16._Spec_03_35_00_10-Concrete_Finishing.pdf

PDF 32 KB Posted

Attached to
Construct Guardian Angel AFE Shop Federal contract opportunity
Solicitation number
FA487718B0004
Issued by
Department of the Air Force Air Combat Command

About this file

Concrete Finishing

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Davis-Monthan Air Force Base, Arizona FBNV 120068, Repair/Construct Addition Parachute Shop, Fac 4824

SECTION 03 35 00.00 10

CONCRETE FINISHING

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 301 (2016) Specifications for Structural Concrete

ACI 305R (2010) Guide to Hot Weather Concreting

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 FINISHING FORMED SURFACES

Forms, form materials, and form construction are specified in Section 03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING. Finish formed surfaces as specified herein. Unless another type of architectural or special finish is specified, leave surfaces with the texture imparted by the forms except that defective surfaces must be repaired.

Maintain uniform color of the concrete by use of only one mixture without changes in materials or proportions for any structure or portion of structure that is exposed to view. The form panels used to produce the finish must be orderly in arrangement, with joints between panels planned in approved relation to openings, building corners, and other architectural features. Do not reuse forms if there is any evidence of surface wear or defects that would impair the quality of the surface.

3.1.1 Class B Finish

Class B finish is required at all locations unless noted otherwise. Formed surfaces meet the requirements of ACI 301, surface finish SF-2.0.

3.1.2 Class D Finish

Class D finish is required at all concrete below grade. Formed surfaces meet the requirements of ACI 301, surface finish SF-1.0.

3.1.3 Architectural and Special Finishes

Conform special finishes to the requirements specified herein.

SECTION 03 35 00.00 10 Page 1

3.1.3.1 Smooth Finish

After other concrete construction is complete in each overall separate contiguous area of the structure, apply smooth finish to the following areas, wash tank walls. Use a mortar mix consisting of one part portland cement and two parts well-graded sand passing a No. 30 sieve, with water added to give the consistency of thick paint. After the surface has been thoroughly wetted and allowed to approach surface dryness, vigorously apply the mortar to the area by clean burlap pads or by cork or wood-floating, to completely fill all surface voids. Scrape off excess grout with a trowel.

As soon as it can be accomplished without pulling the mortar from the voids, rub the area with burlap pads having on their surface the same sand-cement mix specified above but without any mixing water, until all of the visible grout film is removed. Tightly stretch the burlap pads used for this operation around a board to prevent dishing the mortar in the voids. Complete the finish of any area in the same day, and make the limits of a finished area at natural breaks in the surface. Continuously moist cure the surface for 48 hours commencing immediately after finishing operations in each area. The temperature of the air adjacent to the surface must be not less than 50 degrees F for 24 hours prior to, and 48 hours after, the application. In hot, dry weather apply the smooth finish in shaded areas or at night, and never be apply when there is significant hot, dry wind.

3.2 REPAIRS

Repair in accordance with ACI 301, Section 5.

3.3 FINISHING UNFORMED SURFACES

The finish of all unformed surfaces must meet the requirements of paragraph TOLERANCES in Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE, when tested as specified herein.

3.3.1 General

The ambient temperature of spaces adjacent to unformed surfaces being finished and of the base on which concrete will be placed must not be less than40 degrees F. In hot weather meet all requirements of Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE paragraphs HOT WEATHER REQUIREMENTS and PREVENTION OF PLASTIC SHRINKAGE CRACKING. In hot weather when the rate of evaporation of surface moisture, as determined by use of Figure 2.1.5 of ACI 305R, may reasonably be expected to exceed 0.2 pounds per square foot per hour. Make provisions for windbreaks, shading, fog spraying, or wet covering with a light-colored material in advance of placement, and take such protective measures as quickly as finishing operations will allow.

Trowel finish floor surfaces unless noted otherwise. Float finish containment structures and slabs, with additional finishing as specified below, and true to the elevation indicated. Bring surfaces to receive additional concrete or backfill to the elevation indicated, properly consolidate, and leave true and regular. Unless otherwise indicated, evenly slope exterior surfaces for drainage. Where drains are provided, evenly slope interior floors to the drains. Carfully make joints with a jointing or edging tool. Protect the finished surfaces from stains or abrasions. Grate tampers or "jitterbugs" cannot be used for any surfaces.

The dusting of surfaces with dry cement or other materials or the addition of any water during finishing is not be permitted. If bleedwater is present prior to finishing, carefully drag off the excess water or remove by absorption with porous materials such as burlap. During finishing

SECTION 03 35 00.00 10 Page 2 operations, take extreme care to prevent over finishing or working water into the surface; this can cause "crazing" (surface shrinkage cracks which appear after hardening) of the surface. Remove and replace any slabs with surfaces which exhibit significant crazing. During finishing operations, check surfaces with a 10 foot straightedge, applied in both directions at regular intervals while the concrete is still plastic, to detect high or low areas.

