This document is a Questions and Answers file for a carpet installation project at Davis-Monthan Air Force Base Building 4859. The accompanying federal contract opportunity is a Request for Quotation (RFQ) FA487725QA470, issued as a Women Owned Small Business Set-Aside with a $45 Million size standard under NAICS code 236220. The Air Force intends to award a firm-fixed price purchase order for carpet installation, with quotes due by 18 July 2025 at 2:00 PM ET.

The Q&A document contains unresolved questions about the project, including inquiries about carpet colors, cove base measurements, carpet tile specifications, furniture removal/replacement, electrical modifications, flooring substrate, potential asbestos, and design responsibilities. Key procurement details include FOB Destination shipping, evaluation based on technical capability, estimated completion timeline, and price, with the government reserving the right to make multiple or no award. Vendors must comply with REAL ID requirements for base access and submit a comprehensive quotation package including a Statement of Work and completion timeline.

View the file

Other files

File Type Posted
Questions Bldg 4859 Carpet (002).docx DOCX document
Provisions and Clauses Carpet.pdf PDF
Bldg 4859 floor plan.pdf PDF
Pima County Wage Determination.pdf PDF
Salient-Characteristics.pdf PDF
SOW Bldg 4859 Carpet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bldg 4859 Carpet Install Questions

Q. Were their specific colors that you wanted to incorporate?

A.

Q. What are the linear measurements of the Cove Base?

A.

Q. Should carpet tiles be installed on the stairs including stair nosings?

A.

Q. Do you have a specific material specification or product requirement for the carpet tile?

A.

Q. What height of rubber cove base is required 4 inches or 6 inches?

A.

Q. Are any scaled PDF blueprints available for reference?

A.

Q. Does this work need a design professional?

A.

Q. Does the vendor need to remove and install furniture or provide brand new furniture?

A.

Q. Section 3.1.7 of the SOW mentions the use of a licensed electrician. Additionally, based on the floor plans, it appears that some walls are being relocated, which would likely require electrical modifications. Is this intended to be a design-build project that includes these changes?

A.

Q. Section 3.2 (Design Work) refers to space planning, product specifications, and design/layout considerations. It also references the provision of new furniture and the inclusion of new electrical circuits. Can you clarify the extent of the contractor's design responsibility and whether new electrical work is part of the scope?

A.

Q. Can you confirm the type of existing flooring substrate? Specifically, is the current flooring installed over a concrete slab?

A.

Q. Has any asbestos been identified under previous flooring in these areas, or is there a known history of asbestos-containing materials within the project scope?

A.

Q. The scope of work indicates removal and installation of carpet, including cove base and the move/return of existing furniture, which suggests that current furnishings will remain. However, Section 3.1 (General Services) under the Design Requirements references the provision and installation of new office workplace furniture. Can you confirm whether new furniture is to be provided, or if existing furniture is to be reused?

A.