The attached document is responses to the questions received after solicitation. Document is dated 30 May 2019
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_3_19Q0075_Q&A_12_June_19.pdf | ||
| Q&A_Amendment_Acknowledgement.docx | DOCX document | |
| FA462519Q0075_Q&A_5_June_2019.pdf | ||
| FA462519Q0075_Atch_4_Clauses_dtd_22May19.pdf | ||
| FA462519Q0075_Atch_2_Bid_Schedule.xlsx | XLSX spreadsheet | |
| FA462519Q0075_Atch_3_PPQ.pdf | ||
| FA462519Q0075_Atch_1_SOW_21May19.pdf | ||
| FA462519Q0075_Combo_22May19.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B2 Wing Maintenance Stand
FA462519Q0075
30 May 2019
Q & A
Q: Is the design intent that the stands to be positioned along the trailing edges by the flight control surfaces, one complete set pilot left and another complete set pilot right as indicated in provided sketch
A. The stands will be positioned just forward of the flight controls. One set consists of one left wing stand assembly, and one right wing stand assembly, they shall be mirror images of each other.
(SOW Para 1. Introduction)
Q: Is there a preferred platform working height?
A. 35”
Q: Will the stands need to have a capability for vertical adjustment, if so how much?
A. No
Q: Please confirm, 3 stairway locations required per side, total 6 stairways
A. Correct, 3 stairway locations per side, total 6 stairways( Drawing)
Q: As indicated, should the stairways be the full width of the deck?
A. Yes (reference SOW drawing)
Q: Please indicate the depth of the pull out drawers, 100 wide x 50 long x ?? deep
A. 3 inches
Q: Please indicate the desired internal dimensions of the forward shelving. Also should the lower shelf be at deck level or higher
A. The internal dimensions should be 1’, 5 7/8” deep and the full length of the outboard stand wing. The bottom shelf should be 24” off the platform and the top shelf to be 42”off the platform (Drawing)
Q: Please indicate hanger power supply available and air supply available.
A: Hanger has all power/air supply capabilities. Stand should have electrical cord to plug into a 220 V outlet, and a compressed air manifold that will attach to shop air.
Q: Please confirm that Past Performance responses may include Commercial (Non Government) Contract Customers. If allowed, will Commercial Contracts receive equivalent evaluation as DOD contracts?
A: Commercial Contract Customers will receive equivalent evaluation on this solicitation as long as it meets the recency and relevancy evaluation criteria of being same/similar in technical scope as outlined in Attachment 4 of the solicitation .
Q: What are the payment terms?
A: Net 30