FA5000-09-R-0028
Attachment 1
1010-1 11May09
FXSB 09-2300
M/R Roofs - REQ
Section 1010
General Requirements
1. PROJECT LOCATION: All work under this project will be performed within the geographical boundaries of Elmendorf AFB and Ft. Richardson, Alaska. Work areas will be identified in the issued delivery orders.
2. ISSUING OFFICE / NOTIFICATION OF WORK START:
2.1 For Elmendorf issued delivery orders:
2.1.1 The following office is authorized to place delivery orders and will be responsible for the administration of placed delivery orders:
3rd Contracting Squadron 10480 22nd Street Elmendorf AFB, AK 99506
2.1.2 The Contractor shall give at least 3 working days advance notice in writing to the Contracting Officer, unless approved otherwise, prior to starting any work under this contract and prior to starting on-site work on each delivery order, Provide an “on-site start work” notice to the Contracting Officer for establishing the “on-site” construction start and completion dates.
2.1.3 In 2010 Fort Richardson and Elmendorf will Joint Base and at that time all delivery orders will be placed by the Elmendorf office and they will have full responsibility for the administration of the placed delivery orders.
2.2 Building Custodian: The contractor shall notify the building custodian of the approved work schedule for each roof at 3 days prior to starting the on-site roof work, unless approved otherwise by the Contracting Officer.
2.3 For Fort Richardson issued delivery orders:
2.3.1 The following office is authorized to place delivery orders and will be responsible for the administration of placed delivery orders:
Regional Contracting Office-Alaska Attn: SFCA-PRA-AA PO Box 5-525 Bldg 977 Attu Hall Fort Richardson, AK 99505-0525
Roof Requirements FA5000-09-R-0028
1010-2
2.3.2 The Contractor shall give at least 3 working days advance notice in writing to the Contracting Officer, unless approved otherwise, at Fort Richardson prior to beginning any work on each delivery order,
3. WORK SCHEDULE:
3.1 Work Hours: Work hours on this project shall be limited to Monday through Friday inclusive, between 0700 - 1800 hours, excluding federal holidays, unless approved otherwise by the Contracting Officer.
3.2 Should the Contractor desire to work other than these hours, Contractor must request approval of deviation in writing at least 24 hours prior to the period of the intended deviation, but not later than Friday 0900 hours for working on the weekend. The Contractor shall not accomplish the deviation in work hours unless approved by the Contracting Officer.
4. FIRE AND SAFETY REGULATIONS:
4.1 For Elmendorf AFB issued delivery orders, the Contractor shall comply with all national, state, local and Air Force fire and safety regulations. A copy of Air Force and Elmendorf AFB fire and safety regulations can be reviewed at the Contract Management Office, Base Civil Engineer, 6326 Arctic Warrior Dr.
4.2 Prior to using any open flame devices, welding equipment and other similar operations the contractor and subcontractor personnel performing this type of work shall be certified to issue AF Form 592, USAF Welding, Cutting and Brazing Permit. Certification training is provided by appointment and can be scheduled by contacting Technical Services at 552-2620/3267. Compliance with the requirements set forth in NFPA Standard No 241, Bldg Construction and Demolition Operations, NFPA 51B, AFOSH 91-5, and OSHA 1910-252 is mandatory.
4.3 Training of Contractor Employees: Contractor shall ensure that all their employees, including the employees of subcontractors receive an initial Fire Prevention Orientation briefing prior to beginning any work under the scope of this contract. This briefing is given by the Elmendorf AFB Fire Department on every Thursday each month at 0800 at 5126 Arctic Warrior Dr., Fire Station #2 and shall be scheduled through written request to the Fire Department at least 72 hours prior to the intended date of the briefing. The Contractor shall submit a written record to the Contracting Officer indicating that all of his/her employees and subcontractor employees have received this briefing. As new employees of the Contractor and subcontractor are added during the performance of this contract, update the written record to the Contracting Officer. The Contracting Officer shall retain the right to spot check employees to verify if they have been provided the briefing.
