JFSD 200800

REPAIR, INSTALL VALVES/HYDRANT-

WATER TOWER 123 (R/M)

Grand Forks AFB, North Dakota February 2008

Plans & Technical Specifications

REPAIR, INSTALL VALVES/HYDRANT-WATER TOWER 123 (RM) 200800

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS - SECTION 01000 - GFAFB TECHNICAL PROVISIONS

DIVISION 02 - EXISTING CONDITIONS

02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD

DIVISION 03 - CONCRETE

03 62 16 METALLIC NON-SHRINK GROUTING

DIVISION 05 - METALS

05 05 23 WELDING, STRUCTURAL

DIVISION 09 - FINISHES

09 97 13.16 INTERIOR COATING OF WELDED STEEL WATER TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 26 - ELECTRICAL

26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 23 SODDING

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS

REPAIR, INSTALL VALVES/HYDRANT-WATER TOWER 123 (RM)

Section 01000

Technical Provisions

1. SCOPE OF WORK:

1.1. Work to Be Done: The work consists of furnishing all plant, labor and materials to perform all work in strict accordance with these technical provisions and the project drawings.

1.2. Location: The site of the work is Grand Forks Air Force Base, ND.

2. PROJECT DESCRIPTION: The work to be performed includes but is not limited to the following:

2.1. Interior Wet Structural – All interior wet structural work shall be conducted in accordance to NACE Standard RP0178-2003.

2.1.1. Seal weld the inside of the joint between the roof plate and the vent. Seal weld the inside of the dollar plate butt joint. Seal weld the inside of the joints between the roof plate and the two roof couplings. See photos 1 & 2.

Photo 1 – Interior View of Tower Roof

Photo 2 - Interior View of Roof Vent

2.1.2. Caulk the lapped plate joints between roof plates and the upper shell torus section with epoxy caulk. See photos 1 & 2.

2.1.3. Repair welding on the two, approximately 6-inch diameter patch plates in the top shell course by grinding and welding. See photo 3.

01000 JFSD 200800

March 12, 2008

Photo 3 - Patch Plates

2.1.4. Remove all erection bracket scab marks below the High Water Level (HWL) by air arc gouging, cutting torch, or grinding. This includes the scab marks left following the removal of the erection ring. Repair the tank surface by welding and grinding.

This shall comply with AWWA D100-96. See photos 3 & 4.

Photo 4 - Erection Scab Marks

2.1.5. Grind off all weld spatter below the HWL. This shall also comply with AWWA

D100-96.

2.1.6. Replace the two gaskets for the wet riser man ways.

2.1.7. On the inside of the top section of the wet riser there is a ½-inch thick, 28-inch tall repair plate section, rolled to match the interior diameter of the wet riser, seal welded to the wet riser at its top and bottom. Repair plate section by grinding and re-welding bottom weld. See photos 5 – 7.

Photo 5 - Patch Plate on Top of Wet Riser

Photo 6 - Patch Plate on Top of Wet Riser

Photo 7 - Patch Plate on Top of Wet Riser

2.2. Interior Cathodic Protection

2.2.1. Scope & Design: The contractor shall provide all engineering services, materials, equipment, labor, and supervision for the installation of an automatically controlled impressed current cathodic protection system for corrosion control for the interior submerged surface of the specified tank. All work furnished shall be in accordance with A.W.W.A. Standard D104-97 and features included in this specification. The cathodic protection constructor shall be Corrpro Waterworks or equal. All engineering services shall be provided by a Corrosion Protection Engineer who is accredited by the National Association of Corrosion Engineers International. The system shall be designed by a Corrosion Protection Engineer with experience in cathodic protection for water storage tanks. The Corrosion Protection Engineer shall design the system to provide effective corrosion control in accordance with criteria for protection. The criteria for protection shall be based on a tank-to-water potential, IR drop free, within a range of -0.850 volts to -1.050 volts relative to a stationary copper-copper sulfate reference electrode. This potential shall be measured free of the effect of voltage gradients (IR drops).The Corrosion Protection Engineer shall also base system capacity and performance on:

2.2.1.1. Total submerged surface area of the tank. Total surface area includes HWL in bowl and wet risers in elevated tanks, which are 30" diameter or larger.

01000 JFSD 200800

2.2.1.2. Type of coating and condition of coating.

2.2.1.3. Total bare surface area to be protected will be a minimum of 25% of total surface area. Minimum current density of 0.5 MA/ft.2 bare surface area.

