Answers_to_Questions.docx
DOCX document 4 MB Posted
- Attached to
- 317 OSS Phenolic Lockers
- Solicitation number
- FA4661-18-Q-0147
About this file
Answers to Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Question_Form.doc | DOC document | |
| RFQ-03.pdf | ||
| Statement_of_Work_for_Lockers.pdf | ||
| Statement_of_Work_for_Lockers.pdf | ||
| Question_Form.doc | DOC document | |
| RFQ-02.doc | DOC document | |
| Question_Form.doc | DOC document | |
| Statement_of_Work_for_Lockers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4661-18-Q-0147
8/2/12
CUSTOM PHENOLIC LOCKERS: ANSWERS TO QUESTIONS
1. Where can we get a copy of the floor plan?
SITE VISIT: A site visit will be held on 16 August 2018 at 9:00 A.M. (CST). Please notify A1C Johnson if you will be attending by 14 August 2018 at 5:00 P.M. (CST). An escort will be provided at the visitor control center to provide access to base. Please arrive between 8:30 A.M. and 8:50 A.M. to be signed on to base (if required). The address of the Dyess AFB Visitor Control Center is: 1517 Arnold Boulevard, Dyess AFB, TX 79607.
There is no floor plan currently available. The room is 32’ 4” by 20’ 11”. There is a 4’ 4” by 10’ area at one corner where there is a staircase. There are also nine support beams, mostly against the walls. The lockers shall be installed around the staircase and support beams. The contractor shall install the lockers against the three walls and forming aisles in between. Please see the images and diagram (not to scale) below.
2. Are there any terms that impact companies that have filed bankruptcy in the past 10 years?
There are no terms that impact companies that have filed bankruptcy in the past 10 years, however bankruptcy could affect the SAM (System for Award Management) registration of a company. All contractors are required to have an active SAM registration with no active exlcusions in order for their bid to be considered.
3. Is there a loading dock at the facility?
There is no loading dock at the facility where the lockers will be installed. The contractor shall be responsible for providing all equipment necessary for the delivery and installation of the lockers in accordance with the attached SOW (Statement of Work).