4.4 Contractor Fire Prevention Responsibility:
4.4.1 The roofing contractor is responsible for:
1010-3
4.4.1.1 The contractor shall provide a “firewatch” person during all welding performed on-base, which includes any welding work on heavy equipment anywhere on-base.
4.4.1.2 The Contractor shall notify the Base fire department and the 3 CES Fire Alarm shop at least 24 hours in advance prior to any fire alarm or sprinkler system shutdowns or prior to performing any roof demolition, which may set off the building’s fire alarm system.
4.4.1.3 Welding, cutting or brazing will only be done after a valid AF Form 592 has been issued by an individual certified by the Base Fire Protection Flight to issue welding permits. Daily permits are required for the operation of any asphalt kettles.
4.4.1.4 Fire extinguishers required during construction shall be supplied by the Contractor. The contractor shall provide at least 2 operating fire extinguishers at the hot roof work location.
4.4.2 It is the inherent responsibility of the Contractor to practice good fire prevention measures while working on Elmendorf Air Force Base and these include, but not limited to:
4.4.2.1 Contractor personnel shall confine smoking to designated smoking area(s).
4.4.2.2 Flammable paints, oil, varnishes, etc., stored in inside storage shall be in a metal storage cabinet or in outside storage in a controlled area. Flammables being used outside of these areas are limited to a one day supply.
4.4.2.3 Temporary wiring must be in compliance with Article 305 of the National Electric Code.
4.4.3 Questions concerning fire prevention can be referred to the Technical Services Section at extension 552-2620/3267.
4.5 For Fort Richardson issued delivery orders, the Contractor shall comply with all national, state, local and Army fire and safety regulations. A copy of Army and Fort Richardson fire and safety regulations can be reviewed at the Contract Management Office, Dept of Public Works, Ft.
Richardson.
4.5.1 The contractor shall notify and obtain approval from the Fort Richardson Fire Department prior to performing any flame cutting or welding operations, or closing any roads. Contractor shall have a type “A” fire extinguisher at the site of all cutting or welding operations.
4.5.2. The Contractor will be responsible for notifying the Fort Richardson Fire Department and Alarm shop prior to any alarm or sprinkler system shutdowns at least 48 hours in advance or prior to performing any roof demolition, which may set off the building’s fire alarm system.
5. AS-BUILT DRAWINGS: Provide on AF Form 3000 as required on each individual delivery order.
6. SAMPLING AND TESTING:
1010-4
6.1 All tests shall be performed using specified testing procedures, or if no procedure is specified, the standard testing procedure used by the ASTM will be used. The Contractor shall verbally notify the Contracting Officer or his/her designated representatives at least 24 hours in advance when such testing will be performed so that the test may be observed by the Contracting Officer and/ or his/her designated representatives.
6.2 In addition to the specified testing requirements stated on the delivery orders, the Government may require additional verification testing at the contractor’s expense. All necessary samples and/or work associated with such samples for such verification testing shall be provided by the Contractor at no additional cost to the Government. Repairs required to the work to correct the evidence of such Governmental testing shall be replaced at the Contractor's expense within 24 hours unless otherwise directed in writing by the Contracting Officer.
7. UTILITIES:
7.1 Reasonable amounts of on-base water, electricity and other available utilities will be made available to the Contractor at no cost to the Contractor. The contractor shall provide the utility connections at no addition costs to the contract. The Contractor shall exercise strict conservation practices in the use of these utilities. Should the Contractor be found not using utility conservation practices by the contracting officer or his authorized representative, then the cost of this utility use will be passed along to the Contractor for the remaining performance period of the contract.
7.2 Telephone services for Contractor use can be secured at the Anchorage Telephone Utility Office, 10492 Necrason St., Elmendorf AFB, with the cost of the telephone service and connections borne by the Contractor.
