Section_01_11_00_-_Special_Condition_08_Nov_2013.pdf
PDF 324 KB Posted
- Attached to
- Demolition Dormitories 37, 38 and 162 Federal contract opportunity
- Solicitation number
- FA4800-15-R-0004
About this file
Attachment 2 Section 01 11 00 Special Conditions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Final_Q_ _A_Demo_37 _38 _162_Rev_1.pdf | ||
| SOW_Revision_2_Demo_37 _38 _162.pdf | ||
| Amendment_3_FA4800-15-R-0004.pdf | ||
| B_37 38 _162_Sidewalk_Demo.pdf | ||
| QA_Response_FA4800-R-15-0004.pdf | ||
| B_162_Utilities.pdf | ||
| Amendment_2_FA4800-15-R-0004.pdf | ||
| B_37_38_Utilities.pdf | ||
| Section_32_92_19.pdf | ||
| SOW_Rev_1_17_Mar_15_Demo_37 _38 _162.pdf | ||
| Site_Visit_Sign_In_Sheet_Demo_37 38_ _162.pdf | ||
| AmendmentFA4800-15-R-0004-_0001.pdf | ||
| FINAL_RFP_FA4800-15-R-0004.pdf | ||
| Sectio_01_12_00-Enviro_Special_Conditions_(2014_-_4_Dec).pdf | ||
| WD_2005_2543_______Rev_16_______07_25_2014.doc | DOC document | |
| Section_02_41_00_Special_Conditions_May_2010.pdf | ||
| Demo_SOW_(LGCS_Format)_F_3738162_(Revised_4_Feb_15).pdf | ||
| Bid_schedule.pdf | ||
| DD_CHECKLIST_FORM_1354.pdf | ||
| RFP_Solicitation_Demo_37 38_and_162.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2
SECTION 01 11 00
SPECIAL CONDITIONS
REVISED 08 November 2013
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are re-ferred to within the text by the basic designation only.
SECTION 01 12 00 Environmental Special Conditions [Langley Air Force Base (AFB), Joint Base Langley-
Eustis (JBLE)]
U.S. ARMY CORPS OF ENGINEERS (USACE) EM 385-1-1
(2003 or most current version) Safety and Health Requirements
JBLE-LANGLEY, JBLE TELECOMMUNICATIONS BUILDING CABLING SYSTEMS STANDARDS
(JBLE-Langley, JBLE Specification 27 10 10 dated 02 June 2008 or most current ver-sion)
1.2 SUBMITTALS
The following items specified herein shall be submitted in accordance with SUBMITTAL PROCEDURES:
SD-03 Product Data
Material Safety Data Sheet (MSDS) for each item
State and EPA Region 3 Notifications
Recycling Report
Trip Tickets
Affirmative Procurement Report
Exemption Form, Annex B to LAFB Affirmative Procurement Plan
32-7080
All Employee Names and Social Security Numbers
Work Clearance Requests (Air Force Form 103)
Quality Control (QC) Report
SD-11 Closeout Submittals
Survey Report
Metadata
Deliverables and Final As-builts
Three copies of Computer-Aided Drafting and Design (CADD) digital final as-built drawings on CD’s
One As-Built (Redline) Drawings
SECTION 01 11 00 Page 1
Warranty of Construction
Equipment Warranty Certificate
Equipment Warranty/Guarantee Record
DD Form 1354 Acceptance and Transfer of Real Property Facilities
1.2.1 SUBMITTAL PROCEDURES
1.2.1.1 Schedule of Material Submittals (Air Force Form 66)
Information, shop drawings, certificates, test data, etc., listed on the attached AF Form 66, Schedule of Material Submittals, shall be submitted for approval by the Contracting Officer, or his/her designated representative in ac-cordance with the General Provisions. Whenever in this contract materials or drawings are required to be submit-ted by the Contractor to the Contracting Officer for approval and the material or drawings submitted are at vari-ance with the specifications or Government drawings, but are, nevertheless, approved by the Contracting Officer, inadvertently and without consciousness of the variance, and regardless that a closer review could have revealed the variance, then such approval shall not be final unless the Contractor expressly noted in a memorandum to the Contracting Officer, on the material submittal or drawing that “this material or drawing varies from specifications in the following aspects –” or uses other works of similar clear meaning. In the event of such an inadvertent, er-roneous approval, the Contracting Officer, upon discovering the variance at any stage, have the right to require the Contractor to do such rework and/or material replacement as is necessary to obtain compliance with the speci-fications, and the expense of such rework and material replacement shall be borne solely by the Contractor.
1.3 SCOPE OF WORK
The work under this project consists of demolition of Facilities 37, 38 and 162, located on JBLE-Langley, VA as shown on the attached sketches.
1.3.1 Work Hours
Normal duty hours for JBLE-Langley, JBLE are 0730 through 1630, Monday through Friday. Work on week-ends, recognized Federal holidays, or other than normal duty hours must be coordinated with the Contracting Of-ficer (CO) or his/her designated representative.
1.3.2 General Working Conditions
a. Work shall be performed in such a manner as to cause minimum disruption to the users in the area.
b. The Contractor shall notify the Contracting Officer or his/her designated representative when he in-tends to work so Government inspection can be provided while work is in progress.
1.4 ORDER OF WORK
The Contractor shall coordinate all work with the Contracting Officer, or his/her designated representative, and the Base Civil Engineer. Before starting work at the job site, provide five days notice to the Contracting Officer or his/her designated representative and the Chief of Contract Management at 764-3268.
1.5 PHASING OF WORK
Phasing will not be a factor in the demolition of this project. The Contractor may establish any sequence of work to accomplish the intended goals of demolition and removal of both facilities
1.6 APPLICABLE CODES AND REGULATIONS
The latest edition of the following Building Codes shall be used for all construction under this contract:
SECTION 01 11 00 Page 2
A. Air Force Engineering Technical Letter ETL 01-1, Reliability and Maintainability (R&M) Design Checklist
B. American National Standards Institute (ANSI) C. American Standards for Testing Materials (ASTM) D. Americans with Disabilities Act (ADA) E. ANSI C-2, National Electrical Safety Code (QIESC) F. Applicable Unified Facilities Guide Specifications G. Institute of Electrical and Electronics Engineers (IEEE) H. International Building Code I. International Code Council (ICC) International Plumbing Code J. International Fire Code K. International Mechanical Code L. International Society of Automation (ISA) M. JBLE-Langley, JBLE Electrical, Fire, and Communications Design Standards – latest edition N. Leadership in Energy and Environmental Design (LEED®) for New Construction and Major
Renovation v2.2 Reference Guide O. Life Safety Code, NFPA 101 P. MIL Handbook 1190 Q. National Electrical Code (NEC) R. National Electrical Manufacturers Association (NEMA) S. National Fire Protection Association (NFPA) T. National Fire Protection Association Codes (NFPA) – latest edition U. Supervisory Control and Data Acquisition (SCADA) V. Underwriters Laboratories, Inc. (UL) W. Unified Facilities Criteria (UFC) 3-600-01, Fire Protection Engineering for Facilities X. Unified Facilities Criteria (UFC) 4-020-01, DoD Security Engineering – Facilities Planning
Manual
NOTE: If there is a conflict between these codes or regulations and these contract specifications, the most strin-gent requirements shall apply at all times.
1.7 SALVAGE
Title to all materials and equipment to be demolished, excepting items indicated as Government salvage, shall be vested to the Contractor upon removal from the base except as noted below. The Government will not be respon-sible for the condition, loss or damage to such property after notice to proceed. All unsalvageable material will be disposed of legally off base.
1.7.1 Items Salvaged for the Government
The Contractor shall salvage the following existing materials to the Government as indicated below. Salvaged materials shall be cleaned, sorted, identified, bundled, boxed, etc. and delivered to the collection location identi-fied below.
ITEM DELIVERY LOCATION
NONE
SECTION 01 11 00 Page 3
1.8 CONSTRUCTION STANDARDS
1.8.1 General
The Contractor is reminded that the construction site must be operated and maintained according to these specifi-cations and is subject to inspection and enforcement according to all federal, state and local codes/regulations.
1.8.2 Office Trailers and Storage Units
1.8.2.1 Office Trailers
If a trailer is required for work and at the discretion of the Government, an office trailer may be located at the project site. The Contractor shall request Contracting Officer approval for the trailer location. The Contractor shall make the request in writing at least fourteen calendar days prior to placement of trailer at site. All office trailers shall be located in areas as directed by the Contracting Officer or his/her designated representative. Any office trailer shall be not more than 10’ x 32’ in size, provided with a skirt on all sides, in like new condition, and painted either Langley Brown (Federal Standard 595a, 20100), Langley Beige, or white. Office trailers in need of painting and / or repairs or that are in an unsightly condition will not be al-lowed at the project site. Displayed on the exterior of all trailers shall be a nameplate which has the name of the Contractor’s company, name for Con-tractor’s point(s) of contact (POC) and telephone number where he or she can be reached, contract number, pro-ject number, title and date trailer was placed on site where located.
1.8.2.2 Storage Units
The Contractor shall request Contracting Officer approval for the siting, size and color of Storage Units, CONEX boxes and dumpsters. The Contractor shall not bring any such items to the job site without the Contracting Of-ficer’s approval. All storage units shall be painted Langley Brown (Federal Standard 595a, 20100), Langley Beige or white. Displayed on the exterior of all storage units shall be a nameplate which has the name of the Contractor’s company, name for Contractor’s point(s) of contact (POC) and telephone number where he or she can be reached, contract number, project number, title and date unit was placed on site where located.
1.8.3 On-Site Storage Units
Availability and size of material lay down area shall be restricted as noted on the contract documents or as dis-cussed during the preconstruction conference. The Contractor shall consolidate all bulk or large quantities of ma-terials at the construction site in area(s) approved by the CO. All such items shall be stored neatly grouped to-gether. Bulky or unsightly construction materials, heavy or light equipment or tanks shall not be delivered to or stored on the construction site for any period longer than seven calendar days prior to use, installation in the pro-ject or start of construction. The Contractor shall store all supplies and equipment on project site to preclude theft or damage. Protection and security for materials and equipment on site is the sole responsibility of the Contrac-tor. The Contractor shall not use any area(s) for material or equipment storage that has not been approved by the CO or his/her designated representative.
