Questions Answers for Pre-Solicitation.docx

DOCX document 13 KB Posted

Attached to
Architectural & Engineering (A&E) Services
Solicitation number
FA4621-12-R-0005A
Issued by

About this file

Attached is a correction to Question 1. Please note the correct percentage is 50 .

View the file

Other files

File Type Posted
Questions Answers for Pre-Solicitation —
Question 3 answer.docx DOCX document
Questions Answers for Pre-Solicitation.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Architectural & Engineering (A&E) Services

FA4621-12-R-0005A

5 April 2012

Questions & Answers

QUESTION #1 - We will be the Prime (contractor); however, some of our sub-consultants are not able to be certified as a Small Business. Does the Pre-solicitation require all team members to be Small Business?

ANSWER #1 - In accordance with the FAR Clause 52.219-14, your company shall perform at least 50 percent of the cost of the contract, not including the cost of materials, with its own employees.