8. UTILITY OUTAGES:
8.1 Scheduled: Request for all outages and interruption of electricity or other utility services shall be made in writing through the contract inspector to the utility manager, copy furnished to the Contracting Office at least 7 working days (excluding Federal holidays and weekends) prior to the desired period of outage. All outages are subject to written approval by the Utility Manager and will be authorized only at the convenience of the Government. This notification shall be made at least 7 working days prior to the utility outage and in sufficient time to give the utility personnel ample opportunity to arrange and schedule discontinuance of utility services. The Contractor shall hold all outages to a minimum number and of the shortest duration possible and only as necessary to accomplish the required work.
8.2 Unscheduled: The Contractor shall reimburse the government for man-hours, materials, and circuit cost when damage to or interruption of service on any cable or utility occurs through negligence of the excavator/constructor, including any failure to obtain proper coordination of 3rd Wing Form 3 prior to commencement of construction or excavation in accordance with paragraph 9 of this section.
1010-5
9. BASE CIVIL ENGINEER WORK CLEARANCE REQUEST:
9.1 Work Clearance Request [3rd Wing Form 3]: Before any alteration, roof demolition, or other construction work is begun, the Contractor shall obtain and fully process a 3rd Wing Form 3, Base Civil Engineer Work Clearance Request. The contractor shall process a separate request for each building requiring roof replacement that has an approved delivery order, unless approved otherwise.
This form can be obtained from the Construction Management Office, Base Civil Engineering, Elmendorf AFB, 6326 Arctic Warrior Dr; and it shall be prominently displayed on the job site at all times for review by the Contracting Officer and/or his/her designated representative. Since this form requires extensive coordination with several base agencies, expect 5 working days for completion.
9.1.1 Coordinate with appropriate utility locating agencies, both on-base and off-base, as shown on the Work Clearance Request [3rd Wing Form 3]. Initially, this form will be given to the contractor during the pre-construction conference. Contractor shall complete and follow all instructions on this form before the start of work IAW Wing Instructions [WI 32-1007], “Safeguarding Utilities from Damage”.
The contractor is considered the “construction agency” for compliance with WI 32-1007. A copy of WI 32-1007 will be available to the contractor during the pre-construction conference.
9.1.2 The Work Clearance Request is not valid until it is signed by the approving officer (block 21), who will not sign until all affected utility locates are marked in the field and all utility locating agency signatures are on this form. Work must commence within 30 calendar days after the approving officer’s signature, otherwise the work clearance request is no longer valid and a new work clearance request will be required.
9.1.3 Contractor shall notify the Contracting Officer immediately if new utilities were installed by others and not marked after all the initial locates were marked.
9.2 Protection of Existing Utilities: All underground utilities and overhead utilities with their support poles shall be safeguarded and protected from damage by the Contractor at all times, but especially when encountered or uncovered during excavation or backfilling operations.
9.2.1 Communications Cables: Complete all excavations in red area(s), as defined by Eleventh Air Force Regulation 700-5, by hand rather than machine methods, or expose cables by hand-digging prior to completing excavation by machine.
9.2.1.1 Contractor shall be held fully responsible for all cables/circuits that he has damaged when:
contractor failed to fully process 3rd Wing Form 3, or contractor failed to fully comply with 3rd Wing Form 3 instructions, or contractor failed to follow 3 WG/SCLPK (Base communications cable maintenance) instructions appended to 3rd Wing Form 3. Contractor shall then restore damaged cable(s) and circuits to their fully operational condition.
9.2.1.2 Contractor shall immediately report the damage to the Base Telephone Trouble desk, 552- 4647, and to the Contracting Officer; and the contractor shall commence restoration efforts within 1 hour. Failure to commence restoration within the required time limit, or to make continuous progress toward restoration, or to complete acceptable restoration within a 4-hour time limit or an alternate time limit negotiated with and established by the Contracting Officer, may result in suspension of contract work until acceptable restoration is completed and approved by the Contracting Officer.
