORCE PROJECTS
Submit two sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board.
If more space is needed, more than one board per set may be submitted.
Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 300 DPI minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on
SECTION 01 30 00 Page 1 the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
1.5 PRECONSTRUCTION
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 30 00 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
3.2 PROJECT SCHEDULE
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contract Clauses will dictate the appropriate level of detail.
3.2.2 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.2.3 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
SECTION 01 32 01.00 10 Page 1
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Long procurement activities.
d. Submission and approval of O & M manuals.
e. Submission and approval of as-built drawings.
f. Submission and approval of DD1354 data and installed equipment lists.
g. Submission and approval of testing and air balance (TAB).
h. Submission of TAB specialist design review report.
i. Submission and approval of fire protection specialist.
j. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
k. Air and water balancing.
l. Building commissioning - Functional Performance Testing.
m. Controls testing plan submission.
n. Controls testing.
o. Performance Verification testing.
p. Other systems testing, if required.
q. Contractor's pre-final inspection.
r. Correction of punch list from Contractor's pre-final inspection.
s. Government's pre-final inspection.
t. Correction of punch list from Government's pre-final inspection.
u. Final inspection.
3.2.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
SECTION 01 32 01.00 10 Page 2
3.2.5 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.2.5.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.2.5.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.2.5.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.2.5.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.2.5.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.2.6 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
SECTION 01 32 01.00 10 Page 3
3.2.7 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.2.8 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.2.9 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.2.10 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.2.11 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.2.12 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.2.13 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence
SECTION 01 32 01.00 10 Page 4 progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.2.14 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.2.15 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.2.16 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4 SUBMISSION REQUIREMENTS
Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.4.1 Data
Provide the project schedule and all subsequent schedules in the format of the scheduling software (e.g. .xer) and in PDF format. Each schedule must have a unique file name and use project specific settings.
3.5 WEEKLY PROGRESS MEETINGS
Progress will be discussed at the weekly CQC Coordination/Production meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly meeting, address the status of RFIs, RFPs and Submittals.
SECTION 01 32 01.00 10 Page 5
3.6 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule for reasons other than those that are excusable within the terms of the contract, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.6.1 Artificially Improving Progress
Artificially improving progress by means such as, but not limited to, revising the schedule logic, modifying or adding constraints, shortening activity durations, or changing calendars in the project schedule is prohibited. Indicate assumptions made and the basis for any logic, constraint, duration and calendar changes used in the creation of the recovery plan. Any additional resources, manpower, or daily and weekly work hour changes proposed in the recovery plan must be evident at the work site and documented in the daily report along with the Schedule Narrative Report.
3.6.2 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
3.6.3 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
-- End of Section --
SECTION 01 32 01.00 10 Page 6
SECTION 01 32 16.00 20
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
02/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule; G
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause FAR 52.236-15 Schedules for Construction Contracts, except as modified in this contract.
The acceptance of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled.
] 1.3.2 Schedule Submittals and Procedures
Submit Bar Chart Schedules and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
SECTION 01 32 16.00 20 Page 1
1.4 SCHEDULE PROGRESS REPORTS
Update the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work.
Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
1.5 3-WEEK LOOK AHEAD SCHEDULE
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.
Key the work plans to activity numbers and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule and reviewed during the weekly CQC Coordination or Production Meeting. Deliver the 3-Week Look Ahead Schedule to the Contracting Officer in PDF file format.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 32 16.00 20 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
04/18
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to commencing with the start of work
List of proposed products
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
SECTION 01 33 00 Page 1
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS) concerning impedances, SECTION 01 33 00 Page 2 hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.1.2 Approving Authority
Office or designated person authorized to approve submittal.
1.1.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation.
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
SECTION 01 33 00 Page 3
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
1.4 PREPARATION
1.4.1 Transmittal Form
Transmittal form shall be Air Force Form 3000
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. In addition to the electronic submittal, provide three hard copies of the submittals. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/ .
Provide hard copies of submittals when requested by the Contracting Officer. Up to two additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.
SECTION 01 33 00 Page 4
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.6 SUBMITTAL REGISTER
Maintain submittal register as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.6.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
1.6.2 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each
SECTION 01 33 00 Page 5 submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.6.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.6.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.7 VARIATIONS
Variations from contract requirements require Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.7.1 Considering Variations
Discussion with Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.7.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
SECTION 01 33 00 Page 6
1.7.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.7.4 Review Schedule Extension
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.8 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. An additional 10 calendar days will be allowed and shown on the register for review and approval of submittals for refrigeration and HVAC control systems.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.9 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, SECTION 01 33 00 Page 7 stamp and date submittals. One copy of the submittal will be retained by the Contracting Officer and two copies of the submittal will be returned to the Contractor.
1.9.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.10 DISAPPROVED OR REJECTED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.11 APPROVED/ACCEPTED SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction…