Solicitation.doc

DOC document 777 KB Posted

Attached to
Pavement Requirements Federal contract opportunity
Solicitation number
FA4626-08-R-0009
Issued by
Department of the Air Force Global Strike Command

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Pavement Requirements, newest first.
File Type Posted
Questions.pdf PDF
CoverPagesandTOC.doc DOC document
WageDetermination.doc DOC document
SubmittalScheduleR1_08-1021.xls XLS spreadsheet
Spec's.zip ZIP file
PastPerfQuestionaire_Atch4.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
ESTIMATED QUANTITY
UNIT
UNIT PRICE
ESTIMATED AMOUNT
1
Each

BASE YEAR SUB-CLINS

FFP

All sub-clins (1001 AA thru 1001 BS) indentified in "Section "B" Continuation of Schedule" shall aplly to this Clin.

FOB: Destination

NSN: Z222-CE-PAV-CONS

MILSTRIP: F2W3D58038A001

PURCHASE REQUEST NUMBER: F2W3D58038A001

SIGNAL CODE: A

ESTIMATED

NET AMT

ITEM NO
SUPPLIES/SERVICES
ESTIMATED QUANTITY
UNIT
UNIT PRICE
ESTIMATED AMOUNT
1
Each
OPTION
OPTION YEAR 1

FFP

All sub-clins (1002 AA thru 1002 BS) indentified in "Section "B" Continuation of Schedule" shall aplly to this Clin.

FOB: Destination

NSN: Z222-CE-PAV-CONS

MILSTRIP: F2W3D58038A001

ESTIMATED

ITEM NO
SUPPLIES/SERVICES
ESTIMATED QUANTITY
UNIT
UNIT PRICE
ESTIMATED AMOUNT
1
Each
OPTION
OPTION YEAR 2

FFP

All sub-clins (1003 AA thru 1003 BS) indentified in "Section "B" Continuation of Schedule" shall aplly to this Clin.

FOB: Destination

NSN: Z222-CE-PAV-CONS

MILSTRIP: F2W3D58038A001

ESTIMATED

ITEM NO
SUPPLIES/SERVICES
ESTIMATED QUANTITY
UNIT
UNIT PRICE
ESTIMATED AMOUNT
1
Each
OPTION
OPTION YEAR 3

FFP

All sub-clins (1004 AA thru 1004 BS) indentified in "Section "B" Continuation of Schedule" shall aplly to this Clin.

FOB: Destination

NSN: Z222-CE-PAV-CONS

MILSTRIP: F2W3D58038A001

ESTIMATED

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN
MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

CONTINUATION OF SCHEDULE B

SCHEDULE “B” CONTINUATION SHEET FA4626-08-R-0009

PROJECT NUMBER : NZAS 08-1021

ACTUAL DATES; MM/DD/YYYY FOR ALL PERIODS WILL BE IDENTIFIED UPON AWARD OF CONTRACT.

UNIT OF

EST. EXTENDED

ITEM

DESCRIPTION
EST QTY
MEASURE

UNIT PRICE

AMOUNT

BASIC YEAR 2008 THRU 2009

1001
AA
Remove Existing Concrete Curb and Gutter, and Sidewalk
680.00
SY
$
$
-
1001
AB
Trench Excavation
85.00
CY
$
$
-
1001
AC
Excavation and Embankment
500.00
CY
$
$
-
1001
AD
Graded Aggregate Base
1,190.00
TON
$
$
-
1001
AE
Borrow
85.00
TON
$
$
-
1001
AF
Topsoil/Topsoiling
4,165.00
SY
$
$
-
1001
AG
Drill Seeding and Mulching
2,125.00
SY
$
$
-
1001
AH
Hydraulic Seeding and Mulching
2,125.00
SY
$
$
-
1001
AJ
Asphalt Pavement, Grade A
26,500.00
SY-IN
$
$
-
1001
AK
Portland Cement Concrete Integral Curb and Gutter
1,500.00
LF
$
$
-
1001
AL
Portland Cement Concrete Sidewalk - 4" thick
6,800.00
SF
$
$
-
1001
AM
Portland Cement Concrete Sidewalk - 6" thick
850.00
SF
$
$
-
1001
AN
Reinforced Portland Cement Concrete Slab - 6" thick
638.00
SF
$
$
-
1001
AP
Reinforced Portland Cement Concrete Slab - 8" thick
850.00
SF
$
$
-
1001
AQ
Reinforced Portland Cement Concrete Slab - 10" thick
580.00
SF
$
$
-
1001
AR
Striping
39,695.00
SF
$
$
-
1001
AS
Woven Geotextile Fabric
1,275.00
SY
$
$
-
1001
AT
Non-Woven Geotextile Fabric
1,275.00
SY
$
$
-
1001
AU
Geogrid
1,275.00
SY
$
$
-
1001
AV
Petromat with Flood Coat
2,550.00
SY
$
$
-
1001
AW
Stabilized Construction
1,275.00
SY
$
$
-
1001
AX
Sub & Edge Drain
850.00
LF
$
$
-
1001
AY
Sub & Edge Drain Manhole Connections
9.00
LF
$
$
-
1001
AZ
Bituminous Pavement Pulverization
510.00
SY-IN
$
$
-
1001
BA
Remove Existing Asphalt Pavement - Full Depth
8,500.00
SY-IN
$
$
-
1001
BB
Remove Existing Asphalt or Concrete Pavement -Partial Depth
595.00
SY-IN
$
$
-
1001
BC
Remove Existing Concrete Pavement -Full Depth
298.00
SY-IN
$
$
-
1001
BD
Butt Joints
638.00
LF
$
$
-
1001
BE
Preparation of Existing Base Course
425.00
SY
$
$
-
1001
BF
Emulsion/Sand Crack Sealing
595.00
LF
$
$
-
1001
BG
Rubberized Hot Applied Crack Sealant
3,400.00
LF
$
$
-
1001
BH
Manhole Adjustment to Grade
4.00
EA
$
$
-
1001
BJ
Valve Box Adjustment
4.00
EA
$
$
-
1001
BK
Asphalt Pavement Patching
1,150.00
SY
$
$
-
1001
BL
Cracking and Seating of Concrete
425.00
SY-IN
$
$
-
1001
BM
MPDES General Permit (SWPPP)
2.00
EA
$
$
-
1001
BN
Paint Removal
1,250.00
SF
$
$
-
1001
BP
Crushed Aggregate Chip Seal
2,550.00
SY
$
$
-
1001
BQ
Cement Treated Base (4% Blend)
3,000.00
SY-IN
$
$
-
1001
BR
Cement Treated Base (6% Blend)
4,250.00
SY-IN
$
$
-
1001
BS
Silt Fence
1,000.00
SF
$
$
-