1010-6
9.2.1.2 In cases where a cable is damaged for reasons noted in Para 9.2.1.1 above, the Contractor shall, if lacking the qualified trades in his organization, employ as necessary such qualified trades or employ another Contractor having such trades to restore the cable and circuits to original condition and full operation at no expense to the Government.
9.2.1.3 The Government reserves the right to protect a damaged cable from further damage or deterioration and the right to restore priority circuits; these actions shall not relieve the Contractor of his full responsibility for restoration.
9.3 Department of Public Works for Fort Richardson:
9.3.1 Permit: Before any excavation, alteration or other construction work is begun for Fort Richardson issued delivery orders, the Contractor shall obtain and fully process a digging permit from the Directorate of Public Works. The contractor is responsible for obtaining the signatures from all of the responsible officials identified on the permit. The contractor shall provide a drawing showing the limits of work identified on the delivery order for markup to accompany the permit. An approved copy of the excavation permit shall be in the possession of the project superintendent. The contractor shall coordinate all on-site utilities marking with the responsible official.
10. MONUMENT RESTORATION:
10.1 The contractor shall not disturb any existing on-base bench marks, monuments, and other survey reference points. If it is necessary to disturb or destroy a bench mark, monument, or other survey reference point, notify the 3rd Civil Engineer Squadron / Engineering Technician Unit at 552-2765 / 5661 before proceeding.
10.2 Any bench mark, monument, or other survey reference point already accidentally disturbed or destroyed requires immediate notification by the contractor to the Engineering Technician Unit. All disturbed or destroyed bench marks, monuments, and other survey reference points shall be restored to their original location as nearly as possible by the contractor at his expense. The specific location shall be tied to monuments using Elmendorf local grid coordinates. When a bench mark, monument, and other survey reference point is restored, the record of the survey shall indicate the deviation from the original location. Field notes shall be recorded in hard bound field books, which shall become the property of the government.
10.3 Report all known bench marks, monuments, & survey reference points on 3rd Wing Form 3.
11. CONTRACTOR’S USE OF PREMISES:
11.1 This project will be constructed within and utilizing facilities, some parts of which may continue to be in use and occupied during the construction. The Contractor shall coordinate all work to minimize inconvenience to facility occupants and to airfield operations.
1010-7
11.2 The Contractor shall be responsible for moving all mechanical equipment related to the roof work that is necessary to gain access to an area in order to complete the required roof work. The Contractor shall move back all mechanical equipment that is moved.
11.3 The Contractor shall take efforts to hold dust and noise to a minimum.
11.4 The Contractor shall not use traffic ways for storage areas unless granted permission to do so in writing by the Contracting Officer. At no time shall the Contractor block hallways, traffic ways or other access areas.
12. ACCESS TO CONSTRUCTION SITE / HAUL ROUTES:
12.1 The contractor will provide proposed access routes to the construction site, haul routes, and certain portions of existing parking areas for use by the contractor and his work force to the project engineer / project inspector for acceptance.
12.2 The contractor shall submit all proposed haul routes to the project inspector/project engineer for acceptance at least 5 days prior to starting hauling, unless indicated otherwise. Proposed haul routes shall include: to the construction site from off-base, and to the off-base disposal site, etc, for each delivery order. Haul routes are subject to change by the government.
12.3 The contractor shall provide daily clean-up of the approved haul routes that the contractor is responsible for dropping gravel or debris. When required by the government, the contractor shall provide a water truck for watering down the haul routes for dust control, etc.
12.4 Contractor shall be responsible for maintaining, repairing, and restoring existing parking areas and grass areas, which are used by his work forces, to their original condition immediately prior to his commencement of work. Normal wear and tear will be taken into account.
12.5 Employee parking shall be restricted to those areas designated by the project inspector.
12.6 The Security Forces will enforce traffic regulations, parking area assignments and security and the Contractor shall cooperate and coordinate to the fullest extent. The Security Forces are not responsible for the security of the contractor’s materials, equipment, etc..
12.6.1 All Contractors are advised that it is a violation of a post traffic regulation to exceed 10 miles per hour while passing military personnel in formation, or a military group running or walking along the side of the road. Driving privileges on this installation may be suspended or canceled for violating post traffic regulations or applicable state laws and will not be considered an excusable delay under the contract. Each Contractor must ensure that all of its employees have been informed of this information.
1010-8
12.7 Contractor shall provide to the Contracting Officer, Security Forces, and entry control personnel, 72 hours advance notice for each entry into restricted areas, unless approved otherwise by the Contracting Officer. Delays due to lack of immediately available military escort for Contractor personnel entering these areas shall be at the Contractor's expense.
13. ROOFING CONTRACTOR'S STORAGE AREAS / OFFICE AREA:
13.1 The Government will provide an on-base outdoor area for the Contractor's main storage area.
Limit storage in this area to the materials and equipment that pertain to this contract. This area shall be kept clean. Properly store hazardous materials.
13.2 The Contractor shall erect an approved 6’ high chain link temporary fence with black cloth covering around the main storage area. The Government in no way will be responsible for the security of any items stored in this area. The Contractor will return the area in the same condition as when he received it and remove the temporary fencing.
13.3 The contractor will also be provided an on-site outdoor storage area reasonably close (within 500 feet one way) to the work area of each building being re-roofed. Limit storage in this area to the materials and equipment that pertain to the building being re-roofed. This area shall be kept clean.
Fencing is normally not required. For high visibility buildings, the contracting officer may require black clothed fencing.
14. BARRICADES:
14.1 Construct and maintain barricades as required by the Safety Officer, the MUTCD and OSHA sufficient to prevent injury to persons and damage to property.
15. COLD WEATHER OPERATIONS: If any part of this project is pursued during periods of cold or inclement weather, the Contractor shall take all appropriate precautions to protect facilities and work involved in the project scope from damage by cold/or inclement weather. The contractor shall be responsible for snow removal required at the project site.
16. SUBMITTALS:
16.1 The contractor shall submit all required Material Submittals on AF Form 3000 in accordance with instructions contained herein and as specified on AF Form 66, Schedule of Material Submittals, to the Contracting Officer for approval. The government shall be allotted 10 working days to properly evaluate each material submittal & re-submittal. Contractor shall consider this time to evaluate submittals in his construction schedule.
16.2 “30 Days Prior to Starting Work on Order” means that the contractor shall provide the material submittals [for the line items on the issued delivery orders only] to the government for approval not later than 30 days prior to starting on-site construction work for that issued delivery order. When the material submittal for that line item is approved, that material submittal is approved for the entire
1010-9 duration of the contract and does not have to be re-submitted for approval for each delivery order with that line item. It does however, have to be re-submitted for informational purposes for each delivery order with that line item. Should there be a change from the approved material submittal, then it shall be re-submitted for re-approval.
16.3 Rejection of submittals for technical violations of the drawings or specifications will not be grounds for an extension of the performance period. If resubmittals are required, all parts of the original submittal package will be resubmitted together with changes so that coordination may be maintained.
16.4 All sections shall be submitted in 3 ring binders with clearly marked tabs separating each item.
Submittals will be consolidated by type (i.e. concrete, metal, wood) and all submittals for each specification section will be submitted at the same time.
16.5 Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 4 copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the test to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
17. CODES:
17.1 References to standards, codes, specifications, recommendations and regulations refer to the latest edition/printing issued prior to the proposal receipt date.