2.2.1.4. Chemical analysis of water including resistivity expressed in ohm-cm.

2.2.1.5. Tank is susceptible to icing.

2.2.1.6. Minimum anode design life of twenty years.

2.2.1.7. Selection, dimensions, and layout of system components specified in

Section 2.2.2

2.2.2. System Components:

2.2.2.1. Rectifier: The rectifier unit shall perform in accordance with

ANSI/AWWA Standard D104-97 Section 4: 4.1.1.1.1., Type A, IR drop free system, and include:

2.2.2.1.1. Transformer

2.2.2.1.2. Selenium or silicon rectifying elements

2.2.2.1.3. Circuit breaker(s)

2.2.2.1.4. Lightning, surge, and overload protection

2.2.2.1.5. Provision for air-cooling operation

2.2.2.1.6. Voltmeter(s) and ammeter(s)

2.2.2.1.7. Weatherproof cabinet in accordance with NEMA 3R

requirements

2.2.2.1.8. Provision to vary current output from 0% to 100% of rated capacity

2.2.2.1.9. Provisions for mounting, grounding, and locking

2.2.2.1.10. Provision for 110-120 volt, 60 Hz, single phase A.C. power

2.2.2.1.11. D.C. output capacity in volts and amperes in accordance with

Design (Section 2.2.1)

2.2.2.1.12. Number of circuits or separate rectifiers in accordance with

Design (Section 2.2.1)

2.2.2.1.13. Automatic controller shall be AWWA D104-97, Type A and shall adjust current output to compensate for changes in water level, temperature of water, water chemistry, and cathodic polarization, and shall include the following provisions:

2.2.2.1.13.1. Utilize long-life reference electrode(s)

mounted in tank

2.2.2.1.13.2. Monitor the tank-to-water potential, free of

IR drop

2.2.2.1.13.3. Automatically adjust the tank-to-water

potential, free of IR drop, to a preset value (Section 2.2.1)

2.2.2.1.13.4. Operate within 25MV of preset value

2.2.2.1.13.5. Limit current to a preset value

2.2.2.1.13.6. Utilize potential meter(s) to display tank-to-

water potential, free of IR drop

2.2.2.2. Long Life Reference Electrode(s): The permanent reference electrode shall consist of a copper-copper sulfate electrode which is manufactured to remain stable (plus or minus 10MV) for a minimum of ten years. The reference electrode to lead wire connection shall be encapsulated to prevent water migration. The stationary reference electrode shall be positioned in the tank water to provide the most representative measurements for the submerged surface area(s).

2.2.2.3. Anode Suspension System for Icing Tanks: The anode suspension system shall be designed to be resistant to ice damage and in accordance with ANSI/AWWA Standard D104-97, Section 4.2.4.1.1 Type A, Horizontal System. The anode suspension system shall consist of a minimum 5/16" polyester cord. The cord shall be secured to steel anchors welded to the side wall of the tank bowl or to the exterior of the dry access column of spheroidal type tanks and the side wall of wet risers which are 30" diameter or larger. All cord to cord connections shall be tied and taped. Any damaged caused to the exterior coating by welding shall be repaired.

2.2.2.4. Anode Materials: The anode materials shall be selected in accordance with

Design (Section 2.2.1) and shall consist of one of the following:

2.2.2.4.1. Minimum .062" diameter platinized niobium with 25 micro inches of platinum. The wire anode shall be continuous with a maximum of two (2) anode to header connections.

2.2.2.4.2. Minimum .062" diameter titanium with a precious metal oxide coating. The wire Anode shall be continuous with a maximum of two (2) anode to header connections.

All anode to header cable connections shall be sealed to prevent water migration.

2.2.2.5. Pressure Entrance Fitting: For icing tanks the pressure entrance fitting shall accommodate anode and reference electrode lead wires at the base of the tank or at the base of wet risers for elevated tanks, which are 30" diameter or larger. The fitting shall be manufactured to prevent leakage through the fitting and to prevent water migration through the wire insulation. The entrance fitting shall be sized for a maximum 1.5 inch Schedule 80 steel coupling.

2.2.2.6. Wiring: All wiring within the tank shall be insulated to prevent copper conductor to water contact. All wiring on the exterior of the tank shall be insulated and run in rigid conduit.

2.2.2.7. Hardware: All hardware used in conjunction with the system shall be protected against corrosion.

2.2.3. Energizing System: After the system is installed and the tank is filled, the cathodic protection constructor shall provide startup service which includes energizing, testing, and adjusting the system for optimum performance of the cathodic protection system. This startup service shall be in accordance with ANSI/AWWA D104-97 Section 5.2 Testing, 5.2.1 Field Test for Type A, IR Drop-Free System.

This startup service shall be coordinated with the Owner or his representative. All tank-to-water potential measurements shall be conducted with a calibrated portable copper-copper sulfate reference electrode and a portable high impedance voltmeter.