TOTAL ESTIMATED AMOUNT - BASIC YEAR

$
-

(ITEMS 1001AA THRU 1001BS)

OPTION YEAR 1 2009 THRU 2010

1002
AA
Remove Existing Concrete Curb and Gutter, and Sidewalk
680.00
SY
$
$
-
1002
AB
Trench Excavation
85.00
CY
$
$
-
1002
AC
Excavation and Embankment
500.00
CY
$
$
-
1002
AD
Graded Aggregate Base
1,190.00
TON
$
$
-
1002
AE
Borrow
85.00
TON
$
$
-
1002
AF
Topsoil/Topsoiling
3,750.00
SY
$
$
-
1002
AG
Drill Seeding and Mulching
2,125.00
SY
$
$
-
1002
AH
Hydraulic Seeding and Mulching
2,125.00
SY
$
$
-
1002
AJ
Asphalt Pavement, Grade A
25,000.00
SY-IN
$
$
-
1002
AK
Portland Cement Concrete Integral Curb and Gutter
1,500.00
LF
$
$
-
1002
AL
Portland Cement Concrete Sidewalk - 4" thick
6,800.00
SF
$
$
-
1002
AM
Portland Cement Concrete Sidewalk - 6" thick
850.00
SF
$
$
-
1002
AN
Reinforced Portland Cement Concrete Slab - 6" thick
638.00
SF
$
$
-
1002
AP
Reinforced Portland Cement Concrete Slab - 8" thick
850.00
SF
$
$
-
1002
AQ
Reinforced Portland Cement Concrete Slab - 10" thick
580.00
SF
$
$
-
1002
AR
Striping
39,695.00
SF
$
$
-
1002
AS
Woven Geotextile Fabric
1,275.00
SY
$
$
-
1002
AT
Non-Woven Geotextile Fabric
1,275.00
SY
$
$
-
1002
AU
Geogrid
1,275.00
SY
$
$
-
1002
AV
Petromat with Flood Coat
2,550.00
SY
$
$
-
1002
AW
Stabilized Construction
1,275.00
SY
$
$
-
1002
AX
Sub & Edge Drain
850.00
LF
$
$
-
1002
AY
Sub & Edge Drain Manhole Connections
9.00
LF
$
$
-
1002
AZ
Bituminous Pavement Pulverization
510.00
SY-IN
$
$
-
1002
BA
Remove Existing Asphalt Pavement - Full Depth
8,500.00
SY-IN
$
$
-
1002
BB
Remove Existing Asphalt or Concrete Pavement -Partial Depth
595.00
SY-IN
$
$
-
1002
BC
Remove Existing Concrete Pavement -Full Depth
298.00
SY-IN
$
$
-
1002
BD
Butt Joints
638.00
LF
$
$
-
1002
BE
Preparation of Existing Base Course
425.00
SY
$
$
-
1002
BF
Emulsion/Sand Crack Sealing
595.00
LF
$
$
-
1002
BG
Rubberized Hot Applied Crack Sealant
3,400.00
LF
$
$
-
1002
BH
Manhole Adjustment to Grade
4.00
EA
$
$
-
1002
BJ
Valve Box Adjustment
4.00
EA
$
$
-
1002
BK
Asphalt Pavement Patching
1,150.00
SY
$
$
-
1002
BL
Cracking and Seating of Concrete
425.00
SY-IN
$
$
-
1002
BM
MPDES General Permit (SWPPP)
2.00
EA
$
$
-
1002
BN
Paint Removal
1,250.00
SF
$
$
-
1002
BP
Crushed Aggregate Chip Seal
2,550.00
SY
$
$
-
1002
BQ
Cement Treated Base (4% Blend)
3,000.00
SY-IN
$
$
-
1002
BR
Cement Treated Base (6% Blend)
4,250.00
SY-IN
$
$
-
1002
BS
Silt Fence
1,000.00
SF
$
$
-