1.8.4 Fencing and Screening
Contractor shall enclose the lay down area with a chain link fence that has been erected to a minimum height of six feet. Contractor’s lay down area shall also be screened from view. Screening shall be fabricated of 100% Polypropylene, woven, 92% blockage fabric that has been mechanically attached to the fence for the full height of the fence. The edges of each section of screening fabric shall be finished with a reinforced hem. Attachment points shall be reinforced fabric built into the hem or metal grommets built into the hem. All fabric used for screening of the construction lay down area shall be UV rated and dark brown or dark bronze in color. Fence screening fabric shall be inspected weekly to insure all sections remain properly in-stalled and taut at all times.
SECTION 01 11 00 Page 4
1.8.5 Locksets
Not Applicable
1.8.6 Communications
Not Applicable
1.8.7 Electrical Panels
Not Applicable
1.9 CONTRACTOR OPERATIONS
1.9.1 Grassy Areas
Grass and weed growth in excavated materials that are stockpiled on site shall be controlled or cut weekly.
Weeds and grass within the construction site shall also be controlled or cut weekly and any bushes or shrubs shall be trimmed monthly. Areas disturbed by construction or those areas required by the plans to be “re-seeded” shall be re-established by hydroseeding only. Straw shall not be used as a cover for freshly seeded areas.
1.9.2 Privately Owned Vehicles (POVs)
POVs used by Contractor personnel to commute to work are required to park in existing parking lots. Contractor or Contractor’s employees, including subcontractors, shall not park any personally owned vehicle (POV) or com-pany or delivery vehicle on grassy areas near or in the construction site without prior approval from the Contract-ing Officer, or his/her designated representative. When allowed, parking on grassy areas will only be for short-term delivery purposes (to include heavy tools, equipment, construction materials, etc.). Use designated hard sur-faces or existing parking lots near or within the project site for parking of POVs or company or delivery vehicles.
Tire and track impressions (ruts) created on wet or soft soil by vehicles or equipment used in the Contractor’s op-erations shall not be left for more than one day after removal of such vehicle or equipment that cased the rutting.
The Contractor shall restore the affected area(s) of the site to its original condition within that one-day period.
1.9.3 Site Cleanup
During construction, the Contractor shall maintain all areas in a neat and orderly manner. Contractor shall keep the construction site cleaned daily of all construction trash, trash generated by employees, debris or demolished building materials. If the work areas are not kept neat and orderly, the Contractor must return to the area to cor-rect the unacceptable condition. During the laying of asphalt roads, streets or parking surfaces, areas soiled by residual asphalt shall be cleaned daily. The Contractor shall treat with lime entrances and exits to asphalt work site at his/her own expense.
1.9.4 Access Routes
Access routes to this project shall be limited through the Base onto Sweeney Blvd, Lee Road, Weyland Road and Poplar Road.. The Contractor shall not use the gates at King Street Bridge or LaSalle Gate (Nealy Avenue) for haul route entry or exit. When entering and exiting the base, the haul route shall be through the West Gate only.
1.9.5 Removal of Formwork
The Contractor shall remove all concrete formwork and boards within fourteen calendar days after concrete pour.
SECTION 01 11 00 Page 5
1.9.6 Noise Control
The Contractor shall comply with all applicable state, local and installation laws, ordinances and regulations rela-tive to noise control, to include applicable quiet hours exclusive to JBLE-Langley, JBLE. Work site is in a resi-dential area of JBLE-Langley, JBLE. There shall be absolutely no construction activities in or around the con-struction site prior to or after the hours designated in “Work Hours” paragraph above without an approval from the Contracting Officer, or his/her designated representative. This restriction also applies to holidays also.
1.9.7 Excavations
All trenches/excavations shall be back filled and compacted to 95% of maximum Proctor density. Trenches will be top dressed with no less than three inches of shifted topsoil and then compacted. The finished area will be free of all debris, rocks and then graded to conform to the surrounding area. The area will be hydroseeded in accord-ance with SECTION 32 92 19 HYDROSEEDING of the specifications.
1.9.8 In-Ground Obstructions
Any type of raised obstructions shall have the surrounding soil backfilled, compacted to 95% of maximum Proc-tor density, and graded. The area will be top dressed as above to within four inches of the top of obstruction.
Ground level obstructions will have the area dressed to the level of the obstruction. The area will be hydroseeded in accordance with SECTION 32 92 19 HYDROSEEDING of the specifications.
1.9.9 Architectural Compatibility
Due to JBLE-Langley, JBLE’s distinct historic architecture and the high visitor traffic it receives, several special actions are required during construction:
a. The Contractor is solely responsible for spillage from his/her vehicles and such spillage shall be cleaned up immediately. For the duration of this contract and on a daily basis, the Contractor shall remove from all base roads and streets asphalt, mud, soil, rocks, trash and debris that result from his/her construc-tion operation on base. All roads or streets affected shall be cleaned before close of business on the par-ticular day affected. In the case of asphalt, roads will be cleaned and/or treated with lime immediately up-on detection.
1.9.10 Patching
All holes in walls or other parts of the structure where material or equipment is removed or replaced shall be sealed, painted, caulked or plugged neatly with original type of materials to match the existing part of the struc-ture so involved. All above work and materials shall be approved by the Contracting Officer or his/her designat-ed representative.
1.9.11 Repairs
Replace or restore all pavement, curb and gutter, and sidewalk disturbed by operations under this contract to the original condition, except where shown or specified otherwise. Compact backfill in pavement repairs with me-chanical tampers to affect a density equal to adjacent subgrade. Replace pavement with equal materials and equal thicknesses to that removed, unless indicated otherwise. Each pavement area shall be replaced immediately after the work operation for that area is completed. At the Contractor’s option, a temporary repair with a surface of bi-tuminous concrete may be made immediately and removed and the permanent repair made before completion of the contract.