3.3.2 Float Finish

In accordance with ACI 301, Section 5.

3.3.3 Trowel Finish

In accordance with ACI 301, Section 5.

3.3.4 Non-Slip Finish

Apply non-slip floor coatings in accordance with manufacturer's instructions.

3.4 EXTERIOR SLAB AND RELATED ITEMS

3.4.1 Pavements

Immediately following the final consolidation of the surface, float the pavement longitudinally from bridges resting on the side forms and spanning but not touching the concrete. If necessary, place and screed additional concrete, and operate the float until a satisfactory surface has been produced. Advance the floating operation not more than half the length of the float and then continued over the new and previously floated surfaces.

After finishing is completed but while the concrete is still plastic, eliminate minor irregularities and score marks in the pavement surface by means of long-handled cutting straightedges. Use straightedges that are 12 feet in length and operated from the sides of the pavement and from bridges. Equip a straightedge operated from the side of the pavement with a handle 3 feet longer than one-half the width of the pavement. Test the surface for trueness with a 12 foot straightedge held in successive positions parallel and at right angles to the center line of the pavement, and the whole area covered as necessary to detect variations. Advance the straightedge along the pavement in successive stages of not more than one-half the length of the straightedge. Immediately fill depressions with freshly mixed concrete, strike off, consolidate, and refinish. Also strice and refinish projections above the required elevation. Continue the straightedge testing and finishing until the entire surface of the concrete is true. Before the surface sheen has disappeared and well before the concrete becomes nonplastic, give the surface of the pavement a nonslip sandy surface texture by use of a light broom finish. Round edges and joints with an edger having a radius of 1/8 inch.

3.4.2 Sidewalks

Apply a lightly broomed finish.

3.4.3 Curbs and Gutters

Finish exposed surfaces using a stiff bristled brush.

-- End of Section --

SECTION 03 35 00.00 10 Page 3

SECTION 03 39 00.00 10

CONCRETE CURING

05/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 301 (2016) Specifications for Structural Concrete

ACI 308.1 (2011) Specification for Curing Concrete

ASTM INTERNATIONAL (ASTM)

ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Curing Materials

SD-06 Test Reports

Testing and Inspection for CQC

SD-08 Manufacturer's Instructions

Curing Compound

1.3 DELIVERY, STORAGE, AND HANDLING

Store materials in such a manner as to avoid contamination and deterioration. Materials must be capable of being accurately identified after bundles or containers are opened.

PART 2 PRODUCTS

2.1 CURING MATERIALS

Provide curing materials in accordance with ACI 301 Sections 5 and ACI 308.1 Section 2. Submit product data and manufacturer's instructions for

SECTION 03 39 00.00 10 Page 1 concrete curing compound.

2.2 WATER

Provide water for curing that is fresh, clean, potable, and free of injurious amounts of oil, acid, salt, or alkali, except that non-potable water may be used if it meets the requirements of ASTM C1602/C1602M.

PART 3 EXECUTION

3.1 CURING AND PROTECTION

Cure and protect concrete in accordance with ACI 301 Section 5.

3.2 TESTING AND INSPECTION FOR CQC

Perform the inspection and tests described below and, based upon the results of these inspections and tests, take the action required. Submit certified copies of laboratory test reports, including curing compound proposed for use on this project.

3.2.1 Moist Curing Inspections

At least once each shift, and not less than twice per day on both work and non-work days, inspect all areas subject to moist curing. Note and record the surface moisture condition.

3.2.2 Moist Curing Corrective Actione

When a daily inspection report lists an area of inadequate curing, take immediate corrective action, and extend the required curing period for those areas by 1 day.

3.2.3 Membrane Curing Inspection

Apply no curing compound until the Contractor has verified that the compound is properly mixed and ready for spraying. At the end of each operation, estimate the quantity of compound used by measurement of the container and the area of concrete surface covered, compute the rate of coverage in square feet/gallon, and note whether or not coverage is uniform.

3.2.4 Membrane Curing Corrective Action

When the coverage rate of the curing compound is less than that specified or when the coverage is not uniform, spray the entire surface again.

3.2.5 Sheet Curing Inspection

At least once each shift and once per day on non-work days, inspection all areas being cured using impervious sheets. Note and record the condition of the covering and the tightness of the laps and tapes.

3.2.6 Sheet Curing Corrective Action

When a daily inspection report lists any tears, holes, or laps or joints that are not completely closed, promptly repair the tears and holes or replace the sheets, close the joints, and extend the required curing period for those areas by 1 day.

SECTION 03 39 00.00 10 Page 2

-- End of Section --

SECTION 03 39 00.00 10 Page 3