Response_to_Questions__2.docx

DOCX document 13 KB Posted

Attached to
Remodel Repair Jolly Pad Federal contract opportunity
Solicitation number
FA4626-16-R-0028
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Remodel Repair Jolly Pad, newest first.
File Type Posted
Response_to_Questions__3_(12vdc_Cable).docx DOCX document
Appendix_E_-_Asbestos_LBP_Report.pdf PDF
Amendment__2.pdf PDF
Addendum__2.docx DOCX document
Addendum__2.docx DOCX document
Response_to_Questions.docx DOCX document
Questions_and_Answers.docx DOCX document
E3.0_Revision_1.pdf PDF
Addendum__1.docx DOCX document
Amendment_001.doc DOC document
Pre-Proposal_Conference_-_Site_Visit.pdf PDF
Pre-Proposal_Meeting_Attendees.pdf PDF
Attch_9_Subcontractor_Consent.doc DOC document
Attach_7_Special_Contract_Requirements.docx DOCX document
Attach_3_SCHEDULE_OF_DRAWINGS.doc DOC document
Attch_8_Past_Performance_Questionaire_-_working.docx DOCX document
Attach_6_Base_Entry.pdf PDF
Attach_4_Drawings.zip ZIP file
Attach_2_Material_Submittal.xls XLS spreadsheet
Attach_1_Specifications.zip ZIP file
Solicitation.doc DOC document
Attach_5_Wage_Determination.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS FOR FA4626-16-R-0028

REPAIR RHS JOLLY PAD

1. Specification section 32 17 23 – Pavement Markings – Paragraph 3.2 requires a machine to sprayeach line completely in a single pass. The restricted area has 2’ wide sections. Spraying in a single pass will require incredible specialty equipment that we have not found in Montana. Are multiple passes acceptable when painting this area? The final product will meet or exceed Malmstrom QA/QC requirements.

· Multiple passes will be allowed to accommodate the extreme width in this area and the helipad itself as long as the requirements of the specs and drawings are met.

2. Please provide lead paint inspection report as referenced in the specification.

· The lead-based paint report is attached.