1.9.12 Marking
Contractor shall not mark any curb or pavement with paint.
SECTION 01 11 00 Page 6
1.9.13 Protection Requirements
The Contractor shall at all times protect and preserve the property of the Government which is within the work area and could be affected by the accomplishment of the work specified and indicated, and all parties and indi-viduals within or near the work areas who could be endangered by the installation of the work.
1.9.14 Accidental Spills
In the event of fuel spillage during the performance of this contract, the Contractor shall be responsible for its containment, clean-up and related disposal costs. The operator shall have sufficient spill supplies readily availa-ble on the pumping vehicle or at the site to contain any spillage. In the Event of a Contractor related release, the Contractor shall immediately notify the Environmental Management Office and take appropriate actions to cor-rect its cause and prevent future occurrences. If the federal, state, or local authorities assess any monetary fine, penalty or assessment related to the release of any substance by the Contractor, his/her employees, or agents dur-ing the performance of this contract, the Contractor shall be solely liable for its payment, authorizes the United States Air Force to withhold such form of payment and otherwise indemnify and hold the United States Air Force harmless.
1.10 ENVIRONMENTAL PROTECTION. PLEASE REFER TO JBLE-LANGLEY, JBLE SECTION 01 12
00, ENVIRONMENTAL SPECIAL CONDITIONS.
1.10.1 Environmental Restoration Program (ERP) Requirements
1.10.1.1 Contaminated Soil and Free Products
Any material (soil) that is suspected of containing petroleum products shall be reported to the Contracting Officer or his/her designated representative. If discovered, the Contractor shall mitigate any potential threat to the work-ers, public and environment. The area that will be disturbed under this contract has the potential to have free product migrate into and under the construction site. Comply with VR-680 and record the quantity of any fuel removed from the line. Contaminated soil or free product shall not be used for backfill or removed from the base without written approval from the Contracting Officer. Once removal is approved, Contractor shall dispose of material under guidance of the Pollution Prevention Officer (633 CES/CEAN). All hazardous waste manifests shall be prepared by the Contractor and shall be coordinated, approved and signed by 633 CES/CEAN Hazardous Waste Manager (37 Sweeney Boulevard) prior to removal of such waste from the base.
1.10.1.2 Site Safety
Site summaries from our Management Action Plan are furnished with this contract to familiarize personnel with the potential hazards associated with construction and demolition work at these sites. Ensure workers are in-formed of potential hazardous exposures from working at these sites, and that the appropriate precautions are fol-lowed to minimize hazards to human health and the environment. Personnel working at these sites shall have 40-hour HAZWOPER Training. At least one individual on site should have completed the OSHA 8-hour supervisor training course. The plans identify the boundary of these IPR sites. To perform work at these sites, the Contrac-tor must have a Health and Safety Plan and Hazardous Waste Disposal Plan for proper disposal of all regulated materials generated during execution of this project.
1.10.1.3 Monitoring Wells
There are several monitoring wells installed in and around the proposed construction area. Site maps and con-struction drawings provide the location of these wells. The Contractor shall take all precautions to prevent any damage to wells. If the wells and associated structures are damaged during the project, the Contractor shall re-pair/replace all damages at no additional expense to the Government. Contractor shall dispose of all regulated
SECTION 01 11 00 Page 7 materials during repair of the damaged structures and remove any free product as required by Virginia Depart-ment of Environmental Quality (VDEQ) regulations.
1.10.1.4 Additional Excavation
Prior to any excavation beyond the immediate area or boundary of the construction site, the Contractor shall co-ordinate with 633 CES/CEAN and obtain the Contracting Officer’s approval.
1.10.2 NOTIFICATION OF ASBESTOS CONTAINING MATERIALS (ACM)
1.10.2.1 Asbestos Notification
There is no indication of Asbestos Containing Materials (ACM) in the areas affected by this work. However, if ACM is discovered the Contractor shall immediately stop all work operation and notify the Contracting Officer Technical Representative (COTR) and the Contracting Officer before proceeding with any work. Contractor is reminded that all asbestos removal work is subject to OSHA, EPA and Commonwealth of Virginia compliance and inspection for asbestos abatement. Contractor must perform asbestos removal work in accordance with these specifications and EPA National Emissions Standards for Hazardous Air Pollutants (NESHAPs) for asbestos and any subsequent updates thereto. This includes State and EPA Region 3 Notifications that shall be accomplished at least twenty days prior to starting any asbestos abatement or removal. A copy of the notifications shall be submitted to the Contracting Officer. All hazardous waste manifests shall be signed by 633 CES/CEIE (37 Sweeney Boulevard) prior to removal of such waste from the base. Only CEIE is authorized to sign these mani-fests. The Asbestos Program Manager is Mr. David Jennings who can be contacted at (757) 764-1133. Please contact him if you have any questions.
1.11 PROTECTION OF GOVERNMENT PROPERTY
1.11.1 General
The Contractor shall at all times protect and preserve the property of the Government which is within the work area and could be affected by the accomplishment of the work specified and indicated, and all parities and indi-viduals within or near the work areas who could be endangered by the installation of the work. Protection re-quirements include protecting the interior of the facility from inclement weather. Any actions necessary for ade-quate protection are solely the Contractor’s responsibility. Any temporary boarding of windows or doors must be painted Langley Brown or Langley Beige to match the exterior.
