FA4620-15-R-A007_0002_Answer_Questions.pdf

PDF 142 KB Posted

Attached to
Elevator Maintenance Services Federal contract opportunity
Solicitation number
FA4620-15-R-A007
Issued by
Department of the Air Force Air Mobility Command

About this file

Amendment 2 - This is an amendment to answer questions received on 4 June 2015.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The Solicitation is amended to add answ ers to questions received on 4 June 2015.

A copy of this Amendment must be signed and returned w ith the contractor`s proposal.

Please remember to complete Block 8 and 15 of this Amendment.

POC: SSgt Zachery Ray CO: Edw ard C. Campbell

Phone: 509-247-2608 Phone: 509-247-1970

Email: zachery.ray@us.af.mil Email: edw ard.compbell.2@us.af.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Jun-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA4620-15-R-A007

X 9B. DATED (SEE ITEM 11)

19-May-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Jun-2015

CODE

92 CONTRACTING SQUADRON

BLDG 2451

110 W ENT ST

STE 200

FAIRCHILD AFB WA 99011-8568

FA4620 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA4620-15-R-A007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

Elevator Maintenance Questions – Received 4 June 2015

1. In the Quality Assurance Surveillance Plan document, there is a matrix for customer complaints. Please define what a customer complaint is.

Answer: A customer complaint is an input from a customer, and that can be either an elevator user or the

Contracting Officer's Representative (COR), that alleges a violation of the performance objectives in the Service

Summary. Each potential customer complaint is evaluated by the COR, and if need be by the Contract Specialist

(CS) and Contracting Officer (CO) for the contract. The CO makes the final determination.

Example 1: If the successful offeror did not clean up the work site and equipment spaces after performing maintenance (para 1.3.4. of the PWS) that would be a valid customer complaint.

2. What is the consequence if the performance threshold is not met?

Answer: In the very worst case it could lead to termination or not exercising the contract option. This would only be the case if there was a long history of the contractor not meeting requirements. In most cases it simply affects the respective company's past performance.

3. The Performance Work Statement (PWS) says, in regards to obsolescence, that “Any part, component or assembly unavailable from the manufacturer due to obsolescence or age of the equipment, remains the contractor’s responsibility to obtain an engineered equivalent product from a commercial source”. Other government contracts have similar language, but allow the Contractor to submit a request for the government to pay the difference between the new part and the obsolete part. Would you take exception/clarification to this statement?

Answer: The paragraph mentioning obsolescence is para 1.2.5. and refers to items that are normally excluded from routine service and inspections. Those items, including the total cost of parts and labor are not included under the normal service CLIN but are included under the "Excluded Services) CLIN. The government is responsible for reimbursing the contractor the total cost of the part, not just the difference between the new part and the obsolete part.

4. Section 1.3.5 of the PWS states that all required tests and inspections must be performed by a Qualified Elevator

Inspector. This severely limits who can perform testing on the elevator. All of our mechanics are licensed to test elevators but do not hold a QEI. Can this section be amended?

Answer: We have received permission to rephrase para 1.3.5 as follows: "1.3.5. The Contractor shall perform all required inspections and tests in accordance with ASME A17.1, Appendix N. All inspections and tests shall be performed by properly trained, qualified, and licensed inspectors. Elevator repairer technicians that are separately licensed to test elevators may perform routine inspections; however, five year tests shall be performed by a

Qualified Elevator Inspector (QEI). The first annual test shall include the five-(5)-year test for all traction and roped hydraulic elevators regardless of due date. The three- (3) - year test shall be scheduled in conjunction with the annual test two years later from the first annual test."

FA4620-15-R-A007

5. Section 1.4 in the PWS states that “Routine emergency service calls shall be included in the full maintenance service CLIN on the pricing schedule”. Does this include routine and emergency service calls during hours that fall outside of your “Hours of Operation” listed in section 4.3?

Answer: Yes, regardless of the time the service call occurs, the costs the offeror expects to incur must be included in the full service CLIN.

(End of Summary of Changes)