CLIN ITEM QUANTITY UNIT UNIT PRICE TOTAL

0001 HSCI Iron Anodes w/200 #8 HMWPE 80 EA -$

0002 Graphite Anodes w/200 #8 HMWPE 8 EA -$

0003 HMWPE #4 Wire 230 LF -$

0004 Borehole / Drilling 2000 LF -$

0005 Coke Breeze 100lb bag 284 EA -$

0006 Bentonite Hole Plug 50 lb bag 110 EA -$

0007 Backfill 793 LF -$

0008 Anode Centralizers 160 EA -$

0009 Rectifier-LF (18V/16A) 10 EA -$

0010 Rectifier-MAF (48V/30A) 1 EA -$

0011 1" PVC Vent Pipe 2000 LF -$

0012 Mobilization 25 mile round trip 10 EA -$

0013 Mobilization Each additional 5 miles 136 EA -$

0014 Wyoming DEQ Inspection 5 EA -$

TOTAL - BASE YEAR -$

BASE YEAR

Bid Schedule (17-1014)

Atch 2, Bid Schedule

Base Year

1001 HSCI Iron Anodes w/200 #8 HMWPE 50 EA -$

1002 Graphite Anodes w/200 #8 HMWPE 40 EA -$

1003 HMWPE #4 Wire 270 LF -$

1004 Borehole / Drilling 2040 LF -$

1005 Coke Breeze 100lb bag 294 EA -$

1006 Bentonite Hole Plug 50 lb bag 110 EA -$

1007 Backfill 793 LF -$

1008 Anode Centralizers 164 EA -$

1009 Rectifier-LF (18V/16A) 9 EA -$

1010 Rectifier-MAF (48V/30A) 1 EA -$

1011 1" PVC Vent Pipe 2040 LF -$

1012 Mobilization 25 mile round trip 10 EA -$

1013 Mobilization Each additional 5 miles 184 EA -$

1014 Wyoming DEQ Inspection 1 EA -$

TOTAL - OPTION YEAR 1 -$

OPTION YEAR ONE

Bid Schedule (17-1014)

Option Year 1

2001 HSCI Iron Anodes w/200 #8 HMWPE 48 EA -$

2002 Graphite Anodes w/200 #8 HMWPE 34 EA -$

2003 HMWPE #4 Wire 250 LF -$

2004 Borehole / Drilling 1840 LF -$

2005 Coke Breeze 100lb bag 268 EA -$

2006 Bentonite Hole Plug 50 lb bag 100 EA -$

2007 Backfill 716 LF -$

2008 Anode Centralizers 148 EA -$

2009 Rectifier-LF (18V/16A) 9 EA -$

2010 Rectifier-MAF (48V/30A) 2 EA -$

2011 1" PVC Vent Pipe 1840 LF -$

2012 Mobilization 25 mile round trip 10 EA -$

2013 Mobilization Each additional 5 miles 348 EA -$

2014 Wyoming DEQ Inspection 1 EA -$

2015 Casing 1 EA -$

TOTAL - OPTION YEAR 2 -$

OPTION YEAR TWO

Bid Schedule (17-1014)

Option Year 2

3001 HSCI Iron Anodes w/200 #8 HMWPE 74 EA -$

3002 Graphite Anodes w/200 #8 HMWPE 16 EA -$

3003 HMWPE #4 Wire 270 LF -$

3004 Borehole / Drilling 2040 LF -$

3005 Coke Breeze 100lb bag 294 EA -$

3006 Bentonite Hole Plug 50 lb bag 110 EA -$

3007 Backfill 793 LF -$

3008 Anode Centralizers 164 EA -$

3009 Rectifier-LF (18V/16A) 9 EA -$

3010 Rectifier-MAF (48V/30A) 2 EA -$

3011 1" PVC Vent Pipe 2040 LF -$

3012 Mobilization 25 mile round trip 10 EA -$

3013 Mobilization Each additional 5 miles 286 EA -$

3014 Wyoming DEQ Inspection 1 EA -$

3015 Casing 5 EA -$

TOTAL - OPTION YEAR 3 -$

OPTION YEAR THREE

Bid Schedule (17-1014)

Option Year 3

4001 HSCI Iron Anodes w/200 #8 HMWPE 44 EA -$

4002 Graphite Anodes w/200 #8 HMWPE 8 EA -$

4003 HMWPE #4 Wire 210 LF -$

4004 Borehole / Drilling 1080 LF -$

4005 Coke Breeze 100lb bag 174 EA -$

4006 Bentonite Hole Plug 50 lb bag 60 EA -$

4007 Backfill 408 LF -$

4008 Anode Centralizers 88 EA -$

4009 Rectifier-LF (18V/16A) 7 EA -$

4010 Rectifier-MAF (48V/30A) 3 EA -$

4011 1" PVC Vent Pipe 1080 LF -$

4012 Mobilization 25 mile round trip 9 EA -$

4013 Mobilization Each additional 5 miles 220 EA -$

4014 Wyoming DEQ Inspection 1 EA -$

4015 Casing 8 EA -$

TOTAL - OPTION YEAR 4 -$

OPTION YEAR FOUR

Bid Schedule (17-1014)

Option Year 4