TOTAL ESTIMATED AMOUNT - OPTION YEAR 1

$
-

(ITEMS 1001AA THRU 1001BS)

OPTION YEAR 2 2010 THRU 2011

1003
AA
Remove Existing Concrete Curb and Gutter, and Sidewalk
680.00
SY
$
$
-
1003
AB
Trench Excavation
85.00
CY
$
$
-
1003
AC
Excavation and Embankment
500.00
CY
$
$
-
1003
AD
Graded Aggregate Base
1,190.00
TON
$
$
-
1003
AE
Borrow
85.00
TON
$
$
-
1003
AF
Topsoil/Topsoiling
3,750.00
SY
$
$
-
1003
AG
Drill Seeding and Mulching
2,125.00
SY
$
$
-
1003
AH
Hydraulic Seeding and Mulching
2,125.00
SY
$
$
-
1003
AJ
Asphalt Pavement, Grade A
22,000.00
SY-IN
$
$
-
1003
AK
Portland Cement Concrete Integral Curb and Gutter
1,500.00
LF
$
$
-
1003
AL
Portland Cement Concrete Sidewalk - 4" thick
6,800.00
SF
$
$
-
1003
AM
Portland Cement Concrete Sidewalk - 6" thick
850.00
SF
$
$
-
1003
AN
Reinforced Portland Cement Concrete Slab - 6" thick
638.00
SF
$
$
-
1003
AP
Reinforced Portland Cement Concrete Slab - 8" thick
850.00
SF
$
$
-
1003
AQ
Reinforced Portland Cement Concrete Slab - 10" thick
580.00
SF
$
$
-
1003
AR
Striping
39,695.00
SF
$
$
-
1003
AS
Woven Geotextile Fabric
1,275.00
SY
$
$
-
1003
AT
Non-Woven Geotextile Fabric
1,275.00
SY
$
$
-
1003
AU
Geogrid
1,275.00
SY
$
$
-
1003
AV
Petromat with Flood Coat
2,550.00
SY
$
$
-
1003
AW
Stabilized Construction
1,275.00
SY
$
$
-
1003
AX
Sub & Edge Drain
850.00
LF
$
$
-
1003
AY
Sub & Edge Drain Manhole Connections
9.00
LF
$
$
-
1003
AZ
Bituminous Pavement Pulverization
510.00
SY-IN
$
$
-
1003
BA
Remove Existing Asphalt Pavement - Full Depth
8,500.00
SY-IN
$
$
-
1003
BB
Remove Existing Asphalt or Concrete Pavement -Partial Depth
595.00
SY-IN
$
$
-
1003
BC
Remove Existing Concrete Pavement -Full Depth
298.00
SY-IN
$
$
-
1003
BD
Butt Joints
638.00
LF
$
$
-
1003
BE
Preparation of Existing Base Course
425.00
SY
$
$
-
1003
BF
Emulsion/Sand Crack Sealing
595.00
LF
$
$
-
1003
BG
Rubberized Hot Applied Crack Sealant
3,400.00
LF
$
$
-
1003
BH
Manhole Adjustment to Grade
4.00
EA
$
$
-
1003
BJ
Valve Box Adjustment
4.00
EA
$
$
-
1003
BK
Asphalt Pavement Patching
1,150.00
SY
$
$
-
1003
BL
Cracking and Seating of Concrete
425.00
SY-IN
$
$
-
1003
BM
MPDES General Permit (SWPPP)
2.00
EA
$
$
-
1003
BN
Paint Removal
1,250.00
SF
$
$
-
1003
BP
Crushed Aggregate Chip Seal
2,550.00
SY
$
$
-
1003
BQ
Cement Treated Base (4% Blend)
3,000.00
SY-IN
$
$
-
1003
BR
Cement Treated Base (6% Blend)
4,250.00
SY-IN
$
$
-
1003
BS
Silt Fence
1,000.00
SF
$
$
-

TOTAL ESTIMATED AMOUNT - OPTION YEAR 2

$
-

(ITEMS 1001AA THRU 1001BS)