17.2 These Construction Documents, and the joint and several phases of construction hereby contemplated are to be governed, at all times, by applicable provisions of the Federal Law(s), including but not limited to, the latest amendments of the following:
17.2.1 Williams-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596.
17.2.1.1 By agreement between the US Department of Labor, Occupational Safety and Health Administration (OSHA) and State Department of Labor, Division of Occupational Safety and Health (DOSH), and HQ 11th Air Force, applicable OSHA regulations as amended by the State of Alaska are enforced for Contractors and Contractor personnel only by DOSH. At no time will the level of protection afforded the worker be less than the most strict of either the Federal or State regulations.
17.2.1.2 Code of Federal Regulations, Title 29, Parts 1910 (Occupational Safety and Health Standards) and 1926 (Safety and Health Regulations for Construction).
17.2.2 Federal Standard 313B, as it pertains to the procurement, identification, marking and control of potentially toxic or hazardous materials, and to the reporting of information concerning these materials.
1010-10
17.2.3 International Building Code, International Mechanical Code and International Plumbing code.
17.2.4 National Electric code.
17.2.5 NFPA 101, Life Safety Code.
17.3 Applicable portions of standards listed in the Specifications that are not in conflict with Contract Documents or with the Federal Acquisition Regulations (FAR).
17.4 All Air Force, llth Air Force, 3rd Wing or Elmendorf Base Regulations as pertain to construction, safety, fire, health and associated activities are part of this contract, which includes WING INSTRUCTION 31-203 Base Traffic Regulations. Publications are available thru the 3CES Construction Management office.
17.5 All Army Post Regulations as pertain to construction, safety, fire, health and associated activities are part of this contract, which includes 6th I.D. Circ 385-XX. Publications are available thru the Army Construction Management office.
18. TECHNICAL SPECIFICATIONS:
18.1 The words "approved", "inspected", "directed", "selected", and similar words and phrases shall be presumed to be followed by "by Contracting Officer". The words "satisfactory", "submitted", "reported", and similar words or phrases shall be presumed to be followed by "to Contracting Officer".
18.2 Instructions, directions and requirements as specified shall be considered to be followed by the phrase "unless otherwise specified or indicated".
18.3 The approving official and point of contact for this contract is the Contracting Officer. All direction and contract requirements will be determined by the Contracting Officer. The project engineer / project inspector will work with the contractor to provide the joint estimated quantities.
The project engineer will designate the work areas and the performance time for each delivery order, which will be issued by the Contracting Officer.
18.4 The “Contracting Officer” as used in this contract is defined as the “Contracting Officer or his/her designated representative”. The “project engineer / project inspector / project manager” as used in this contract is defined as the “government’s project engineer / project inspector / project manager”.
19. SALVAGE:
19.1 Equipment and materials indicated on the drawings for reuse shall be approved by the Contracting Officer before re-installation. Contract amount includes cleaning, conditioning and installing materials indicated for reuse.
1010-11
19.2 Any excess equipment and materials selected to remain the property of the Government shall be removed by the Contractor and delivered to the Property Disposal Officer 12737 Vandenburg Ave..
The following materials shall be delivered for re-cycling at the Municipality of Anchorage Metal Re-cycle Center: Metal roof panels and metal flashings.
20. DISPOSAL OF ELMENDORF AFB & FORT RICHARDSON MATERIALS:
20.1 Solid Wastes: Contractors will be required to dispose of all solid wastes generated by on-base and on-post delivery orders at state permitted off-base sanitary landfill facilities.
20.2 Minimum requirements for off-base solid waste disposal are as follows:
20.2.1 All wastes shall be disposed of in a State of Alaska permitted solid waste disposal facility, such as the municipal sanitary landfill located near Hiland Road and the New Glenn Highway.
20.2.1.1 Contractor is responsible for paying all dumping fees for Elmendorf AFB materials.
20.2.1.2 There are no dumping fees for Fort Richardson materials taken to the Hiland Landfill provided the contractor has the proper passes.
