Questions_Regarding_ECU.docx
DOCX document 14 KB Posted
- Attached to
- ECU's Federal contract opportunity
- Solicitation number
- FA5000-19-Q-0010
About this file
Please see correct Q&A attached
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA5000-19-Q-0010-U00009_-_Combined_Synopsis-Solicitation.pdf | ||
| FA5000-19-Q-0010-U00009_-_Attachment_1_Pricing_Schedule.pdf | ||
| FA5000-19-Q-0010-U00009_-_Amendment_Purpose-Description.pdf | ||
| FA5000-19-Q-0010_-_Questions_and_Answers_Jan_19.pdf | ||
| Attachment_1_Pricing_Schedule_V2.docx | DOCX document | |
| RFQ_-_Amendment_7.docx | DOCX document | |
| Questions_Regarding_ECU.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| Attachment_1_Pricing_Schedule.docx | DOCX document | |
| Questions_Regarding_ECU.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| Attachment_1_Pricing_Schedule.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| Attachment_1_Pricing_Schedule.docx | DOCX document | |
| Questions_Regarding_SShelters.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| Attachment_1_Pricing_Schedule.docx | DOCX document | |
| RFQ.docx | DOCX document | |
| RFQ_CO_Reviewed.docx | DOCX document | |
| Attachment_1_Pricing_Schedule.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions Regarding Solicitation No. FA5000-19-Q-0010
Q1. What are the maximum allowable dimensions of an “Or Equal” ECU?
A1. The maximum allowable dimensions for the “Or Equal” is 52”w x 42”d x 25”.
Q2. ECU with the ability to nest on top of other ECUs and be locked together during storage and shipment. Will you require the “Or Equal” ECU to be able to do the same?
A2. Yes. The Government requires the “Or Equal” to have the ability to be locked together.
Q3. AKS (AK-ECU-5T) has the below features. Is an “Or Equal” ECU required to have any of the following features:
a. Scroll compressor – Scroll compressor is not required.
b. Hot-gas, by pass valve – Hot-gas, by pass valve is not required.
c. Micro channel condenser coil – Micro Channel condenser coil is required.
d. Phase rotation monitor – Phase rotation monitor is not required.
e. Removable legs – Removable legs is not required.
f. Drain hose – ECU is required to have a drain hose.
g. Certificate from nationally accredited testing lab for UL1995 and CSA C22.2 No. 236- Yes. The Contractor is required to have this certificate.
h. Wood crate for shipping – Wood Crate is required for shipping.
i. Operation & maintenance manual - Operation & maintenance manual is required.
j. Spare parts kit. – Spare parts kit is required.
Q4. The Brand Name offers a 5 year non pro-rated warranty. What will you require the or Equal warranty to offer?
A4. Yes, The Government requires a 5 – Year or greater non pro-rated warranty on the ECU.
Q5. What is the latest required delivery date after award?
A5. The latest delivery date is 20 Mar 2019.