OPTION YEAR 3 2011 THRU 2012

1004
AA
Remove Existing Concrete Curb and Gutter, and Sidewalk
680.00
SY
$
$
-
1004
AB
Trench Excavation
85.00
CY
$
$
-
1004
AC
Excavation and Embankment
500.00
CY
$
$
-
1004
AD
Graded Aggregate Base
1,190.00
TON
$
$
-
1004
AE
Borrow
85.00
TON
$
$
-
1004
AF
Topsoil/Topsoiling
3,750.00
SY
$
$
-
1004
AG
Drill Seeding and Mulching
2,125.00
SY
$
$
-
1004
AH
Hydraulic Seeding and Mulching
2,125.00
SY
$
$
-
1004
AJ
Asphalt Pavement, Grade A
22,000.00
SY-IN
$
$
-
1004
AK
Portland Cement Concrete Integral Curb and Gutter
1,500.00
LF
$
$
-
1004
AL
Portland Cement Concrete Sidewalk - 4" thick
6,800.00
SF
$
$
-
1004
AM
Portland Cement Concrete Sidewalk - 6" thick
850.00
SF
$
$
-
1004
AN
Reinforced Portland Cement Concrete Slab - 6" thick
638.00
SF
$
$
-
1004
AP
Reinforced Portland Cement Concrete Slab - 8" thick
850.00
SF
$
$
-
1004
AQ
Reinforced Portland Cement Concrete Slab - 10" thick
580.00
SF
$
$
-
1004
AR
Striping
39,695.00
SF
$
$
-
1004
AS
Woven Geotextile Fabric
1,275.00
SY
$
$
-
1004
AT
Non-Woven Geotextile Fabric
1,275.00
SY
$
$
-
1004
AU
Geogrid
1,275.00
SY
$
$
-
1004
AV
Petromat with Flood Coat
2,550.00
SY
$
$
-
1004
AW
Stabilized Construction
1,275.00
SY
$
$
-
1004
AX
Sub & Edge Drain
850.00
LF
$
$
-
1004
AY
Sub & Edge Drain Manhole Connections
9.00
LF
$
$
-
1004
AZ
Bituminous Pavement Pulverization
510.00
SY-IN
$
$
-
1004
BA
Remove Existing Asphalt Pavement - Full Depth
8,500.00
SY-IN
$
$
-
1004
BB
Remove Existing Asphalt or Concrete Pavement -Partial Depth
595.00
SY-IN
$
$
-
1004
BC
Remove Existing Concrete Pavement -Full Depth
298.00
SY-IN
$
$
-
1004
BD
Butt Joints
638.00
LF
$
$
-
1004
BE
Preparation of Existing Base Course
425.00
SY
$
$
-
1004
BF
Emulsion/Sand Crack Sealing
595.00
LF
$
$
-
1004
BG
Rubberized Hot Applied Crack Sealant
3,400.00
LF
$
$
-
1004
BH
Manhole Adjustment to Grade
4.00
EA
$
$
-
1004
BJ
Valve Box Adjustment
4.00
EA
$
$
-
1004
BK
Asphalt Pavement Patching
1,150.00
SY
$
$
-
1004
BL
Cracking and Seating of Concrete
425.00
SY-IN
$
$
-
1004
BM
MPDES General Permit (SWPPP)
2.00
EA
$
$
-
1004
BN
Paint Removal
1,250.00
SF
$
$
-
1004
BP
Crushed Aggregate Chip Seal
2,550.00
SY
$
$
-
1004
BQ
Cement Treated Base (4% Blend)
3,000.00
SY-IN
$
$
-
1004
BR
Cement Treated Base (6% Blend)
4,250.00
SY-IN
$
$
-
1004
BS
Silt Fence
1,000.00
SF
$
$
-

TOTAL ESTIMATED AMOUNT - OPTION YEAR 3

$
-

(ITEMS 1001AA THRU 1001BS)

TOTAL ESTIMATED AMOUNT - BASIC + OPTION YEARS 1,2, & 3

(ITEMS 1001AA THRU 1004BS)

$
-

Section C - Descriptions and Specifications

DESCRIPTIONS AND SPECS

C-1 SPECIFICATIONS, STANDARDS, AND DRAWINGS IAW FAR 11-201

Furnish all labor, materials, supervision, quality control, testing, equipment, and transportation necessary to perform the work required by the drawings, statement of work, and specifications applicable to Malmstrom AFB, Project Number NZAS 08-1021, Dated Feb 2008 and that are identified as attachments to this solicitation in Section J hereof.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
1001
Destination
Government
Destination
Government
1002
Destination
Government
Destination
Government
1003
Destination
Government
Destination
Government
1004
Destination
Government
Destination
Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC
1001
POP 01-APR-2008 TO

31-MAR-2009

N/A
F2W3D5 341CES/CECR-BASE SRMC

KEN MURPHY

39 78TH ST N BLDG 470

MALMSTROM AFB MT 59402

406-731-6865

FOB: Destination F2W3D5

1002
POP 01-APR-2009 TO

31-MAR-2010

N/A
(SAME AS PREVIOUS LOCATION)

F2W3D5

1003
POP 01-APR-2010 TO

31-MAR-2011

N/A
(SAME AS PREVIOUS LOCATION)

F2W3D5

1004
POP 01-APR-2011 TO

31-MAR-2012

N/A
(SAME AS PREVIOUS LOCATION)

F2W3D5

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the negotiated period of performance as specified in each delivery order, which includes the winter exclusion of 1 Nov to 1 Apr of each fiscal year. The time stated for completion shall include final cleanup of the premises.

Note 1: Funding will be provided to each delivery order, period of performance will be negotiated for each delivery order. Bonding will be required for each delivery order. This shall be applicable to all CLIN’s and sub-clin’s 1001 thru 1004BS.

Note 2: The following CLINs and/or sub-clins list below shall be referenced and applied to the corresponding listed year of award, each year of award shall be for a period of 365 calendar days from date of award; to include the winter exclusion period of 1 Nov to 1 Apr of each year.