A minimum of five (5) locations shall be measured. All test data shall be reviewed and evaluated by the Corrosion Protection Engineer. In addition to the startup service, "as-built" drawings and an Owners Maintenance Manual shall be submitted to owner.

2.2.4. Warranty: All workmanship, equipment, and materials furnished by the cathodic protection constructor shall be guaranteed for one (1) year.

2.3. Interior Wet Coating

2.3.1. After structural repairs are completed, the roof, upper torus, shell, lower torus, and bowl shall be abrasive blasted to an SSPC-SP-10 Near White Metal Blast and coated with a light-colored polyamide epoxy system (similar to a Tnemec Series 20 Pota- Pox Epoxy). See photos 8 – 15.

Photo 8 - Overall Interior Coating Condition Photo 9 - Bowl Coating Condition

Photo 10 - Lower Torus & Bowl Coating

Condition Photo 11 - Delaminated Coating

Photo 12 - Pre-existing Pitting on Tank Bowl

Photo 13 - Lower Torus Sample Coating

Thickness

Photo 14 - Lower Torus Sample Coating

Photo 15 - Lower Torus Sample Coating

2.4. Exterior Structural

2.4.1. Install eight additional bolts to secure the removable top of the roof vent in place.

A 1/8-inch thick rubber gasket shall also be installed between the flanges to prevent damage to the coating and to assist in maintaining a water tight roof. See AWWA C111/A21.11 for gasket details. See photo 16.

Photo 16 - Roof Vent

2.4.2. Modify the locking hasps on the roof access manway as required to facilitate the use of locks.

2.4.3. Install 15 – 20 additional drain holes in the balcony floor/girder to protect the urethane finish coat. See photo 17.

Photo 17 - Balcony Floor/Girder

2.4.4. Replace 10 – 15 feet of loose or missing concrete grout under the base plates for the support columns and the wet riser using non-shrink 3000-PSI concrete grout.

Urethane caulk around the entire perimeter of the seam between the grout and base plate(s) using Sika-flex 1-A or approved equal. See photos 18 & 19.

Photo 18 - Condition of Tower Base Wet Riser

Photo 19 - Condition of Tower Base

2.5. Exterior Dry Coating

2.5.1. The coating on the roof shall be brush blasted to remove the loose and delaminating finish coat and to provide a surface profile. Coat with a two-coat epoxy coating and a finish coat of urethane to match the existing. The remainder of the tower shall be spot repaired by abrasive blasting to remove damaged and failed coatings. Repair with two coats of epoxy coating and one coat urethane to match existing finish coat.

Primer coating is assumed to be lead based & contain chromium. Contractor shall follow the proper local, state, and federal codes when removing & disposing of the coatings. In conformance with Federal USEPA Rules and Local State Rules for Removal of Lead Paint from Steel Structures, and for air quality and control of dust and fugitive emissions, a “Risk Factor” (RF) analysis for this storage structure has been performed and has been classified as a Class II for pollution control. See photos 20 – 28. Contractor shall provide adequate overspray protection. Any damaged caused by overspray will be the responsibility of the contractor.

Photo 20 - Tower Roof Coating Conditions

Photo 21 - Tower Roof Coating Conditions

Photo 23 - Shell Coating Conditions

Photo 25- Tower Bowl Coating Conditions

Photo 22- Tower Bowl Coating Conditions

Photo 24 -Exterior Coating Conditions

Photo 26 - Support Column Coating

Conditions

Photo 27 -Wet Riser Coating Conditions Photo 28 - Wet Riser Base Coating Conditions

2.6. Install new 10 inch water tower isolation valve & post indicator (PI) on tower main as well as a 6 inch Waterous or equivalent traffic type hydrant w/weep hole, isolated by a 6 inch gate valve. New hydrant shall be installed between new 10 inch water tower isolation valve & water tower. New hydrant, PI valve, and isolation valve shall be cathodically protected per specification 26 42 14.00 01. See photos 29 – 31 for more detail. Disturbed turf shall be sodded once all work is complete.

New Tower Isolation Valve w/ PI

New Hydrant w/ Isolation Valve

Photo 29 - Utility Map

01000 - 1 of 47 JFSD200800

JUNE 2008

Photo 30 – Typical Hydrant Detail

Photo 31 – Typical Gate Valvr

2.7. All tower work & utility work must comply with latest AWWA standards and state & local codes. Once all work is complete, the contractor shall clean and disinfect tank as specified AWWA Method No.3 C-652-92. Contractor is required adhere to EM 385-1-1, OSHA, 29

01000 - 2 of 47 JFSD200800

01000 - 3 of 47 JFSD200800

CFR 1910, other occupational health and safety requirements of the contract, and local, state, and federal codes throughout the duration of the contract.