20.2.1.3 Contractor is responsible for keeping Elmendorf AFB materials separate from Fort Richardson materials that are disposed of at the Hiland Landfill. Elmendorf AFB materials cannot be mixed with Fort Richardson materials to avoid the dumping fees.
20.2.2 Waste hauling from Elmendorf AFB / Fort Richardson to off-base disposal locations shall meet or exceed all requirements and restrictions levied by the State of Alaska and the Municipality of Anchorage, including:
20.2.2.1 Meeting of any weight restrictions for any public roadways used.
20.2.2.2 Covering and securing all loads of waste other than earth materials to ensure that no materials are lost from each load during transit.
20.2.2.3 Prevention of overloading with earth materials such that load contents are prevented from escaping during transit.
20.3 Liquid Wastes:
20.3.1 Runoff and residues generated from any process including water-washing processes shall not be directly wasted to the sanitary sewer or to the storm drain system. They shall be collected, sampled and disposed of based on the results of the analysis of samples, compliance with EPA requirements and this specification. Contractor shall obtain the necessary permits from the State of Alaska for the discharge of industrial waste water.
20.4 Asbestos Disposal: See section 1124 and 1125.
1010-12
20.5 Lead-based Paint Disposal: See section 1120 and 1121.
20.6 Concrete Pavers Disposal: On-base disposal site is available.
21. HEALTH HAZARDS:
21.1 Health Hazards: The Contractor shall comply with the following sections of this specification regarding the following recognized health hazards: PCB Contaminated Oils - Section 1120, Lead-base paint - Section 1121, Asbestos Containing Materials - 1124 and 1125.
21.2 Confined Spaces:
21.2.1 For roofing projects, not required.
22. ENVIRONMENTAL CONCERNS & HEALTH HAZARDS:
22.1 The Contractor shall comply with the following environmental sections of this contract for Elmendorf projects:
22.1.1 Environmental Protection/Hazardous Materials: The Contractor shall strictly comply with Section 1120 of this contract for protection of personnel, Government property, and the environment, and for hazardous material handling, use and disposal.
22.1.2 Hazardous Waste: The Contractor shall strictly comply with Section 1121 of this contract for hazardous waste accumulation and disposal.
22.1.3 Asbestos removal: The Contractor shall strictly comply with Section 1124 and 1125 of this contract for asbestos removal and disposal.
22.1.4 Lead based paint removal: The Contractor shall strictly comply with Section 1126 of this contract for lead based paint removal and disposal.
22.2 The Contractor shall comply with the following environmental specification for Fort Richardson projects:
22.2.1 “United States Army, Alaska, Pamphlet 200-1”, “Hazardous Materials and Regulated Waste Management May 2000”. This publication is available thru the Army Construction Management office.
23. DD FORM 1354: Upon completion and acceptance of new work for each delivery order, the contractor shall complete DD Form 1354, Transfer and Acceptance of Military Real Property, prepared according to Air Force Regulations and submitted with AF Form 3000. This Form shall be obtained from the Contracting Officer.
24. CELL PHONE USE POLICY ON-BASE:
1010-13
24.1 Motor vehicle operators will not use cell phones on-base or on-post unless the vehicle is safely parked or they are using a hands-free device.
24.2 This requirement applies to all contractor’s/subcontractor’s vehicles as well as POVs used by the contractor’s/subcontractor’s personnel to drive to/from the jobsite.
24.3 A violation of this policy will result in the loss of on-base driving privileges for 30 days.
25. UNITS OF MEASUREMENT:
25.1 Lump sum items or Each items;: Lump sum items or Each items are normally measured for payment as a complete item(s) at the time of 100% completion. When accompanied with an approved progress report, the lump sum item or each item may be paid up to the same percentage as shown on the approved progress report.
25.2 Linear, area, and volume units: Measurements of items by linear, area, or volume may be rounded up to facilitate payment as approved by the project manager as long as the dollar amount of the delivery order is not exceeded.
End of Section