Attached is a correction to Question 1. Please note the correct percentage is 50 .
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions Answers for Pre-Solicitation | — | |
| Question 3 answer.docx | DOCX document | |
| Questions Answers for Pre-Solicitation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Architectural & Engineering (A&E) Services
FA4621-12-R-0005A
5 April 2012
Questions & Answers
QUESTION #1 - We will be the Prime (contractor); however, some of our sub-consultants are not able to be certified as a Small Business. Does the Pre-solicitation require all team members to be Small Business?
ANSWER #1 - In accordance with the FAR Clause 52.219-14, your company shall perform at least 50 percent of the cost of the contract, not including the cost of materials, with its own employees.