1.11.2 Protection of Equipment
Contractor is required to cover equipment that is to remain in place within the area of contract operations and pro-tect it against damage or loss and store equipment that is removed in performance of work where directed or use in work as required by drawings and specifications. Equipment temporarily removed shall be protected and re-turned equal to its condition prior to starting work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
1.11.3 Protection of Grounds
Contractor shall provide protective barriers for all grass, trees, shrubs, sidewalks, curbs and gutters within the construction boundary. Furthermore, such items, including grass, outside the construction boundary shall also be protected during delivery of materials or moving of equipment. Damages caused by the Contractor to existing grounds, plants, pavements, utilities, work by others, fixtures, or furnishings shall be repaired by the Contractor.
Such repairs shall be of as good condition as exited before the damaging, unless such existing work is scheduled for removal or replacement by the work requirements of the contract. This requirement also pertains to grading of site to remove all clods and grade irregularities prior to final inspection and acceptance. The Contractor may be required to install temporary fencing to protect the site, at no cost to the Government.
SECTION 01 11 00 Page 8
1.12 SAFETY
1.12.1 Safety Barriers and Signs
Contractor shall provide barricades, traffic control signs and construction safety signs that meet industry stand-ards. Actual location, size and final arrangement of these items shall be discussed and approved by the Contract-ing Officer prior to installation. Such approved items shall be of uniform size, design and color. All cones, bar-ricades, warning lights, temporary signs and protective devices shall conform to the current requirements of the Federal Highway Administration’s Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD) and the US Army Corps of Engineers Safety and Health Requirements Manual EM 385-1-1.
http://mutcd.fhwa.dot.gov/pdfs/2003r1r2/pdf_index.htm
1.12.2 Employee Health and Safety
1.12.2.1 Compliance
In order to provide safety controls for protection to the life and health of employees and other persons; for pre-vention of damage to property, materials, supplies, and equipment; and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all pertinent provisions of the Corps of Engineers Manual, EM 385-1-1 (2003), entitled “Safety and Health Requirements Manual”, as amended. The Contractor will also take or cause to be taken such additional measures as the Contracting Officer or his/her designated rep-resentative may determine to be reasonably necessary for the purpose. A copy of the manual is available for re-view in the Civil Engineering Contract Management Section office (Building 328) or copies can be obtained from the Government Printing Office, Washington DC 20402.
1.12.2.2 Subcontractor’s Compliance
Compliance with the provisions of this clause by subcontractors will be the responsibility of the Contractor.
1.12.2.3 Safety Records
The Contractor will maintain an accurate record of, and will report to the Contracting Officer or his/her designat-ed representative in the manner and on the forms prescribed by the Contracting Officer or his/her designated rep-resentative, exposure data and all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies and equipment incident to work performed under this contract.
1.12.2.4 Notification of Non-Compliance and Corrective Action
The Contracting Officer or his/her designated representative will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. After receipt of such notice, the Contractor shall take immediate corrective action. Such notice, when delivered to the Contractor or his/her representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Contracting Officer or his/her designated representative may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
1.12.3 Applicable Publications
The publications listed below form a part of this specification to the extent referenced. The publications are re-ferred to in the text by basic designation only.
a. Code of Federal Regulations (CFR):
(1) OSHA General Industry Safety and Health Standards (29 CFR 1910); Publication V2206; OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety
SECTION 01 11 00 Page 9 http://mutcd.fhwa.dot.gov/pdfs/2003r1r2/pdf_index.htm and health. They are for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402.
b. National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61).
c. Federal Standard (Fed. Std.):
(1) 313A Material Safety Data Sheets, Preparation and the Submission to the BioEnvironmental Of-fice on JBLE-Langley, JBLE. Safety and Health Requirements Manual, EM 385-1-1
(2) Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds is pro-hibited at JBLE-Langley, JBLE, DA Circular 40-83-4
(3) Work covered by this section: This section is applicable to all work covered by this contract.
(4) Definition of Hazardous Materials: Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910 and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, lead paint, polychlorinated biphenyl’s (PCBs), explosives and radioactive material, but may include others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging and pipe covering.
1.12.4 Precautions Against Hazards
1.12.4.1 Welding, Cutting and Burning
All welding and cutting operations shall be done in accordance with nationally recognized good practice. The current publications of the American Welding Society, 2501 NW 7th Street, Miami FL 33125, and the National Fire Protection Association, 470 Atlantic Avenue, Boston MA 02110, shall be used as a minimum standard of na-tionally recognized safety procedures in welding and cutting.
The Contractor shall provide the necessary methods of fire extinguishment and fire prevention, and before opera-tions begin, clear all welding and cutting operations with the representative of the Contracting Officer or his/her designated representative. The Contractor shall request and receive an AF Form 592, USAF Welding and Braz-ing Permit, before preparing for such operations.
The Contractor shall discontinue all burning, welding or cutting operations one hour prior to the end of the nor-mal workday. The Contractor shall provide a workman to remain at the site for thirty minutes after discontinuing the above operations. This workman shall make a thorough inspection of the area for possible sources of latent combustion. Any unsafe conditions shall be reported to the Fire Department for their investigation – EMER-
GENCY PHONE NO 911.