CLINS

PERIOD OF AWARD

1001AA thru 1001BS Base Year

1002AA thru 1002BS 1st Option Year

1003AA thru 1003BS 2nd Option Year

1004AA thru 1004BS 3rd Option Year

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $485.88 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

Section G - Contract Administration Data

CLAUSES INCORPORATED BY FULL TEXT

252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (MAR 2007)

(a) Definitions. As used in this clause--

(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.

(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using one of the electronic forms provided for in paragraph (b) of this clause.

(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.

(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests using one of the following electronic forms:

(1) Wide Area WorkFlow-Receipt and Acceptance (WAWF-RA). Information regarding WAWF-RA is available on the Internet at https://wawf.eb.mil.

(2) Web Invoicing System (WInS). Information regarding WInS is available on the Internet at https://ecweb.dfas.mil.

(3) American National Standards Institute (ANSI) X.12 electronic data interchange (EDI) formats.

(i) Information regarding EDI formats is available on the Internet at http://www.X12.org.

(ii) EDI implementation guides are available on the Internet at http:// www.dod.mil/dfas/contractorpay/electroniccommerce.html.

(4) Another electronic form authorized by the Contracting Officer.

(c) The Contractor may submit a payment request in non-electronic form only when--

(1) DoD is unable to receive a payment request in electronic form; or

(2) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment.

(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.

(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.

(End of clause)

CLAUSES INCORPORATED BY FULL TEXT

Electronic invoicing is now required in accordance with DFARS 252.232-7003. You will need the following information in order to complete your invoices: Paying Office DODAAC; 503000; Issuing Office DODAAC: FA4626; Inspectors DODAAC: F2W3D5; Email addresses: Contracting Officer: Russell.Bryan@Malmstrom.AF.Mil; Contract Administrator: Mark.Jefferson@Malmstrom.AF.mil; Engineer/Inspector: Sean.Cockrell@Malmstrom.AF.Mil; FSC:Z222

NOTE: All projects undertaken commensurate with this solicitation and resultant contract will be issued by Delivery Order. Funds will only be applied to each Delivery Order and not to parent contract. As such, all invoicing will be against the applicable Delivery Order. Any invoices submitted against a delivery order for items not ordered or chargable aginst the Delivery Order will be rejected.

(End of Clause)

