Slab_Repair_Questions_-_5-07-15.doc
DOC document 24 KB Posted
- Attached to
- Bi-Annual PCC Slab Repair
- Solicitation number
- FA4626-15-R-0008
About this file
Questions Answers 6 May 15
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 32_13_11_PCC_Airfield_Pavements_revised.docx | DOCX document | |
| Revised_Drawings.zip | ZIP file | |
| Amendment__1.pdf | ||
| Site_Visit_Minutes.pdf | ||
| Attch_3_Schedule_of_Drawings.doc | DOC document | |
| Solicitation.doc | DOC document | |
| Attch_2_Submittal_Schedule.xls | XLS spreadsheet | |
| Attch_5_Wage_Determination.docx | DOCX document | |
| Attch_4_Drawings.zip | ZIP file | |
| Attch_1_Specifications.zip | ZIP file | |
| Attch_6_Base_Entry_Policy_Letter.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PCC SLAB REPAIR
FA4626-15-R-0008
QUESTIONS & ANSWERS
06 MAY 15
Q1. In the sec. 32 13 11 Page 22 2.7.1 it says that dowels bars shall be epoxy coated, however on the drawing on page 2 it says the dowels shall be painted and greesed?
A1: The dowel bars should be epoxy coated, as specified in section 32 13 11 (Page 22). This is from the UFGS specifications for airfield pavement. I will change the drawings so the detail says "Epoxy Coated Dowel" and delete the word "paint".