1.12.4.2 Open Flames
The use of open-flame heating devices will not be allowed except by special permission of the Contracting Of-ficer or his/her designated representative. Such permission will not be granted unless the Contractor has taken all venting precautions. Burning trash, brush or trees on the job site will not be allowed unless specific approval is granted for each incident by the Contracting Officer or his/her designated representative. Approval for the use of open fires and open-flame heating devices will in no way relieve the Contractor from the responsibility of any damage incurred because of fires
1.12.4.3 Flammable Liquid Storage
Flammable liquids shall be stored and handled in accordance with the Flammable Liquids Code (No. 30) of the National Fire Protection Association. Flammable liquids shall not be stored in the Contractors storage trailers.
SECTION 01 11 00 Page 10
1.12.4.4 Technical Services
The Langley Fire Department, Technical Services Section, (757) 764-4275, is available for assistance concerning fire hazard questions.
1.13 SECURITY
1.13.1 General Base Requirements
Access to JBLE-Langley, JBLE is restricted to those Contractor and subcontractor employees required for the performance of this contract and only for the performance period of this contract. Contractor passes are issued by the Pass and Registration Section, Building 5 (Visitor Control Center, at the LaSalle gate), after a signed letter from the Contractor listing all employee names and social security numbers has been delivered to and approved by the Contracting Officer or his/her designated representative. Procedures for requesting Base Passes for em-ployees and Contractor vehicles will be further explained during the preconstruction conference.
1.13.2 Emergency Security Situations
If a security violation is detected from any cause, it may result in the cessation of all work and evacuation of the area by all Contractor personnel to a point to be determined by the Security Forces Supervisor at the scene. The control of construction personnel under these conditions is a Security Forces Officer and their orders shall be fol-lowed in detail. Construction will be permitted to resume as quickly as possible. The individual causing the vio-lation may be apprehended, and if so, will be processed and released to a responsible supervisor; such person might be away from his/her work site as long as 1 to 1½ hours. If a hostile situation is detected because of the construction activity, the entire crew may be removed from the area and detained until competent authority ap-proved their release. All Security Forces exercises will be scheduled not to interfere with construction personnel or with their work.
1.13.3 Work In Special Security Areas
1.13.3.1 Escorts
Not Applicable.
1.13.3.2 Applicable Security Criteria
AFI 31-101, The Air Force Installation Security Program shall apply to construction projects at JBLE-Langley, JBLE.
1.13.4.1 General
All work to be performed on this project is within the boundary of a USAF Installation and will be confined to the immediate vicinity of Facilities 37, 38 and 162. Full operational status of the mission and Security Forces will be maintained throughout the contract period. To facilitate contract work while preserving strict security, a Contractor free zone will be established around each work area, and a combination of entry control, internal movement and surveillance techniques will be employed. Security procedures and USAF Security Forces actions will take precedence over all concerns at the time of emergencies or mission operations. The use of deadly force is authorized to protect government resources.
1.13.4.2 Entry Control
Entry into the work areas will be by Air Force Form 75, Visitor Pass and an Entry Authority List provided by the Contractor to the Chief of Security Forces. The Base Commander retains the authority to deny entry to any per-son(s). Security Forces and Escort Officials execute this authority for the Base Commander.
SECTION 01 11 00 Page 11
1.13.4.3 Identification Permits
The Contractor is responsible for requiring each employee to display an identification permit while within the ar-
ea. All identification permits shall be immediately delivered to the Contracting Officer or his/her designated rep-resentative, for cancellation upon release of any employee or termination of contract work, whichever is sooner.
All Contractor personnel shall stay within the boundaries of the guarded work zone. Subcontractors, material de-liverers or other workers must be pre-identified 48 hours in advance of their arrival by an Entry Authority List approved by the Contracting Officer or his/her designated representative. This list will contain the full name, SSAN and the base pass number (Air Force Form 75). If this notification is not received, some delay may be ex-pected
1.13.4.4 Search Procedures
Search procedures will be in effect at all times. Each time a Contractor personnel enters the secure area the vehi-cle and cargo, briefcases, toolboxes, etc. may be searched. Individuals are also subject to search by the use of a metal detector. Primary emphasis will be placed on locating explosive devices, instruments of espionage, unau-thorized individuals and other objects of a suspicious nature. The Contractor shall store tools and cargo that are not required for the job in his/her own facility that will be located in a designated area.
1.13.4.5 Internal Controls
The boundaries of the designated work areas will be under surveillance of armed guards. Contractor personnel must remain within the boundaries of the designated area and shall enter or depart the work areas only through the designated Exit / Entry Point. The Contractor shall insure all persons are aware of the boundaries, and that they are to remain within the work zone.
1.13.4.6 Security Manager
The Contractor shall designate a representative as Security Manager to coordinate security matters. At least 48 hours in advance of a change in work hours, the Security Manager shall notify the Contracting Officer or his/her designated representative, who will notify the Security Forces.
1.13.4.7 Housekeeping
The Contractor shall keep the work area neat and tidy. Clean up shall be accomplished daily, and all piles of ma-terials, equipment and debris that could afford cover or concealment for unauthorized persons shall be removed from the area. Storage areas will be designated and the Contractor shall not store anything within thirty feet of the boundary fence.
