This document contains a submittal schedule for a federal construction project to install backup generators. Key details include a requirement to submit construction schedules, health and safety plans, load power studies, and design drawings by dates ranging from 15 to 150 days after notice to proceed. The design drawings must include floor plans, elevations, sections, schedules and details for a walk-in weather tight enclosure and foundation plans. Submittals such as concrete mix designs, test results, generator enclosure details, and building one-line diagrams are also required. The related federal contract opportunity is soliciting offers to install backup generators in accordance with the attached statement of work. The project price is estimated between $500,000 to $1,000,000, and the opportunity is set aside for small businesses. A site visit will be held on October 14, 2021.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Conformed Solicitation - FA500022R00010003.pdf | ||
| Amendment FA500022R00010003 SF 30.pdf | ||
| Amendment FA500022R00010002 SF 30.pdf | ||
| Amendment FA500022R00010001 SF 30.pdf | ||
| Drawings.pdf | ||
| Specifications.pdf | ||
| Statement of Work.pdf | ||
| General Specifications.pdf | ||
| Wage Determination 30 Jul 2021.pdf | ||
| Solicitation - FA500022R0001.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| HJZH 21-1409 | INSTALL BACKUP GENERATOR FOR LAB EQUIP B986 | |||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | NOTES |
| GENERAL | ||||||||||||||||||||||
| 1 | Project Specific Form 66 | X | NTP + 15 | |||||||||||||||||||
| 2 | Construction Schedule | X | NTP + 15 | |||||||||||||||||||
| 3 | Contractor's Health, Safety, and Environment Plan | X | NTP + 15 | |||||||||||||||||||
| 4 | Contractor's QA/QC Plan | X | NTP + 15 | |||||||||||||||||||
| 5 | Load Power Study SOW 3.4.4 | X | NTP + 90 | |||||||||||||||||||
| 6 | Copy of Engineering License(s) Of Person Or Consultancy Responsible For Design | X | Design | |||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| 7 | All submissions to be provided electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include: | X | NTP + 90 (100%) | |||||||||||||||||||
| 8 | Floor Plan, Elevations, Sections, Schedules, and Details | X | NTP + 90 | For Walk-In Weather Tight Enclosure | ||||||||||||||||||
| 9 | Foundation Structural Plans and Details | X | X | NTP + 90 | For Walk-In Weather Tight Enclosure | |||||||||||||||||
| 10 | Trenching Detail | X | NTP + 90 | |||||||||||||||||||
| 11 | Quality Assurance Identified In SECTION 26 32 14.00 10 | X | X | NTP + 45 | ||||||||||||||||||
| 12 | SOUND LIMITATIONS SECTION 26 32 14.00 10 | X | X | X | NTP + 90 | |||||||||||||||||
| 13 | SD-06 Test Reports & all Submittals SECTION 26 36 00.00 10 | X | X | NTP + 90 | ||||||||||||||||||
| 14 | All SD submittals from SD-2 to SD-10 Submittals | X | X | X | X | X | X | X | X | X | X | X | NTP + 150 | |||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| 15 | Fuel Resistive Resinous Flooring, 3-Coat System | X | X | X | NTP + 45 | |||||||||||||||||
| 16 | Canopies | X | X | NTP + 45 | ||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| 17 | Concrete/Reinforcing Steel Drawings | X | NTP + 90 | Design and Stamped Required | ||||||||||||||||||
| 18 | Concrete Mix Design | X | NTP + 90 | |||||||||||||||||||
| 19 | Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | X | NTP + 90 | |||||||||||||||||||
| 20 | Concrete Field Test Results | X | WITHIN 7 DAYS OF TEST | |||||||||||||||||||
| 21 | Anchor Bolt ICC Report | X | X | NTP + 90 | ||||||||||||||||||
| 22 | Slump Test Results & Concrete Truck Tickets (per truck) | X | WITHIN 7 DAYS OF TEST | |||||||||||||||||||
| 23 | 28-Day Concrete Compressive Strength Test | X | WITHIN 7 DAYS OF TEST | |||||||||||||||||||
| ELECTRICAL | ||||||||||||||||||||||
| 24 | Generator Enclosure | X | X | X | X | X | NTP + 45 | |||||||||||||||
| 25 | Cables (Electrical, Communications) | X | NTP + 45 | |||||||||||||||||||
| 26 | ATS Switch 4 Pole Closed Transition | X | X | X | X | NTP + 45 | ||||||||||||||||
| 27 | Grounding Test Resistance to Earth Test New Rod | X | X | X | NTP + 45 | |||||||||||||||||
| 28 | Panels Breakers , Conduits | X | ||||||||||||||||||||
| 29 | Grounding Rods, Saftey Marking Warning Tape | X | X | NTP + 45 | ||||||||||||||||||
| 30 | Generator sizing calculations from commercially generator sizing software | X | X | NTP + 45 | ||||||||||||||||||
| 31 | Generator Enclosure Location | X | NTP + 45 | |||||||||||||||||||
| 32 | Building One line Diagram | X | X | X | X | NTP + 45 | ||||||||||||||||
| 33 | Generator Factory Test Result | X | X | X | X | X | X | X | NTP + 45 | |||||||||||||
| 34 | Generator Final Test Procedure | X | X | X | NTP + 200 | |||||||||||||||||
| 35 | Generator Commissioning Test Result by 3rd Party | X | X | X | X | NTP + 350 | ||||||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| 36 | O&M Generator & ATS & Training Class with DVD | X | X | X | X | X | X | X | X | X | X | X | Install + 4 | |||||||||
| 37 | DD1354 | X | Before Acceptance | |||||||||||||||||||
| 38 | As Builts (electronic in AutoCAD ) | X | Final + 7 |
&L&"Arial,Bold"&6AF FORM 66, OCT 99 &"Arial,Regular"Previous Edition Will Be Used