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.202-1
Definitions
JUL 2004
52.203-3
Gratuities
APR 1984
52.203-5
Covenant Against Contingent Fees
APR 1984
52.203-6
Restrictions On Subcontractor Sales To The Government
SEP 2006
52.203-7
Anti-Kickback Procedures
JUL 1995
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
JAN 1997
52.203-10
Price Or Fee Adjustment For Illegal Or Improper Activity
JAN 1997
52.203-12
Limitation On Payments To Influence Certain Federal Transactions
SEP 2007
52.204-4
Printed or Copied Double-Sided on Recycled Paper
AUG 2000
52.204-7
Central Contractor Registration
JUL 2006
52.209-6
Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
SEP 2006
52.215-2
Audit and Records--Negotiation
JUN 1999
52.215-8
Order of Precedence--Uniform Contract Format
OCT 1997
52.217-8
Option To Extend Services
NOV 1999
52.219-8
Utilization of Small Business Concerns
MAY 2004
52.219-9
Small Business Subcontracting Plan
NOV 2007
52.222-1
Notice To The Government Of Labor Disputes
FEB 1997
52.222-3
Convict Labor
JUN 2003
52.222-4
Contract Work Hours and Safety Standards Act - Overtime Compensation
JUL 2005
52.222-6
Davis Bacon Act
JUL 2005
52.222-7
Withholding of Funds
FEB 1988
52.222-8
Payrolls and Basic Records
FEB 1988
52.222-9
Apprentices and Trainees
JUL 2005
52.222-10
Compliance with Copeland Act Requirements
FEB 1988
52.222-11
Subcontracts (Labor Standards)
JUL 2005
52.222-12
Contract Termination-Debarment
FEB 1988
52.222-13
Compliance with Davis-Bacon and Related Act Regulations.
FEB 1988
52.222-14
Disputes Concerning Labor Standards
FEB 1988
52.222-15
Certification of Eligibility
FEB 1988
52.222-21
Prohibition Of Segregated Facilities
FEB 1999
52.222-26
Equal Opportunity
MAR 2007
52.222-27
Affirmative Action Compliance Requirements for Construction
FEB 1999
52.222-35
Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans
SEP 2006
52.222-36
Affirmative Action For Workers With Disabilities
JUN 1998
52.222-37
Employment Reports On Special Disabled Veterans, Veterans Of The Vietnam Era, and Other Eligible Veterans
SEP 2006
52.223-5
Pollution Prevention and Right-to-Know Information
AUG 2003
52.223-6
Drug-Free Workplace
MAY 2001
52.223-11
Ozone-Depleting Substances
MAY 2001
52.223-14
Toxic Chemical Release Reporting
AUG 2003
52.225-13
Restrictions on Certain Foreign Purchases
FEB 2006
52.227-1
Authorization and Consent
DEC 2007
52.227-2
Notice And Assistance Regarding Patent And Copyright Infringement
DEC 2007
52.227-4
Patent Indemnity-Construction Contracts
DEC 2007
52.228-2
Additional Bond Security
OCT 1997
52.228-5
Insurance - Work On A Government Installation
JAN 1997
52.228-11
Pledges Of Assets
FEB 1992
52.228-12
Prospective Subcontractor Requests for Bonds
OCT 1995
52.228-14
Irrevocable Letter of Credit
DEC 1999
52.228-15
Performance and Payment Bonds--Construction
NOV 2006
52.229-3
Federal, State And Local Taxes
APR 2003
52.232-5
Payments under Fixed-Price Construction Contracts
SEP 2002
52.232-17
Interest
JUN 1996
52.232-18
Availability Of Funds
APR 1984
52.232-23
Assignment Of Claims
JAN 1986
52.232-27
Prompt Payment for Construction Contracts
SEP 2005
52.232-33
Payment by Electronic Funds Transfer--Central Contractor Registration
OCT 2003
52.233-1
Disputes
JUL 2002
52.233-3
Protest After Award
AUG 1996
52.236-2
Differing Site Conditions
APR 1984
52.236-3
Site Investigation and Conditions Affecting the Work
APR 1984
52.236-5
Material and Workmanship
APR 1984
52.236-6
Superintendence by the Contractor
APR 1984
52.236-7
Permits and Responsibilities
NOV 1991
52.236-8
Other Contracts
APR 1984
52.236-9
Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10
Operations and Storage Areas
APR 1984
52.236-11
Use and Possession Prior to Completion
APR 1984
52.236-12
Cleaning Up
APR 1984
52.236-13
Accident Prevention
NOV 1991
52.236-14
Availability and Use of Utility Services
APR 1984
52.236-15
Schedules for Construction Contracts
APR 1984
52.236-17
Layout of Work
APR 1984
52.236-21
Specifications and Drawings for Construction
FEB 1997
52.236-21 Alt I
Specifications and Drawings for Construction (Feb 1997) - Alternate I
APR 1984
52.236-26
Preconstruction Conference
FEB 1995
52.242-13
Bankruptcy
JUL 1995
52.242-14
Suspension of Work
APR 1984
52.243-4
Changes
JUN 2007
52.244-5
Competition In Subcontracting
DEC 1996
52.244-6
Subcontracts for Commercial Items
MAR 2007
52.246-21
Warranty of Construction
MAR 1994
52.248-3
Value Engineering-Construction
SEP 2006
52.249-2
Termination For Convenience Of The Government (Fixed-Price)
MAY 2004
52.249-2 Alt I
Termination for Convenience of the Government (Fixed-Price) (May 2004) - Alternate I
SEP 1996
52.249-10
Default (Fixed-Price Construction)
APR 1984
52.252-2
Clauses Incorporated By Reference
FEB 1998
52.252-6
Authorized Deviations In Clauses
APR 1984
52.253-1
Computer Generated Forms
JAN 1991
252.203-7001
Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies
DEC 2004
252.204-7003
Control Of Government Personnel Work Product
APR 1992
252.204-7004 Alt A
Central Contractor Registration (52.204-7) Alternate A
SEP 2007
252.205-7000
Provision Of Information To Cooperative Agreement Holders
DEC 1991
252.209-7004
Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country
DEC 2006
252.225-7012
Preference For Certain Domestic Commodities
JAN 2007
252.226-7001
Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns
SEP 2004
252.236-7000
Modification Proposals-Price Breakdown
DEC 1991
252.243-7001
Pricing Of Contract Modifications
DEC 1991
252.247-7023
Transportation of Supplies by Sea
MAY 2002
252.247-7024
Notification Of Transportation Of Supplies By Sea
MAR 2000

52.216-18 Ordering. (OCT 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from 365 days from the date of award or 365 days from the date an option is exercised. Whichever is later.

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

(End of clause)

52.216-19 Order Limitations. (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,000.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor:

(1) Any order for a delivery order in excess of $300,000.00;

(2) Any order for a combination of delivery orders in excess of $500,000.00; or

(3) A series of orders from the same ordering office within 14 days that together call for quantities exceeding the limitation in subparagraph (1) or (2) above.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) above.

(d) Notwithstanding paragraphs (b) and (c) above, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within One day after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

(End of clause)

52.216-21 REQUIREMENTS (OCT 1995)

(a) This is a requirements contract applicable to Malmstrom AFB, for the supplies or services specified in the attached specifications only (NZAS 08-1021) dated Feb 2008 and shall not include other projects, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government's requirements do not result in orders in the quantities described as "estimated'' or "maximum" in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(c) Except as this contract otherwise provides, the Government shall order from the Contractor all the supplies or services specified in the Schedule that are required to be purchased by the Government activity or activities specified in the Schedule.

(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.

(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing for the accelerated delivery, the Government may acquire the urgently required goods or services from another source.

(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after after 31 March 2012 or until all delivery orders issued on or before 31 March 2012 are closed out, whichever is later.

(End of clause)

52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 15 Calendar days; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 calendar days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 4 Years and 6 Months (End of clause)

52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS CONCERNS (JUL 2005)

(a) Definition. HUBZone small business concern, as used in this clause, means a small business concern that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration.