1.13.4.8 Power Interruptions
Power interruptions necessary as a part of the construction project shall be coordinated with the Contracting Of-ficer or his/her designated representative who will notify the Base Civil Engineer, Central Security Control and the area occupants. The request for interruptions shall include reason, date, time, area affected and duration, and shall be submitted to allow notification at least two days in advance of the interruptions.
1.13.4.9 Repair Responsibilities
Any damages or alteration to any security facility, i.e., fence, lighting, communication cables, will be repaired, replaced, or suitable substitute provided by the Contractor prior to nightfall of the day such action occurred or was detected.
SECTION 01 11 00 Page 12
1.13.4.10 Overnight Storage of Construction Machinery
All construction machinery that is self-propelled (tractors, backhoes, dozers, trucks, etc.) will not be allowed to remain within the Controlled Area overnight. Such vehicles must be parked in a designated area thirty feet be-yond the boundary fence, locked and keys removed.
1.13.4.11 Mission Operation
Not Applicable.
1.13.4.12 Delays In Entering And Leaving Work Area
The Contractor may experience delays due to compliance with entrance/exit requirements of controlled areas.
The Contractor shall not be compensated for reasonable delays in accessing the site. Also, due to the nature of controlled areas, the Contractor may be requested to leave the controlled area at any given time. The Contracting Officer may extend the contract performance time when area designations change while the Contractor is work-ing.
1.13.4.13 Safety
Flame and spark producing equipment (i.e., matches, lighters, vehicle cigarette lighters) shall be surrendered at the Entry Control Point prior to entry to the area. Smoking within the area is prohibited except in Contractor pro-vided approved smoking areas. The use of flame and spark producing equipment within the area is discouraged;
however, in the event that it is necessary to use electric welders, oxygen-acetylene torches or other spark produc-ing devices, the Contractor shall notify the Contracting Officer or his/her designated representative. Should a hazardous condition arise during the use of such devices, contact the Fire Department (Main Base: 911; Bethel Manor Housing: 865-1042). All Contractor personnel are subject to base safety and traffic regulations and may be barred from motor vehicle operation for cause.
1.14 HISTORIC DISTRICT/ARCHITECTURAL COMPATIBILITY
Due to the distinct historic architecture and the high visitor traffic LAFB receives, several special actions are re-quired during construction and are listed herein.
1.14.1 Newly Placed Concrete
When placing concrete adjacent to existing concrete, all newly placed concrete curbs, gutters and sidewalks shall match existing adjacent concrete in color and texture. Miami Buff is the predominate color used on LAFB. All concrete that is newly placed by the Contractor shall be Miami Buff in color unless specifically noted otherwise in the contract documents or instructed otherwise by the Contracting Officer or his/her designated representative.
1.14.2 Unprimed or Factory Finished Equipment
Unprimed or factory-finished equipment installed on the exterior of facilities shall be painted with two coats of brown paint to match existing equipment.
1.14.3 Patching
All holes in walls or other parts of the structure where material or equipment is removed or replaced shall be sealed, painted, caulked or plugged neatly with original type of materials to match the existing part of the struc-ture so involved. The Contracting Officer or his/her designated representative shall approve all above work and materials.
SECTION 01 11 00 Page 13
1.14.4 Pavement Repairs
Replace or restore all pavement, curb and gutter, and sidewalk disturbed by operations under this contract to the original condition, including any markings or striping, except where shown or specified otherwise. Compact Backfill in pavement repairs with mechanical tampers to affect a density that is equal to adjacent subgrade. Re-place pavement with equal materials and equal thickness to that removed, unless indicated otherwise. Each pavement area shall be replaced immediately after the work operation for that area is completed. At the Contrac-tor’s option, a temporary repair with a surface of bituminous concrete may be made immediately and removed and the permanent repair made before completion of the contract.
1.14.5 Marking Restrictions
Contractor shall not mark any curb or pavement with paint unless directed by the Contracting Officer or his/her designated representative.
1.15 RECORDING AND PRESERVING HISTORICAL AND ARCHAEOLOGICAL FINDS
1.15.1 Preservation
All items having any apparent historical or archeological interest, which are discovered in the course of any con-struction activities shall be carefully preserved. The Contractor shall leave the archeological find undisturbed and shall immediately report the find to the Contracting Officer or his/her designated representative so that the proper authorities may be notified.
1.15.2 Rehabilitation
All repair, maintenance, and construction must be completed in a manner that is consistent with the Secretary of the Interior’s “Standards for Historic Preservation Projects” and the Secretary’s “Illustrated Guidelines for Reha-bilitating Historic Buildings”.
1.16 EXCAVATION REQUIREMENTS
The Government will furnish the Contractor with an approved AF Form 103, BCE Work Clearance Request, in-dicating any special precautions or areas that will be marked (for utilities). The contract drawings, AF Form 103 and marking will indicate all information the Government has knowledge of, but will not indicate all conditions that may occur in the field. The Contractor shall not begin (work) excavation until the Clearance Request is is-sued. The Contractor shall be responsible for removing all markings made for his benefit as soon as the need for an individual mark is passed. The Government will mark utilities one time only. Maintaining these marks or ad-ditional marking is the responsibility of the Contractor.
1.16.1 Acquiring a Work Clearance Request (Air Force Form 103)
A coordinated and approved Work Clearance Request is required prior to any excavation activities. The Contrac-tor shall submit a request to the Project Inspector 14 days prior to the start of excavation work. All requests must be initiated no later than Thursday of any week to be inserted into the Work Clearance approval process for the following week. The Contractor will be notified to attend a Work Clearance scheduling meeting. At the Work Clearance meeting, the Contractor will receive an AF Form 103, instructions for completing the form, and a date and time for utilities to be marked. The Contractor shall not commence excavation prior to obtaining an ap-proved AF Form 103. After all respective utilities have been marked and verified by the Project Inspector, the Contractor shall return the original AF Form 103 to his/her respective Project Inspector for coordination and sig-nature by the Chief of Engineering. No digging or excavation shall begin before the Chief of Engineering signs the AF Form 103. After the Chief of Engineering signs the AF Form 103, the Project Inspector will return it to the Contractor. Then, and only then, shall the Contractor commence excavation. The Contractor shall maintain all utility markings for the duration of the contract. Contractor shall maintain original version of the AF Form 103 for the duration of excavation work at the particular site. Ensure all applicable parties have coordinated on
SECTION 01 11 00 Page 14 the form prior to excavation. For Miss Utility, use the Ticket Information Exchange (TIE) number or actual technician signature as evidence of coordination. The AF Form 103 clearance shall not be allowed to expire.
The Contractor shall revalidate/resubmit the AF Form 103 within seven days prior to the expiration date if it is anticipated or known that the duration of excavation will exceed the 30-day limitation.
1.16.2 Miss Utility
Contractor shall contact Miss Utility (1-800-552-7001) at least 48 hours prior to excavation to identify non-Air Force-owned underground utilities (cable TV, Bell Atlantic and Virginia Power, etc.). Notices to Miss Utility are good for 15 working days; after that period, Contractor shall renew the notice. Indicate renewals on the AF Form 103 as applicable. Miss Utility is open 24 hours, seven days a week. Calls after 1700, before 0700, on weekends and on holidays are accepted for emergencies only. Holidays include New Year’s Day, Martin Luther King Day, President’s Day, Memorial Day, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day, Day after Thanksgiving and Christmas Day. After 48 hours, Contractor should contact Miss Utility to confirm that clear-ance/marking operations have been completed. The Contractor must wait an additional 24 hours if any operators or contract locators have not responded to the Ticket Information Exchange (TIE) system request within the first 48 hours.
1.16.3 Markings
1.16.3.1 General Requirements for Marking Utilities
a. Prior to commencing any excavation, the Contractor must inspect the site for clear evidence of un-marked facilities. If evidence of such facilities is present, the excavator must notify the notification center and wait an additional three hours for the facilities to be marked.
b. The Contractor may choose to wait 72 hours and begin work after that time if there is no evidence that any underground facilities remain unmarked. However, it is recommended that Contractors contact the TIE system and confirm the status of underground facilities before they commence work.
c. After the markings have been made, Contractors are required to maintain a minimum clearance of two feet between a marked, underground utility line and the cutting edge of any power-operated excavating equipment. If excavation is required within two feet of any marking, it shall be performed very carefully with hand tools in accordance with Virginia Code Section 56-265.24.
d. If, during the course of excavation, a utility line has been exposed, before backfilling, the Contractor must inspect these facilities to ascertain if the facilities have been damaged. If damage of any kind is dis-covered or suspected, it is the Contractor’s responsibility to immediately notify the utility owner directly.
The Contractor must NOT attempt to repair damaged facilities.
e. Maintain any paint marks or stakes indicating underground utilities/lines as required during the dura-tion of work or thirty calendar days from date of approved AF Form 103 (whichever is earlier). Note that Miss Utility clearance expires after fifteen working days.
1.17 OCCUPANCY AND SERVICES TO EXISTING FACILITIES
The Contractor shall not interrupt utilities serving nearby facilties and parking lights in the areas without coordi-nating with the Contracting Officer or his/her designated representative.
1.18 UTILITIES
All reasonable amounts of water and electricity required for this work will be made available to the Contractor if such utilities exist at the project site. Temporary lines, connections, installation, maintenance and removal shall be the Contractor’s responsibility. The Contracting Officer, or the Contracting Officer’s designated representa-tive, shall approve any temporary lines and connections. All services are subject to discontinuance without notice to the Contractor in an emergency. Three-phase power may not be available. The Contractor shall provide his/her own necessary utilities when such utilities are not available at the project site.
SECTION 01 11 00 Page 15
1.19 UTILITY OUTAGES AND TRAFFIC
Contractor shall request utility / power outages or changes to normal traffic flow pattern at least 14 calendar days in advance of disruption or change to either. The contractor is responsible for supplying temporary restroom fa-cilities if a planned water outage occurs during normal duty hours or affects operations of critical and/or 24-hour manned facilities.
1.20 CONVENIENCE FACILITIES
Existing restroom facilities may not be used by construction personnel. The Contractor shall maintain, in a neat and sanitary condition, such accommodations for the use of his employees. Temporary restroom facilities shall be white in color.
1.21 SUPERVISION
1.21.1 Superintendent
The Contractor shall employ a construction superintendent to oversee all work under this contract. The superin-tendent shall remain at the project site at all times when work is in progress except for such incidental errands re-quired by his/her duties. The superintendent is responsible for the proper coordination and timeliness of the work, and for proper workmanship of all trades; therefore, his/her absence from the project site without a suitable substitute representative of the Contractor shall be considered as damaging to the Government.