3. STANDARD TESTS, QUALITY, AND GUARANTEES:

3.1. Tests or trials to determine the effectiveness of performance of a completed assembly or fabricated system shall be made by the contractor, without cost to the Government.

3.2. All articles, supplies and equipment, parts, and assemblies thereof, of standard manufacturers or for which design requirements are not prescribed by these specifications shall be guaranteed against any failure in the proper use or operation caused by defective material, workmanship, or design for the full warranty time which is standard with the manufacturer and/or supplier.

3.3. The contractor shall provide a minimum one year warranty on all work performed. A copy of the warranty shall be submitted to the Contracting Officer before final inspection of the facility.

4. BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST: Prior to any construction activity, the contractor shall initiate, prepare, and personally hand carry through an AF Form 103, Work Clearance Request. The Base Civil Engineering Work Clearance Request must be approved by the Chief of Operations, building 418. Existing utility lines to remain in place, both Government-owned and private or leased, shall be protected from damage during excavation and backfilling. If damaged, lines shall be repaired in a timely manner by the contractor at no expense to the Government. A minimum of 72 hours should be allowed for agency response to contractor requests for identifying and marking buried utility line routes. The Construction Inspector will assist the contractor by providing points of contact, however, the sole responsibility for executing the digging permit and coordinating utility markings with the Civil Engineer shops/private utility companies is that of the contractor. The contractor shall provide drawings and details showing the exact location and description of the intended type of excavation. The contractor shall also stake and define the boundaries of all required utility locates. The contractor shall allow ten (10) working days for processing the digging permit between the various activities that must coordinate on the request.

The contractor shall provide the Construction Inspector with a copy of the completed AF Form 103 and shall maintain the coordinated AF Form 103 at the construction site. The contractor shall comply with all instructions for hand excavation and other methods of safeguarding the buried utilities. The contractor shall promptly repair any damage created by his/her work force or subcontractors to items indicated on the contract drawings or identified by the coordinating agencies, back to its original working condition. The contractor should take caution at the five (5) foot mark on any side of a utility pre-identified to the contractor. Mechanical digging shall not commence, within 5 ft of buried utility lines, until locations of those lines have been established and properly verified by hand digging. If the contractor damages the marked utility within this area, he/she is responsible for replacing the utility back to its original working condition. Work to repair the damaged utility will commence immediately and will continue uninterrupted until the utility is restored. If the contractor damages a utility that was not identified or is outside 5 feet either side of the utility marking, the contractor shall notify the CO and the Construction Inspector to determine the method of repair (i.e., in-house or by contract). If the damaged utility requires an outside source (e.g., someone to repair fiber optic lines) to accomplish the repairs, and the contractor is responsible for the damage, and the contractor shall be liable to pay for such repairs.

5. POWER OUTAGES: Work shall be planned so that power outages will interfere as little as possible with base operations. Wherever possible, portions of the work that can be accomplished without a power outage will be done prior to outages. All materials, equipment, and labor required during a

01000 - 4 of 47 JFSD200800 power outage shall be on hand before service is interrupted. Whenever outages are limited to weekends or holidays the contractor shall perform the work at such times as designated at no additional cost to the Government. The contractor shall make his outage request on copies of the form (Request to Base Civil Engineering for Electrical Service Interruption at Grand Forks AFB, ND). Forms are available at Customer Service, building 418..

5.1. Control of the base electrical system is the responsibility of the base Utility Superintendent

(Bldg 418). All switching of electrical equipment/circuits must be approved by the base Utility Superintendent or his authorized representative. Work on de-energized high voltage lines or equipment is not permitted until the base Utility Superintendent or his/her authorized representative has issued a safe clearance procedure to the contractor foreman in accordance with AFI 32-1064.

6. FIRE REGULATIONS: Compliance with local, Air Force, and NFPA 241 (Safeguarding Building

Construction and Building Operation) regulations are mandatory. Fire extinguishers rated and approved by the National Fire Protection Association; of sufficient size, type, and quantity to cope with all known hazards, will be available and provided by the contractor during the execution of this contract.

6.1. The primary contractor is responsible to have personnel properly trained in safe welding, cutting, open flame operations and specific requirements of AFOSH Standard 91-5 and CFR 1910 252. This individual shall be certified in writing, by the installation Fire Department to issue the AF Form 592 for the duration of the contract. It shall be the responsibility of the primary contractor to coordinate all certification training instruction with the installation Fire Department.

