This document contains a submittal schedule for a federal construction project to install backup generators. Key details include a requirement to submit construction schedules, health and safety plans, load power studies, and design drawings by dates ranging from 15 to 150 days after notice to proceed. The design drawings must include floor plans, elevations, sections, schedules and details for a walk-in weather tight enclosure and foundation plans. Submittals such as concrete mix designs, test results, generator enclosure details, and building one-line diagrams are also required. The related federal contract opportunity is soliciting offers to install backup generators in accordance with the attached statement of work. The project price is estimated between $500,000 to $1,000,000, and the opportunity is set aside for small businesses. A site visit will be held on October 14, 2021.

View the file

Other files for this federal contract opportunity

Other files attached to INSTALL BACKUP GENERATOR FOR LAB EQUIP B986, newest first.
File Type Posted
Questions and Answers.pdf PDF
Conformed Solicitation - FA500022R00010003.pdf PDF
Amendment FA500022R00010003 SF 30.pdf PDF
Amendment FA500022R00010002 SF 30.pdf PDF
Amendment FA500022R00010001 SF 30.pdf PDF
Drawings.pdf PDF
Specifications.pdf PDF
Statement of Work.pdf PDF
General Specifications.pdf PDF
Wage Determination 30 Jul 2021.pdf PDF
Solicitation - FA500022R0001.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
HJZH 21-1409INSTALL BACKUP GENERATOR FOR LAB EQUIP B986
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERProvide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALNOTES
GENERAL
1Project Specific Form 66XNTP + 15
2Construction ScheduleXNTP + 15
3Contractor's Health, Safety, and Environment PlanXNTP + 15
4Contractor's QA/QC PlanXNTP + 15
5Load Power Study SOW 3.4.4XNTP + 90
6Copy of Engineering License(s) Of Person Or Consultancy Responsible For DesignXDesign
DESIGN
7All submissions to be provided electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include:XNTP + 90 (100%)
8Floor Plan, Elevations, Sections, Schedules, and DetailsXNTP + 90For Walk-In Weather Tight Enclosure
9Foundation Structural Plans and DetailsXXNTP + 90For Walk-In Weather Tight Enclosure
10Trenching DetailXNTP + 90
11Quality Assurance Identified In SECTION 26 32 14.00 10XXNTP + 45
12SOUND LIMITATIONS SECTION 26 32 14.00 10XXXNTP + 90
13SD-06 Test Reports & all Submittals SECTION 26 36 00.00 10XXNTP + 90
14All SD submittals from SD-2 to SD-10 SubmittalsXXXXXXXXXXXNTP + 150
ARCHITECTURAL
15Fuel Resistive Resinous Flooring, 3-Coat SystemXXXNTP + 45
16CanopiesXXNTP + 45
STRUCTURAL
17Concrete/Reinforcing Steel DrawingsXNTP + 90Design and Stamped Required
18Concrete Mix DesignXNTP + 90
19Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion JointsXNTP + 90
20Concrete Field Test ResultsXWITHIN 7 DAYS OF TEST
21Anchor Bolt ICC ReportXXNTP + 90
22Slump Test Results & Concrete Truck Tickets (per truck)XWITHIN 7 DAYS OF TEST
2328-Day Concrete Compressive Strength TestXWITHIN 7 DAYS OF TEST
ELECTRICAL
24Generator EnclosureXXXXXNTP + 45
25Cables (Electrical, Communications)XNTP + 45
26ATS Switch 4 Pole Closed TransitionXXXXNTP + 45
27Grounding Test Resistance to Earth Test New RodXXXNTP + 45
28Panels Breakers , ConduitsX
29Grounding Rods, Saftey Marking Warning TapeXXNTP + 45
30Generator sizing calculations from commercially generator sizing softwareXXNTP + 45
31Generator Enclosure LocationXNTP + 45
32Building One line DiagramXXXXNTP + 45
33Generator Factory Test ResultXXXXXXXNTP + 45
34Generator Final Test ProcedureXXXNTP + 200
35Generator Commissioning Test Result by 3rd PartyXXXXNTP + 350
CLOSEOUT
36O&M Generator & ATS & Training Class with DVDXXXXXXXXXXXInstall + 4
37DD1354XBefore Acceptance
38As Builts (electronic in AutoCAD )XFinal + 7

&L&"Arial,Bold"&6AF FORM 66, OCT 99 &"Arial,Regular"Previous Edition Will Be Used