(b) Evaluation preference. (1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except--

(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and

(ii) Otherwise successful offers from small business concerns.

(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.

(3) A concern that is both a HUBZone small business concern and a small disadvantaged business concern will receive the benefit of both the HUBZone small business price evaluation preference and the small disadvantaged business price evaluation adjustment (see FAR clause 52.219-23). Each applicable price evaluation preference or adjustment shall be calculated independently against an offeror's base offer.

These individual preference amounts shall be added together to arrive at the total evaluated price for that offer.

(c) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes. The agreements in paragraph (d) of this clause do not apply if the offeror has waived the evaluation preference.

___ Offeror elects to waive the evaluation preference.

(d) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for

(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;

(2) Supplies (other than procurement from a nonmanufacturer of such supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;

(3) General construction, at least 15 percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other HUBZone small business concerns; or

(4) Construction by special trade contractors, at least 25 percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other HUBZone small business concerns.

(e) A HUBZone joint venture agrees that in the performance of the contract, the applicable percentage specified in paragraph (d) of this clause will be performed by the HUBZone small business participant or participants.

(f) A HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business manufacturer concerns. This paragraph does not apply in connection with construction or service contracts.

(End of clause)

52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED PRODUCTS (AUG 2000)

(a) Definitions. As used in this clause--

Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall--

(1) Estimate the percentage of the total recovered material used in contract performance, including, if applicable, the percentage of postconsumer material content; and

(2) Submit this estimate to Mark Jefferson 341st Contracting Squadron, 7015 Goddard Drive, Bldg 145, Malmstrom AFB, Montana 59402-6863.

(End of clause)

52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (JAN 2005)

(a) Definitions. As used in this clause--

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means--

(1) An unmanufactured construction material mined or produced in the United States; or

(2) A construction material manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.

Foreign construction material means a construction material other than a domestic construction material.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to the construction material or components listed by the Government as follows: NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price (dollars) \1\

Item 1

Foreign construction material

Domestic construction material

Item 2

Foreign construction material

Domestic construction material

Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.

Include other applicable supporting information.

(End of clause)

52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

(End of clause)

52.244-2 SUBCONTRACTS (JUN 2007)

(a) Definitions. As used in this clause--

Approved purchasing system means a Contractor's purchasing system that has been reviewed and approved in accordance with Part 44 of the Federal Acquisition Regulation (FAR).

Consent to subcontract means the Contracting Officer's written consent for the Contractor to enter into a particular subcontract.

Subcontract means any contract, as defined in FAR Subpart 2.1, entered into by a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.

purchase orders.

(b) When this clause is included in a fixed-price type contract, consent to subcontract is required only on unpriced contract actions (including unpriced modifications or unpriced delivery orders), and only if required in accordance with paragraph (c) or (d) of this clause.

(c) If the Contractor does not have an approved purchasing system, consent to subcontract is required for any subcontract that—

(1) Is of the cost-reimbursement, time-and-materials, or labor-hour type; or

(2) Is fixed-price and exceeds—

(i) For a contract awarded by the Department of Defense, the Coast Guard, or the National Aeronautics and Space Administration, the greater of the simplified acquisition threshold or 5 percent of the total estimated cost of the contract; or

(ii) For a contract awarded by a civilian agency other than the Coast Guard and the National Aeronautics and Space Administration, either the simplified acquisition threshold or 5 percent of the total estimated cost of the contract.

(d) If the Contractor has an approved purchasing system, the Contractor nevertheless shall obtain the Contracting Officer’s written consent before placing the following subcontracts:

SEE PARAGRAPH (2) (i) (e)(1) The Contractor shall notify the Contracting Officer reasonably in advance of placing any subcontract or modification thereof for which consent is required under paragraph (b), (c), or (d) of this clause, including the following information:

(i) A description of the supplies or services to be subcontracted.

(ii) Identification of the type of subcontract to be used.

(iii) Identification of the proposed subcontractor.

(iv) The proposed subcontract price.

(v) The subcontractor’s current, complete, and accurate cost or pricing data and Certificate of Current Cost or Pricing Data, if required by other contract provisions.

(vi) The subcontractor’s Disclosure Statement or Certificate relating to Cost Accounting Standards when such data are required by other provisions of this contract.

(vii) A negotiation memorandum reflecting—

(A) The principal elements of the subcontract price negotiations;

(B) The most significant considerations controlling establishment of initial or revised prices;

(C) The reason cost or pricing data were or were not required;

(D) The extent, if any, to which the Contractor did not rely on the subcontractor’s cost or pricing data in determining the price objective and in negotiating the final price;

(E) The extent to which it was recognized in the negotiation that the subcontractor’s cost or pricing data were not accurate, complete, or current; the action taken by the Contractor and the subcontractor; and the effect of any such defective data on the total price negotiated;

(F) The reasons for any significant difference between the Contractor’s price objective and the price negotiated; and

(G) A complete explanation of the incentive fee or profit plan when incentives are used. The explanation shall identify each critical performance element, management decisions used to quantify each incentive element, reasons for the incentives, and a summary of all trade-off possibilities considered.