6.2. Contractor/user must post a fire guard for twenty-four (24) hours (or certifies the facility fire safe) after welding, cutting and open flame operations in facilities when the following situations apply:

6.2.1. Fire detection/sprinkler systems cannot be returned to service.

6.2.2. Fire detection/sprinkler systems do not exist.

6.3. Fire Protection, Detection, or Suppression Systems: Established systems shall remain operational to the maximum extent possible. Systems in areas unaffected by this contract shall remain operational throughout contract duration. Interruption (disconnection) of systems shall be:

6.3.1. Coordinated (7) seven days in advance with the Contracting Officer and the Base

Fire Department.

7. INTERRUPTION TO UTILITIES: Shall (Electric, water, heat, sewer, traffic, telephone, etc.,) be coordinated 10 days prior to start. The contractor shall provide an estimate of time duration to complete the task to the Contracting Officer. The contractor shall restore the utilities to service before leaving the site unless prior approval has been obtained by the base Utility Superintendent and the Contracting Officer. Whenever interruptions are restricted to weekends or holidays the contractor shall perform required work at no additional cost to the Government.

8. CONSTRUCTION MANAGEMENT STANDARDS:

01000 - 5 of 47 JFSD200800

8.1. GENERAL: The Base Civil Engineer will provide the contractor with the construction site.

Contractors shall have trailers only at that site.

8.1.1. Storage Area: All contractor storage shall take place at the job site and will be properly screened and secured. There are no alternate storage areas on base. The contractor may store materials and trailers off base at his/her own expense.

8.1.2. A visually acceptable site at Grand Forks Air Force Base is an important construction standard. Contractor’s trailers must follow the base paint standards;

therefore, they are to be antique linen or white in color. The contractor shall maintain the trailers in good condition or must remove them. The contractor is responsible for the security of this property and general housekeeping of the area(s).

8.2. PLANS

8.2.1. Site Plan: Prior to starting the work, the contractor shall submit site plans to the

Contracting Officer for approval showing the layout and details of all temporary facilities used for this contact. The base approval authority, normally the Base Civil Engineer, must approve the plan. The plan shall include the location of the safety and construction fences, location of all site trailers, equipment and material storage areas, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas. Site photographs prior to the start of work may be included with the plan. At completion of work, the contractor shall remove the facilities and restore the site to the original condition.

8.2.2. Dirt and Dust Control Plan: The contractor shall submit truck and material haul routes along with a plan for controlling dirt, debris, and dust on base roadways. As a minimum, the plan shall identify the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadways.

8.2.3. Health & Safety Plan: The contractor shall submit a complete health and safety plan for the proposed work. Plan/Program shall be in compliance with EM 385-1-1, OSHA, 29 CFR 1910, and other occupational health and safety requirements of the contract. Plan shall provide a detail description of procedures to comply with health and safety requirements.

8.3. CONTRACTOR’S TEMPORARY FACILITIES

8.3.1. Administrative Field Offices: Contractor’s administrative field office and storage trailers shall be in like new condition and the exterior must be clean and shall be white or antique linen. Contractor shall be responsible for all temporary utility connections to their trailers. Storage of material/debris under the trailers is prohibited. Only minimal storage (for short term work) will be allowed at the project site.

8.3.2. Dumpsters: Equip dumpsters with a secure cover and paint the standard base color

(tobacco brown). The cover shall be closed at all times, except when being loaded with trash and debris. Locate dumpsters behind the construction fence or out of the public view. Empty site dumpsters at least once a week, or as needed to keep the site free of debris and trash. If necessary, provide 208 liter (55 gallon) trash containers painted the darker base color to collect debris in the construct site area.

Locate the trash containers behind the construction fence or out of the public view.

01000 - 6 of 47 JFSD200800

Empty trash containers at least once a day. Large demolition normally requires a large dumpster without lids-these are acceptable, but shall not have debris higher than the sides before emptying.

8.3.3. Temporary Sanitation Facilities: All temporary sewer and sanitation facilities shall be self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the Contracting Officer. The doors shall be self-closing. The exterior of the unit will match the base standard (antique linen), unless the facility is behind the construction fence or out of the public view.

8.3.4. Construction Site Clean Up and Safety Fence:

8.3.4.1. The construction site must be kept neat, clean, and free of debris. Clean up shall be performed at the end of each work day in conjunction with a complete general clean up at the end of the project.

8.3.4.2. The contractor shall provide a temporary construction fence with gates and warnings signs at the construction site prior to the start of work to protect the public from construction activities. Unless shown otherwise in the drawings, the fence shall enclose the construction site. The exact location of the fence shall be coordinated with the Contracting Officer prior to installation. The construction fence shall be chain link with dark brown fabric from ground level to a height of 6’, and shall be secured with vertical wood slats screwed together at least every 8’ and each end of the fabric, or more often if needed. The contractor shall maintain the fence in good condition throughout the construction period, and shall refasten the fabric as needed.

8.3.4.3. A safety fence will enclose those areas not within the construction fence.

The safety fence will match the base standard (Federal Color Standard #23531) (or bright orange where it protects excavated areas), high density polyethylene grid or approved equal, a minimum of 1.1 m (42 inches) high, supported and tightly secured to steel posts located on minimum 3 m (10 feet) centers. The contractor must remove the fence from the work site upon completion of the contract.

8.3.5. Grass Cutting: Cut grass (or annual weeds) within the construction and storage sites to a 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around the fences at times of grass cutting. Grass or weeds on stockpiled earth shall be maintained as described above.

9. UTILITY AVAILABILITY: All reasonable quantities of utilities (water and electricity) will be made available to the contractor without charge. The Government may not be held responsible for interruptions of utility service and shall not be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.

9.1. A centrally located water filling station for contractors is located at Facility 537.

Government provided water is only available at this location. For more information regarding filling station contact designated construction inspector.

9.2. The contractor shall modify source points to meet specific needs for utility use.

01000 - 7 of 47 JFSD200800

10. CONTINUED USE OF FACILITIES: For occupied facilities that are a part of this contract, the contractor shall ensure appropriate notification and coordination prior to task accomplishment with the building manager or housing resident. The contractor shall coordinate phasing of the work as described in paragraph 2, on the plans, or as approved through the Contracting Officer.

11. ADMINISTRATION REQUIREMENTS

11.1. CONTRACTOR PERSONNEL REQUIREMENTS

11.1.1. Subcontractors and Personnel: Furnish a list of contact personnel of the contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

11.1.2. Supervision: Have at least one qualifying supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills. Contractor shall submit a letter to the CO designating site superintendent/project manager for the duration of contract.

11.2. PRECONSTRUCTION CONFERENCE: After award of the contract but prior to commencement of any work at the site, the contractor shall meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.

11.3. AVAILABILITY OF CADD DRAWING FILES: After award and upon request, the electronic “Computer Aided Drafting and Design (CADD)” drawings files will be made available to the contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the contractor and without liability or legal exposure to the Government.

The contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney’s fees and defense costs, arising out of or resulting from the use of these electronic files. These electronic CADD drawing files are not construction documents. Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files and the corresponding construction documents. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the contractor uses, duplicates and/or modifies these electronic CADD files for

01000 - 8 of 47 JFSD200800 use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

11.4. ELECTRONIC MAIL (E-MAIL) ADDRESS: The contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the contractor of base access condition when emergency conditions warrant, such as blizzards, terrorist threats, etc. Multiple email address will not be allowed. It is the contractor’s responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office (s). The contractor shall promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.

12. NOTIFICATION TO THE CONSTRUCTION MANAGEMENT OFFICE (CMO): The contractor shall notify CMO (747-4939) at least seven days in advance of starting all work. This shall include, but is not limited to, notification when the initial work shall begin; when work shall resume after stoppage exceeding three work days; and when work shall begin following all specified exclusion periods. The official Notice to Proceed does not constitute sufficient notification to CMO that work shall begin.

12.1. Contractor Furnished Equipment Data: Approximately ten days prior to project final inspection the contractor shall furnish the following data to the Contracting Officer.

12.1.1. Equipment List: An itemized equipment list, showing unit retail value and nameplate data including serial number, model number, size, manufacturer, etc., for all contractor furnished items of plumbing fixtures, mechanical equipment, and electrical equipment installed under this contract.

12.1.2. Warranty: Provide a list of all equipment items which are specified to be warranted accompanied by a copy of each specific warranty. For each specific warranted item, the list shall include the name, address and telephone numbers of the subcontractor who installed the item, the supplier or distributor, and the manufacturer. The completion date of the warranty period shall correspond to the applicable specification requirements for each warranted item.

12.1.2.1. Warranty Service Calls: The contractor shall furnish to the Contracting

Officer the names of local service representatives and/or contractors that are available for warranty service calls and who will respond to a call within the time periods as follows: 4 hours for emergency calls (heating, air-conditioning, refrigeration, air supply and distribution, critical electrical service systems and food service equipment) and within 10 days of written notice for all other systems. The names, addresses, and telephone numbers for day, night, weekend, and holiday service responses shall be furnished to the Contracting Officer and also posted at a conspicuous location in each mechanical and electrical room or close to the unit.

12.2. Work Schedule: Working hours for the contractor will normally be between the hours of

7:30 a.m. and 4:30 p.m. excluding Saturdays, Sundays, and Federal holidays. If the

01000 - 9 of 47 JFSD200800 contractor desires to work during periods other than above, additional Government inspection forces may be required. The contractor must make his/her request to the Contracting Officer three days in advance of his/her intention to work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the Contracting Officer.

13. SUBMITTALS:

13.1. Material Submittals: After acknowledgment of Notice to Proceed, the contractor shall submit to the Contracting Officer for approval four hard copies of manufacturer's data, catalog cuts, samples, or other information as required for the items on the Material Submittal Schedule and the Technical Provisions and one electronic copy of the same information. No progress payments will be made until all material submittals are received or other arrangements have been made through the Contracting Officer.

13.2. Submittal Preparation: In preparing submittals it shall be incumbent upon the contractor to clearly and fully demonstrate that proposed materials, systems, or methods meet or exceed all applicable specific requirements of the Technical Provisions. Whenever possible, parameters such as units of measurement, testing protocols and technical vernacular specified in the text will be those employed or referenced by the contractor or his agent in demonstrating compliance. When not possible, the contractor will clearly and fully demonstrate, by written notation, how other parameters, employed or referenced, compare with those specified.

13.3. Shop Drawing Submittals: Shop drawings, when required, shall consist of a complete list of equipment and materials, including manufacturer's descriptive and technical literature;

performance charts and curves; catalog cuts and installation instructions. Shop drawings shall be prepared to graphically demonstrate proposed layout and anchorage of materials, equipment and appurtenances; and material/equipment relationships to other parts of the work including clearances for maintenance and operation. They shall also contain complete wiring and schematic diagrams; and any other details to graphically demonstrate that a system has been fully coordinated and will properly function as a unit. See Material Submittal Schedule.

13.4. Test Submittals: See Material Submittal Schedule for tests required.

13.5. Photographs: Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch.

The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report.

Photographs shall be provided for unrestricted use by the Government.

01000 - 10 of 47 JFSD200800

13.6. Project Schedule: Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the contractor proposes to perform the work and dates on which the contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required.

The scheduling of design and construction is the responsibility of the contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The schedule must be a forward planning as well as a project monitoring tool. Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded.

The schedule will provide the basis for all progress payments. If the contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the contractor submits the required schedule.

13.6.1. Construction Schedule: Prior to the start of work, prepare and submit to the

Contracting Officer for acceptance a construction schedule in the form of a Critical Path Method (CPM), Network Schedule in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.

13.6.2. Equipment Delivery Schedule:

13.6.2.1. Initial Schedule: Within 30 calendar days after acceptance of the proposed construction schedule, submit for Contracting Officer acceptance a schedule showing procurement plans for materials and equipment. Submit in the format and content as prescribed by the Contracting Officer, and include as a minimum the following information:

13.6.2.1.1. Description

13.6.2.1.2. Date of the purchasing order

13.6.2.1.3. Promised shipping date

13.6.2.1.4. Name of the manufacturer or supplier

13.6.2.1.5. Date delivery is expected

13.6.2.1.6. Date the material or equipment is required, according to the current construction schedule

13.6.2.2. Updated Schedules: Update the construction schedule and equipment delivery schedule at monthly intervals or when the schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation or the delivery dates as directed.

13.7. As-Built Drawings:

13.7.1. Redline Markup Drawings: The contractor shall revise 2 sets of paper drawings by red-line process to show the as-built conditions during the duration of the project.

These working as-built marked drawings shall be kept current on a weekly basis and at least one set shall be available on the jobsite at all times. Changes from the contract plans which are made in the work or additional information which might be uncovered in the course of construction shall be accurately and neatly recorded

01000 - 11 of 47 JFSD200800 as they occur by means of details and notes. Final as-built drawings shall be prepared after the completion of each definable feature of work (Foundations, Utilities, Structural Steel, etc., as appropriate for the project). The working as-built marked prints and final as-built drawings will be jointly reviewed for accuracy and completeness by the Contracting Officer and the contractor prior to submission of each monthly pay estimate. If the contractor fails to maintain the working and final as-built drawings as specified herein, the Contracting Officer will deduct from the monthly progress payment an amount representing the estimated cost of maintaining the as-built drawings. This monthly deduction will continue until an agreement can be reached between the Contracting Officer and the contractor regarding the accuracy and completeness of updated drawings. The working and final as-built drawings shall show, but shall not be limited to, the following information:

13.7.1.1. Utilities: In addition to record drawings provide for each exterior utility system a set of reproducible utility drawings, stamped and signed by a registered professional civil engineer or professional land surveyor, and two copies. Submit within ten working days after each system is in place, but no later than five working days before final inspection. Indicate exterior utilities from a point five feet from a building to the termination point or point of connection to existing system. Include the following:

13.7.1.1.1. Horizontal and vertical controls for new utilities and existing utilities exposed during construction. Reference to station's horizontal and vertical control system.

13.7.1.1.2. Sufficient dimensional control for all important features such as beginning and termination points, points of connection, inverts for sewer lines and drainage collection systems, top of pipe or conduit runs, manholes, cathodic protection appurtenances, valves, valve stem tops, backflow preventers, and other significant features.

13.7.1.1.3. Indicate type and size of all materials used in the construction of the system.

13.7.1.1.4. Indicate bearing and distance on tangent lines. On curves, indicate delta and radius of the curve, also provide X, Y, and Z coordinates at all BC and EC angle points. Indicate horizontal and vertical control for all intersecting and tangent points where utility alignment changes. Indicate X, Y, and Z coordinates at building line and point of connection for straight building laterals or services under 40 feet.

13.7.1.2. The location and dimensions of any changes within the building structure. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans. Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the contractor; including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.

13.7.1.3. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.

01000 - 12 of 47 JFSD200800

13.7.1.4. Changes or modifications which result from the final inspection.

13.7.1.5. Where contract drawings or specifications present options, only the option selected for construction shall be shown on the final as-built prints.

13.7.1.6. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, the contractor shall furnish a contour map of the final borrow pit/spoil area elevations.

13.7.1.7. Systems designed or enhanced by the contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.

13.7.1.8. Modifications (change order price shall include the contractor's cost to change working and final as-built drawings to reflect modifications) and compliance with the following procedures.

13.7.1.8.1. Directions in the modification for posting descriptive changes shall be followed.

13.7.1.8.2. A Modification Circle shall be placed at the location of each deletion.

13.7.1.8.3. For new details or sections which are added to a drawing, a

Modification Circle shall be placed by the detail or section title.

13.7.1.8.4. For minor changes, a Modification Circle shall be placed by the area changed on the drawing (each location).

13.7.1.8.5. For major changes to a drawing, a Modification Circle shall be placed by the title of the affected plan, section, or detail at each location.

13.7.1.8.6. For changes to schedules or drawings, a Modification Circle shall be placed either by the schedule heading or by the change in the schedule.

13.7.1.8.7. The Modification Circle size shall be 1/2 inch diameter unless the area where the circle is to be placed is crowded. Smaller size circle shall be used for crowded areas.

13.8. Final As-Built Drawing Preparation:

13.8.1. The redline markups drawings shall be submitted 10 days before the final inspection for approval by the Contracting Officer and/or his/her representative. Upon approval the redline markup drawings shall be returned to the contractor.

13.8.2. Preparer Qualifications: The contractor shall, at his own expense, provide a qualified individual or firm to transfer all revisions from the redline markup drawings to the awarded drawings to create the as-built drawings. Upon completion of the transfer both the redline markup drawings and the as-built drawings shall be submitted to the Contracting Officer for approval. The contractor has 20 calendar days to create the as-built drawings beginning from the day the approved redline markup drawings are returned to the contractor. Work shall be accomplished in a professional manner and the quality standards set forth in the following paragraphs.

01000 - 13 of 47 JFSD200800

13.8.3. Drawing Requirement: One complete set of full-size paper as-built drawings and one electronic set (AutoCAD .dwg format) of as-built drawings on a CD or DVD shall be provided by the contractor for each submittal requirement. Drawings, paper or electronic, shall comply with the latest version of the A/E/C CADD Standard available at: https://tsc.wes.army.mil/Products/standards/aec/default.asp Electronic drawings shall be created in model space at a scale of one to one (1 to 1).

A paper space layout will be set-up for each drawing. All X-references shall be attached and bound to each affected sheet. Drawings must open in the specified Auto Cad format and be ready to plot without manipulation of files, directories, or other encumbrances. No securities or safeguards that would prevent full control of any drawing will be installed. Changes made or inserted shall be completely drawn in Auto Cad to depict changes. Clouding, notation, or photo insertion to indicate changes are not acceptable unless approved in advance and can only be used on rare occasions. Electronic as-built drawings are to be delivered in AutoCAD 2004 compatible format. The contractor shall provide one CD or DVD containing all drawings properly labeled including awarded original drawings that were not changed. Drawing names shall mirror the awarded original drawing names and identified on the index sheet and each page. Any changes to the number of sheets in the drawing set will require the renumbering /labeling of the entire set. All drawings in the set must be clearly distinguishable from construction drawings. The words “AS-BUILT” or “RECORD DRAWING” must be prominently displayed in the drawing area or inside the revisions block of the border. The CD/DVD must also contain a second drawing set electronically plotted to a raster media such as .TIFF, .PDF, or JPEG for fast viewing.

13.9. REAL PROPERTY RECORD: Near the completion of Project,…