(2) The Contractor is not required to notify the Contracting Officer in advance of entering into any subcontract for which consent is not required under paragraph (c), (d), or (e) of this clause.

(f) Unless the consent or approval specifically provides otherwise, neither consent by the Contracting Officer to any subcontract nor approval of the Contractor’s purchasing system shall constitute a determination—

(1) Of the acceptability of any subcontract terms or conditions;

(2) Of the allowability of any cost under this contract; or

(3) To relieve the Contractor of any responsibility for performing this contract.

(g) No subcontract or modification thereof placed under this contract shall provide for payment on a cost-plus-a-percentage-of-cost basis, and any fee payable under cost-reimbursement type subcontracts shall not exceed the fee limitations in FAR 15.404-4(c)(4)(i).

(h) The Contractor shall give the Contracting Officer immediate written notice of any action or suit filed and prompt notice of any claim made against the Contractor by any subcontractor or vendor that, in the opinion of the Contractor, may result in litigation related in any way to this contract, with respect to which the Contractor may be entitled to reimbursement from the Government.

(i) The Government reserves the right to review the Contractor’s purchasing system as set forth in FAR Subpart 44.3.

(j) Paragraphs (c) and (e) of this clause do not apply to the following subcontracts, which were evaluated during negotiations:

NONE

(End of clause)

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

ALL DRAWINGS AND/OR BLUEPRINTS TO BE PROVIDED UPON ISSUANCE OF EACH DELIVERY ORDER.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

LIST OF ATTACHMENTS

SECTION J

LIST OF ATTACHMENTS

(All listed documents are at the end of this document)

ITEM NR

SPECIFICATIONS, STANDARDS AND/OR ATTACHMENTS

Attach 1 Technical Specifications, Pavements Requirements Contract , Malmstrom AFB, MT, Project Number NZAS 08-1021, dated Feb, 2008, Cover page and Section 01000-1 thru 02120-1.

Attach 2 Material Submittal Schedule, dated Feb 2, 2007, pages SS-1 thru SS-3.

Attach 3 Wage Determinations MT080001 MT1, Modification 0, dated 02/08/2008, pages 1 thru 9.

Attach 4 Past Performance Questionaire.

NOTE!! IT IS THE RESPONSIBILITY OF THE OFFEROR TO SEND THE CUSTOMER SATISFACTION SURVEY TO THE PREVIOUS CUSTOMERS WHICH THE OFFEROR HAS PROVIDED CONSTRUCTION SERVICES DURING THE PAST THREE YEARS. THE CUSTOMER MUST COMPLETE THE SURVEY, THEN SEND THE COMPLETED SURVEY TO THE FOLLOWING ADDRESS BY 2 April 2008, BUT NOT LATER THAN THE PROPOSAL CLOSING DATE OF 14 April 2008, 2:00 PM MOUNTAIN STANDARD TIME.

Contracting Squadron

341st CONS/LGCA, Attn:Mark Jefferson

7015 Goddard Drive

Malmstrom AFB, MT 59402-6863

THE COMPLETED SURVEY MUST CONTAIN THE CUSTOMERS FULL NAME, ADDRESS, TELEPHONE NUMBER, TYPE OF CONSTRUCTION WORK THAT WAS PERFORMED, AND THE DATE THE WORK WAS COMPLETED.

CLAUSES INCORPORATED BY FULL TEXT

J-500 PRESENT/PAST PERFORMANCE EVALUATION CONTRACTOR PERFORMANCE QUESTIONNAIRE

When filled in this document is source selection sensitive information iaw FAR 3.104

SECTION 1: TO BE COMPLETED BY THE OFFEROR AND PROVIDED TO THE CUSTOMER REFERENCED

Name of Firm being evaluated: ___________________________________

Project Title and Location: _______________________________________

Project dollar value: ____________________________________________

Year Completed: _______________________________________________

Project Manager: _______________________________________________

SECTION 2: TO BE COMPLETED BY THE CUSTOMER REFERENCED AND MAILED, HAND-DELIVERED, EMAILED OR FAXED DIRECTLY TO:

341 CONS/LGCA

FAX: (406) 731-4005/3748

ATTN: Mark Jefferson

EMAIL: mark.jefferson@malmstrom.af.mil

7015 Goddard Avenue

DUTY PHONE (406) 731-4111

Malmstrom AFB, MT 59402-6863

OVERVIEW: The firm shown above is submitting a proposal on a Malmstrom AFB construction/service project and provided your name as a customer reference. Part of our evaluation process requires information on the firm’s past performance. Your participation is important to us and responses are required by the date proposals are due; 14 April 2008, for inclusion in our evaluation. Your assistance is greatly appreciated.

SECTION 3: EVALUATION

Please indicate your satisfaction with the contractor’s performance by placing an “X” in the appropriate block using the scale provided to the right of each question. This scale is defined as follows:

CODE

PERFORMANCE LEVEL

E EXCEPTIONAL - The contractor’s performance meets contractual requirements and exceeds many (requirements) to the Government’s or customer’s benefit. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

VG

VERY GOOD- The contractor’s performance meets contractual requirements and exceeds some (requirements) to the Government’s or customer’s benefit.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .